青海省黄河干流防洪工程(贵南县)施工组织设计目录1.总则·············································································-1-2.工程概述···········································································-2-3.施工总体部署··················································································-3-4.物资配备计划·················································································-8-5.施工方案··············································································-10-6.雨季施工技术措施··············································································-36-7.防汛度汛管理方案···········································································-38-8.工程质量管理方案···········································································-42-9.安全生产管理方案···········································································-49-10.工程进度管理方案·········································································-57-11.文明施工管理方案·········································································-63-12.环境保护管理方案·········································································-67-13.水土保持管理方案·········································································-69-14.农民工工资支付保证措施·····························································-70-15.施工总平面图布置说明·································································-72-附表一:拟投入本项目的主要施工设备表·········································-73-附表二:拟投入本项目的试验和检测仪器设备表·········································-74-附表三:拟投入本项目的劳动力计划表·······················································-75-附表四:施工进度计划网络图·····································································-76-附表五:施工总平面图···············································································-78-附表六:临时用地表··················································································-79-1、
青海省黄河干流防洪工程(贵南县)施工组织设计1、总则1.1编制说明本施工组织设计是依据本项目招标文件、施工设计图,按照国家颁布的现行施工质量验收规范、施工规程和有关工艺标准进行编制。编制原则是:为本工程项目施工阶段提供较为完整的指导性技术纲领,结合了工程实际地理环境等因素,在此基础上进行了强化细分,用以指导工程施工,确保优质、高效、低耗、安全、文明、保质、保量的完成该工程的建设任务。1.2编制依据1.2.1本工程施工设计图、招标文件。1.2.2本工程实地踏勘情况及调查咨询资料。1.2.3我公司的技术、机械设备装备情况及质量管理制度。1.2.4国家和行业有关部门颁布的现行设计规范、施工技术规程、规范、质量检验评定标准及验收办法。堤防工程施工质量评定与验收规程(试行)(SL239-1999)提防工程施工规范(SL260-98)水利水电建设工程规范(SL223-1999)提防工程设计规范(GB50286-98)水利水电工程测量规范(DLJ202-81、SLJ3-81)水利水电工程工程施工测量规范(SL52-93)水利水电工程施工质量评定规程(试行)(SL176-96)水工混凝土施工规范(SDJ207-82)硅酸盐水泥、普通硅酸盐水泥(GB175-92)施工现场临时用电安全技术规范(GBJ232-82)水利基本建设工程验收规程(SD184-86)(试行)《水利水电建设工程验收规范》SL223-2008《水利水电工程质量评定规程》(试行)SL176-1996《混凝土结构工程施工质量验收规范》GB50204-2002《混凝土质量控制标准》GB50164-92《砌体工程施工质量验收规范》GB50203-2002《建筑施工安全检查标准》(JGJ59-11)-78-
青海省黄河干流防洪工程(贵南县)施工组织设计2、工程概述2.1建设内容项目名称:青海省黄河干流防洪工程(贵南县)建设地点:贵南县沙沟乡主要工程内容:本工程为青海省黄河干流防洪工程—贵南段,位于贵南县沙沟乡。2.2项目区地理位置及建设规模贵南县在黄河右岸,左岸为兴海县和共和县,黄河干流在贵南县境内均为龙羊峡库区,自西南向东北流经塔秀乡、茫拉乡、沙沟乡。主要支流有茫拉河、沙沟。沙沟区居民和耕地比较集中。防洪形式迫切。在中小河流治理项目中分两期进行治理。2013年一期在沙沟乡至拉扎村段治理和长5.3Km,两岸防护长度10.17Km;2014年二期在过马营移民安置区段、沙沟乡郭勒村段和多石施工工期安排:2016年4月1日至2016年10月31日,总工期214天。2.3施工重点及难点本工程施工重点为格宾石笼网片及填石,难点为汛期施工的安全度汛。该工程施工经历汛期,且工程分布区域总体上为斜坡地形。因此汛期施工应统筹安排,确保汛期施工的安全,防止带来洪涝灾害。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计3、施工总体部署3.1施工指导思想3.1.1青海省黄河干流防洪工程(贵南段)施工过程中严格按照施工图设计及相关图纸进行施工,严格执行国家及现行有关规范及规程,每一个工序特别是隐蔽工程都需要作好相应的质量检查和验收工作,制定详细的质量保证体系。同时加强项目施工宣传,明确该工程的必要性和重要性。3.1.2施工中特别要做好临时排水工作,该工程需要在汛期施工,汛期对施工影响较大,施工中必须给予周密考虑,统筹安排,减少汛期对施工的影响,确保施工安全。3.1.3施工中配备足够的安全设施及制定抢险应急预案,并制定详细的安全技术保证体系。3.1.4本公司将根据工程情况选配高素质的项目经理组建项目管理班子,实施项目目标控制。积极推广应用新技术、新工艺、新设备、新材料,精心组织科学管理,优质高速地完成本工程的施工任务。3.2施工组织机构与职责3.2.1施工现场组织机构见图3.13.2.2项目管理人员岗位职责(1)项目经理①贯彻执行上级有关工程建设的方针政策及公司有关规定;②对工程项目的安全、质量、成本和进度全面负责;③制定并实施目标成本管理,组织高效文明施工;④组织施工设计的编写和工程验收;⑤落实安全生产责任制,组织安全检查,开展安全班组活动;⑥配合经营人员搞好工程决算及工程进度款的回收,对项目人员的工资进行合理分配;-78-
青海省黄河干流防洪工程(贵南县)施工组织设计⑦负责与建设、设计、监理单位协调解决与工程项目有关的各类重大问题。图3.1施工现场组织机构图预算员施工员质检护岸工程安全员提灌站工程材料堤防工程涵管工程项目经理技术负责人(1)技术负责人①贯彻执行国家施工规范、质量检验评定标准和公司质量体系文件、规章制度;②按照施工图纸、项目质量计划、施工组织设计的要求施工,实现本项目质量目标;③做好施工前向班组的技术交底;④及时填写施工日志和施工记录,具有可追溯性;⑤督促班组做好自检,及时进行工序交接和隐蔽工程、分项工程质量检验评定;(2)施工员①负责贯彻执行国家的技术法规、标准和上级的技术要求以及施工项目的技术管理工作;②组织有关人员熟悉图纸及招标文件,对图纸及施工中出现的问题,及时与设计单位、建设单位及监理单位协商解决并及时办理签证手续;-78-
青海省黄河干流防洪工程(贵南县)施工组织设计③组织施工方案的编制,并由有关技术人员贯彻落实,认真做好技术交底工作;④监督检查施工记录、材料试验记录及施工试验记录是否符合规范及有关规定,对可能出现的问题及时采取解决措施;⑤组织搞好质量体系运行,认真填写质量记录,保证质量体系在本项目运行有效;⑥参与工程验收。负责组织竣工报告编写及资料归档。(4)安全员①认真贯彻执行国家有关安全生产的法定政策及有关规定,制度现场安全生产制度,接受上级安全部门的业务指导;②负责组织新职工的安全教育和考试,定期对职工进行安全生产宣传教育,做好普测、考核、登记和上报工作;③开展安全生产检查,对查出的问题进行登记、上报并督促及时整改;④负责组织项目部的安全例会;⑤协助修订项目部安全管理制度,制定临时性危险作业的安全措施等;⑥经常检查职工执行安全生产规章制度的情况,及时查出“三违”行为,对于危及人员生命安全的重大隐患,有权停止生产,并立即报告领导。(5)质检员①负责组织实现公司质量目标,对施工过程中的各个工序严格把关;②负责对工程质量进行监督、检查、验收、评定,做好质量记录,整理归档;③负责理场材料检验和试验状态的标记。④-78-
青海省黄河干流防洪工程(贵南县)施工组织设计负责施工现场安全、文明施工生产管理,确保安全生产,负责现场施工、机具用电运行情况、生活用电、现场消防情况的督促和纠察工作,做好职工“三上岗、一讲评”活动,做好安全资料的收集整理和归档工作。(5)材料员①项目材料员认真执行物资管理制度,学习仓储管理知识,提高自身的业务素质和水平;②负责编制项目需用材料计划申请表,办理材料的使用和退库等工作;③在工地负责材料的管理和发放及临时采购材料的验收、入库等工作,严把材料验收关,及时填写质量记录;④建立各类物资台账及核算账簿,履行出入库手续;(6)预算员①负责提供施工组织设计和施工阶段所需的工料、机械的需用量数据信息。②负责项目工程预算成本、目标确切及计划统计月、季、年报的具体工作。负责项目月成本的汇总和核算工作。③参与投标文件、标书编制和合同评审,承担监督施工全过程合同和标书以外经济结果丢失责任。④熟悉图纸、参加图纸会审,提出问题,对遗漏未发现问题负责。⑤建好单位工程预结算及计划统计台帐,填报有关报表。3.3施工总体布置3.3.1施工组织的总体安排计划工期为214日历天,拟开工时间为2016年4月1日(具体开工时间以总监理工程师发出的开工通知为准),至2016年10月31日工程全部竣工。3.3.2施工现场布置根据施工现场实际情况,在施工总体布置时,充分考虑以下5个方面的因素:-78-
青海省黄河干流防洪工程(贵南县)施工组织设计①充分利用招标文件指定的承包商临时用地范围布置所需的施工营地、堆放防洪工程所需砂石等材料的备料场和预制场地,不破坏原有土层性状;如监理另有指示,则按监理指示调整施工场地。②临时设施布置尽量少占地,少砍伐树木(力争不砍伐),无拆迁。尽量减少临时工程的基础开挖及场地平整工程量;③场地布置既要便于工程施工,又不影响通过施工区域的供水、供电、通讯等公共设施的正常运行;④临时施工道路与现有施工区域道路的连接力求最短,以减少临时施工道路费用;⑤总体布置必须合理、可靠、实用、方便。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计4、物资配备计划4.1施工设备计划4.1.1机械设备计划本工程的设备进场计划安排,根据工程特点及工期安排分二个阶段进场:第一阶段:施工准备阶段进场设备:办公设备、挖掘机、风钻、自卸汽车等设备立即进场,开展场地准备及石方开挖工作。第二阶段:开工5日以后进场设备:土石方工程开始后,砂浆搅拌机、砼搅拌机、振捣器、风水枪、钢筋调直机、钢筋切断机、钢筋弯曲机、电焊机、对焊机蛙式打夯机及相关设备进场安装调试,投入使用。其他相关机械设备根据工程施工进度陆续进场详见附表“拟投入本项目的主要施工设备表(附表一)4.1.2检测设备计划本工程在施工过程期间,拟投入混凝土质量控制等检测仪器。各种试验仪器均有相关单位颁发的资质认证书,现场监理工程师审查批准。同时安排有实践经验的技术工程师做试验工作,并负责设备维护与维修等工作。测量仪器由专职测量人员负责使用、保管,使用时轻拿轻放,仪器使用后立即放入配套的仪器箱内,不能在工地上乱扔乱放,避免因碰撞和雨、雪、曝晒而造成误差。计划投入项目的试验和检测仪器设备见附表二。4.2主要材料准备4.2.1材料采购建立材料供应科,根据施工进度制定合理的材料供应计划,材料应具备合格证书及相关试验资料。项目部在材料的订购或自采加工之前,应取得监理工程师的同意,任何主材的采购未经监理工程师批准,不准用于工程施工。4.2.2材料的运输与贮存-78-
青海省黄河干流防洪工程(贵南县)施工组织设计①各类材料的搬运方式,均应保证其质量不受损坏、环境不受污染。运料的车辆运送应防止运送途中漏失和分离。②材料堆存以前,堆存场地应进行清理、平整、硬化与围砌。材料采用(水泥分批)分类堆放的贮存方式,并确保每月转堆一次,保证其质量的完好,不使其污染环境。4.3劳动力计划根据本工程施工内容,主要劳务人员可分为机械操作工、砼工、钢筋工、模板工、瓦工、水电工及普工。本工程施工中,各工种劳务人员应具有相应的工种培训班,且从事本工种至少有三年以上的经验。项目经理部对各劳务工种施工队应做到层层负责,层层分工,层层与经济效益挂钩,建立明确的奖励制度,由项目经理部对工程施工的各个环节制定相应的指标,并以此作为考核指标和奖惩依据。劳动力计划详见附表三:拟投入本项目的劳动力计划表-78-
青海省黄河干流防洪工程(贵南县)施工组织设计5、施工方案5.1施工准备5.1.1场地准备①项目部进入场地后,立即对业主交代的控制点进行复核,做好永久性控制点,处理现场的“三通一平”工作。对场地进行场平、作业区划分,对施工场地统筹规划,创造良好的施工条件准备施工。②场地清理,施工辅助道路、材料加工场、材料堆场及搅拌站等用C10素混凝土硬化,修筑材料仓库等,架设供电和供水管线,砌筑临时排水沟。③场地清理如发现异常情况(如文物、古迹、地下缆线等),立即通知发包人和监理工程师并按其指示处理。5.1.2材料准备若我方中标,项目部立即制定材料供应计划,联系材料供应商,确定运输方式,制定材料管理办法,建立完善的检测试验手段,把好材料质量关。同时做好并确定各种砼配合比。所有材料经自检合格,报监理工程师审批后,方可用于本工程。5.1.3设备准备针对本工程施工进度要求,各施工设备、机具应准备充分、预备潜能,并有充足的备用零配件和设备保养维修人员,保证机械的正常运转。5.1.4技术准备开工前,进入工地人员应做好以下各项技术准备工作:①接受发包人提供的现场控制点,组织复测。②协助发包人做好图纸会审和技术交底。③组织编写实施性施工组织设计。④组织编写各种针对性的保证措施。⑤组织内部技术交底和岗位培训。⑥熟悉图纸,准确理解设计意图。⑦编制各项质量管理和技术管理办法,备齐必要的参考资料。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计5.1.5交通疏导安排组织施工时应考虑尽量减少对现有交通的影响。当工程施工可能会干扰道路交通时,在道路上应设置必要的路障、警告信息等。5.2施工方案及工艺5.2.1施工测量放线(1)根据本工程特点对发包人提供的平面控制点成果和准高程点成果进行实地复测,无误并经监理工程师批准后使用才可引用。利用发包人提供的控制点,在场区按相当于二级导线的精度要求进行平面控制网布设施测量,测设出冲沟、截洪沟及截水坝等拟建工程的具体位置。(2)从发包人提供的准高程点成果按三等水准测量要求进行复测。复测结果在误差范围内才可应用,再在场区内按三等水准测量精度要求,测设数个水准基点,作为高程控制及变形观测用。水准基点标志的埋设要求稳固可靠,具体位置由测量工程师根据现场实际情况确定,三等水准观测的技术要求按现行规范执行。(3)根据设计或业主提供的控制坐标及水准点,在工程开工前由测量人员对施工项目进行统一的控制测量。控制测量经监理工程师审批后,下发各项施工队进行测量放线。各施工队及时用砂浆保护好测量控制桩,不得扰动和破坏,每次测量均需对各控制点进行闭合校核,测量资料经检查复核,报现场监理工程师审批后方可进行工程实施。(4)跟踪测量落实在工程施工的全过程中,利用已知导线控制网点严格按照设计和规范要求控制施工项目。(5)测量精度保证措施①严格执行工程测量规范。②严禁使用未经法定计量单位检定的仪器和计量工具。③所有测量数据反复检查,认真计算,测量成果表有仪器编号及测量人、计算人、审核人签名。④所有测量控制点的埋设必须可靠牢固。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计⑤测量控制点和水准点必须定期复测。5.2.2砂砾石开挖回填施工方案1、砂砾石开挖1.1施工条件现场临时道路通畅,已指定砂砾石堆场。本工程多余砂砾石全部外运1-4Km,砂砾石外运工程量必须算好回填的砂砾石量,回填砂砾石量留在厂内就近堆方,以方便回填。1.2施工进度计划本工程砂砾石开挖按总进度计划时间挖完,按1:0.5放坡进行砂砾石大开挖,最后清底、修边。1.3施工机具准备1m³反铲挖土机一台、6台5T的自卸汽车、全站仪一台、经纬仪一台、彩条布5卷、铁锹10把、50m卷尺一把、5m塔尺一把、蛙式打夯机3台。1.4施工人员安排技术负责人一名、技术员施工员各一名、安全员质检员各一名、测量放线人员2名、杂工10名。1.5基坑开挖综合考虑地质条件、周围环境、施工场地等诸方面因素,基坑放坡1:0.5进行开挖后,作好挡水台,以防雨水冲刷坡面形成塌方,影响施工进度和质量。由于本工程属于提标改造工程,故地下障碍物较多,在开挖之前,请甲方给我方交底,并进行4方会签后再进行砂砾石开挖作业。1.5.1基坑开挖方式本工程基坑开挖施工机械采用一台1m³反铲挖土机,6台5T的自卸汽车。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计基坑开挖采用施工机械大开挖,人工配合修边和清底,分层开挖,严禁一次开挖到底或超挖。开挖至设计标高经建设单位组织地基验槽后,立即做垫层,严禁将将基坑长时间暴露。开挖完成以后施工期间严禁在基坑边缘堆放15KPa以上重物或行走重型车辆。为避免开挖时搅动基底,机械开挖至底板垫层底标高底向上200mm,预留200mm土层人工挖除。1.5.2基坑开挖顺序砂砾石开挖按1:0.5放坡,自北向南、从上至下、分层开挖。2.5.3人员及机械安排1.5.2人员安排:测量人员2人,清槽人员5人。现场管理人员若干。1.5.3施工所用的主要机具:反铲挖土机一台、自卸汽车六台、铁锹、手推车、小白线、钢卷尺等。1.5.4砂砾石开挖具体要求砂砾石开挖前,应将施工区域内的地上、地下障碍物清除和处理完毕。砂砾石开挖前,应进行测量定位放线,并经验收合格后方可进行挖土。基坑周围做硬化地面,外围做排水沟,避免地面雨水流入基坑内。2、砂砾石开挖回填施工方案砂砾石开挖过程发现地下管线、电缆等情况应及时通知监理、业主,处理完后,再进行开挖。砂砾石开挖工程中应严格控制标高,防止超挖及欠挖。按要求预留200mm土层由人工进行清除。如果其它原因不能及时施工时,预留的200mm厚土层暂时不挖,待做基础时再挖。砂砾石开挖过程中,应对平面位置、控制边界线、坡度、标高等经常进行校核。开挖过程中机械严禁碰撞工程桩。砂砾石开挖自上而下分段分层进行,及时修整边坡,保持边坡稳定。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计在距基坑底设计标高50cm边坡处抄出水平线,钉上小木橛,然后用人工将预留土层挖走。同时引桩拉通线,检查距坑边尺寸,以此修整坑边,最后清除坑底砂砾石,做护坡。砂砾石开挖过程进行监测,发现位移过大时应立即停止开挖,待应急处理完后再进行开挖。砂砾石开挖后,应及时组织建设单位,设计单位,监理单位和勘察单位对地基工程进行验收、评定。验收合格后并及时进入下道工序,缩短基槽底暴露时间,防止扰动。2.1基坑的局部处理如果开挖砂砾石时,发现部分或者局部不满足设计及地勘的要求,应立即与相关方进行沟通,拿出处理方案进行地基的局部处理,如回填级配碎石等。2.2砂砾石回填2.2.1砂砾石回填准备砂砾石回填时,各构建筑物地下基础已经施工完成,包括各池体地面以下的防水防腐涂料施工完成。基坑里面清理干净不存在其他回落的松散垃圾、砂浆及石子等。回填时,基坑内应无积水、不得带水回填。不得回填淤泥等。2.2.2砂砾石回填材料砂砾石回填材料应选择粉质性粘土或者沙土(有机质含量不大于5%),并应符合最佳含水率的要求(夯实后的干重度不小于16KN/m³),粘性土应符合手捏成团,落地开花为宜,应为回填土过干,将夯打不密实,过湿则容易变成橡皮土。2.2.3砂砾石回填施工回填时从场地的最低端开始,由一端向另一端自下而上分层回填夯实。回填采用机械回填,并采用分层回填,每层回填厚度不大于-78-
青海省黄河干流防洪工程(贵南县)施工组织设计300mm,并进行分层夯实,夯实系数不小于0.94。在夯实或者压实后,应对每层回填土进行质量检查,检测采用环刀法进行取样送检,以保证回填土的夯实系数达到设计要求。在回填时应考虑天气的影响,防止雨雪天气对回填质量的影响。5.2.3钢筋工程1、钢筋工程,钢筋混凝土结构用的钢筋,其种类、钢号、直径等均应符合有关设计文件的规定。热轧钢筋的性能必须符合国家标准GBl499—84的要求。钢筋必须按不同等级、牌号、规格及生产厂家分批验收,分别堆存,不得混杂,且应立牌以资识别。在运输、贮存过程中应避免锈蚀和污染。钢筋宜堆置在仓库(棚)内;露天堆置时,应垫高并加遮盖。钢筋应有出厂证明书或试验报告单。使用前,仍应作拉力、冷弯试验。需要焊接的钢筋尚应作好焊接工艺试验。钢号不明的钢筋,经试验合格后方可使用,但不能在承重结构重要部位上应用。钢筋的调直和清除污锈应符合下列要求:1.1、钢筋的表面应洁净,使用前应将表面油渍、漆污、锈皮、鳞锈等清除干净。1.2、钢筋应平直,无局部弯折,钢筋中心线同直线的偏差不应超过其全长的1/6。成盘的钢筋或弯曲的钢筋均应娇直后,才允许使用。1.3、钢筋在调直机上调直后,其表面伤痕不得使截面面积减少5%以上。1.4、如用冷拉方法调直钢筋,则其短直冷拉率不得大于1%。在钢筋架设完毕,未浇筑混凝土之前,须按照设计图纸和本标书的标准进行详细检查,并作出检查记录。检查合格的钢筋,如长期暴露,应在混凝土浇筑之前,按上述规定重新检查,合格后方能浇筑混凝土。在钢筋架设安装后,应及时妥善保护,避免发生错动和变形。在混凝土浇筑施工中,应安排值班人员经常检查钢筋架立位置,如发现变动应及时矫正。严禁为方便浇筑擅自移动或割除钢筋。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计钢筋连接采用对接,局部采用绑扎,焊接时应避免虚焊、假焊。绑扎应绑扎牢固,避免滑动、移位。钢筋表面要求清除干净,搭接长度应满足钢筋工程的规范要求。具体如下:5.2.4混凝土工程1、准备工作浇筑前除对作业人员再次进行浇筑工序、安全教育、技术要求交底外,尚须注意:1检查模板支撑支架是否牢固可靠,几何尺寸是否与设计相符。②检查钢筋绑扎数量与质量是否和设计一致。2检查模板是否足够并安装正确牢固。3调配好施工配合比。4检查设备器具是否完好正常。5检查预埋件、预埋套管是否有错埋,漏埋。⑦浇注范围内异物、积水是否清除干净。以上准备工作若未经监理工程师签认不许浇筑砼。2、材料的准备和检验①水泥:水泥品质应符合现行的国家标准及有关部颁标准的规定。水泥品质的检验,按现行的国家标准进行。水泥的运输、保管及使用,应符合下列要求:a.水泥的品种、标号不得混杂。b.运输过程中应防止水泥受潮。c.大、中型工程应专设水泥仓库或储罐。水泥仓库宜设置在高燥地点并应有排水、通风措施。d.堆放袋装水泥时,应设防潮层,距地面、边墙至少30cm,堆放高度不得超过15袋。e.袋装水泥到货后,应标明品种、标号、厂家、出厂日期,分别堆放,并留出运输通道。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计f.先到的水泥应先用。水泥储运时间超过三个月、或者对水泥质量有怀疑,应重新检验,不合格者不得使用。g.避免水泥的散失浪费,注意环境保护。②骨料若自行开采,骨料的料源,在开采前应进行详细的补充勘察。同时,应根据技术经济比较,拟定使用平衡计划,避免产生过多弃料。冲洗、筛分骨料时,应控制好筛分进料量、冲洗水压和用水量、筛网的孔径与倾角等,以保证各级骨料的成品质量符合要求,尽量减少细砂流失。人工砂生产中,应保持进料粒径、进粒量及料浆浓度的相对稳定性,以便控制人工砂的细度模数及石粉含量。骨料的堆存和运输应符合下列要求:a.堆存骨料的场地,应有良好的排水设施。b.不同粒径的骨料必须分别堆存,设置隔离设施,严禁相互混杂。c.应尽量减少转运次数。粒径大于40毫米的粗骨料的净自由落差不宜大于3m,超过时应设置缓降设备。d.骨料堆存时,不宜堆成斜坡或锥体,以防产生分离。e.骨料储仓库有足够的数量和容积,并应维持一定的堆料厚度。砂仓的容积、数量还应满足砂料脱水的要求。f.应避免泥土混入骨料。砂料的质量技术要求如下:a.砂料就质地坚硬、清洁、级配良好;使用山砂、特细砂,应经过试验论证。b.砂的细度模数宜在2.4~2.8范围内。天然砂料宜按粒径分成两级,人工砂可不分级。c.砂料中有活性骨料时,必须进行专门试验论证,保证不含有害物质。d.其他质量技术要求应符合有关规定。粗骨料的质量技术要求如下:-78-
青海省黄河干流防洪工程(贵南县)施工组织设计a.粗骨料的最大粒径:不应超过钢筋净间距的2/3及构件断面最小边长的1/4:素混凝土板厚的1/2。对少筋或无筋结构,应选用较大的粗骨料粒径。b.施工中,宜将粗骨料按粒径分成下列几个粒径级:当最大粒径为40mm时,分成5—20和20—40mm两级;当最大粒径为80mm时,分成5~20,20~40和40~80mm三级;当最大粒径为150(或120)mm时,分成5~20,20—40,40~80和80~150(或120)mm四级。应严格控制各级骨料的超、逊径含量,以标准孔筛检验,其控制标准:超径<5%,逊径<10%。当以超、逊径筛检验时,其控制标准:超径为零,逊径<2%。采用连续级配或间断级配,应由试验确定。如采用间断级配,应注意混凝土运输中骨粒的分离问题。粗骨料中含有活性骨料、黄锈等,必须进行专门试验论证。粗骨粒力学性能的要求和检验,可按国家标准《普通混凝土用碎石或卵石质量标准及检验方法》(JGJ53—92)中的有关规定进行。③水:凡适于饮用的水,均可用以拌制和养护混凝土。未经处理的工业污水和沼泽水,不得用以拌制和养护混凝土。天然矿化水,如果化学成分符合规定,可以用来拌制和养护混凝土。④外加剂:a.砼中外加剂的掺入必须通过试验确定经工程师代表书面同意后方可使用。b.外加剂必须与水混合配成一定浓度的溶液,各种成分用量应准确。对含有大量固体的外加剂(如含石灰的减水剂),其溶液应通过0.6mm孔眼的筛子过滤。c.外加剂溶液必须搅拌均匀,并定期取有代表性的样品进行鉴定。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计d.当外加剂贮存时间过长,对其质量有怀疑时,必须进行试验鉴定,严禁使用变质的外加剂。⑤配合比a.为确保混凝土的质量,工程所用混凝土的配合比必须通过试验确定。b.坍落度粗骨粒级配及砂率的选择,应考虑骨料生产的平衡、混凝土和易性及最小单位用水量等要求,综合分析确定。混凝土的坍落度,应根据建筑物的性质、钢筋含量、混凝土的运输、浇筑方法和气候条件决定,尽可能采用小的坍落度。混凝土在浇筑地点的坍落度可参照下表的规定。c.混凝土配比设计的基本准则:施工技术主管部门批准,在施工过程中,如有原则性变动,亦应由该部门批准。混凝土拌和时,必须严格遵守试验室签发的混凝土配料单进行配料,严禁擅自更改。水泥、砂、石、混合料均应以重量计,水及外加剂溶液可按重量折算成体积。称量的偏差,不应超过下表中规定的数值。5.2.5模板工程(1)模板材料的选用:选用钢模板,以保证混凝土观感质量。(2)模板工程应保证:①结构平面位置准确,各构件接头尺寸及相关位置正确。②有足够的强度、刚度和稳定性,能可靠地承受新浇混凝土的重量或侧压力以及施工过程中的施工荷载。③装拆方便,便于钢筋绑扎。④模板平整度、垂直度应符合本工程的合格等级要求,接缝严密。⑤模板制作要尽可能整个工程通用,节约用材。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(3)模板安装①按图纸设计断面尺寸配模。②模板安装和浇筑砼时,对模板及其支架进行观察和维护,发生防止隔离剂沾污钢筋和砼接槎处。③模板安装前与砼的接触面清理干净,涂刷模板隔离剂,并防止隔离剂沾污钢筋和砼接槎处。④模板安装质量要求:模板的接缝不漏浆;在浇筑砼前,木模板浇水湿润,并清除模板内的杂物;保证砼构件的几何尺寸;模板安装偏差满足新规范要求。⑤按高计要求对砼模板起拱,对每根构件均拉线检查。⑥不遗漏固定在模板上的预埋件、预留孔和预留洞,安装牢固,其偏差满足新规范要求。(4)模板拆除在混凝土强度能保证其表面及棱面不因拆除模板而受损害后,对模板进行拆除。模板拆除不能用硬物使劲敲打和撞击,特别是安装了拉杆和传力杆时,要小心拆卸,避免拉杆和传力杆松动5.2.6格宾石笼网工程1、格宾石笼材料及制作技术要求格宾网箱的材料锌-5%铝-混合稀土合金镀层合金钢丝,钢丝材质为合金钢丝(不得采用一般低碳钢丝)。镀层重量≥245g/㎡,石笼尺寸大小为3m*1m*0.4m,网孔尺寸为80mm*100mm,网丝采用2.7mm,边丝3.4mm,绑丝2.2mm;脚槽及水平防护格宾笼网线开孔尺寸为130mm*150mm.。格宾网片网孔须均匀,不得扭曲变形,网孔孔径偏差应小于设计孔径的5%。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计钢丝缠绕标准:网面裁剪后末端与端丝的连接处是整个结构的薄弱环节,为加强网面与端丝的连接强度,采用专业的翻边机将网面钢丝缠绕在端丝上≥2.5圈,不能采用手工绞,翻边强度21KN/m。网片强度不小于35KN/m。格宾石笼半成品到工地时附有钢丝等材料的原厂质量证明书,施工单位对材料按照设计技术要求检测合格后用于工程。格宾石笼中填充料可采用天然块石或卵石,填筑应具有耐久性好、不易碎、无风化迹象、遇水不宜崩解和水解,填石的饱和抗压强度不小区30MPa,填料的中值粒径宜介于1.5D-2.0D之间,最大粒径不超过300mm。格宾石笼施工首先从堤防、护岸及提灌站两侧开始,自下而上垒筑河道边坡。成品格宾石笼按设计图首先就位后再填充石料,格宾石笼在搬运和填充石料过程中小心轻放,避免损坏格宾网铝锌钢丝外表防腐涂层。石材垒砌时外立面摆放平整、美观。2、格宾石笼施工工艺2.1机械、设备及材料准备2.1.1施工机械(包括运输、挖掘、碾压、排水、基础处理等机械)、施工工具(包括绑扎、连结、夯实、维修等工具)、设备(包括水、电等设备)及材料(网材、块石等建筑材料)的型号、规格、技术性能应根据工程施工进度和强度合理安排与调配。2.1.2根据工程施工进度应及时组织材料进场,并应事先对原材料和半成品的质量进行检验。2.1.3进场原材料和半成品必须经检验合格后,方可使用。2.2宾格网箱施工2.2.1一般规定(1)基槽基底土质及其密实度,基础层网箱入土深度和轮廓线长度及宽度,均符合设计要求。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(1)现场如遇较差地基土质时,在做好地基处理,处理后的地基承载力符合设计要求后再进行格宾网施工。(2)网箱砌体符合下列要求:①网箱砌体平面位置须符合设计图纸要求;②层与层间的网箱或网箱组宜纵横交错叠砌,上下联结,严禁出现“通缝”;③每层网箱摆放适当放置“丁”字箱体。④砌体外露面宜人工铺砌整平,保证美观。(3)组装网箱时,绑扎用的组合丝、水平固定丝须与网丝(编织网片用的钢丝)同材质。(4)钢丝缠绕标准:网面裁剪后末端与端丝的连接处是整个结构的薄弱环节,为加强网面与端丝的连接强度,采用专业的翻边机将网面钢丝缠绕在端丝上≥2.5圈,不能采用手工绞,翻边强度21KN/m。(5)单元网箱间连接绑扎,符合下列要求:①相邻单元网箱的上下四角各一道组合丝绑扎;②相邻单元网箱的上下框线或折线,须采用组合丝连接;③相邻单元网箱的网片结合面每平米绑扎2处;(6)裸露部位的网箱,设置水平固定丝,水平固定丝在每层石料填放、铺平后设置。水平固定丝可以分为两种。一种是八字形拉筋,即水平及垂直间距为25cm~35cm,呈八字形向内与边网片或临土面连结并拉紧固定。另一种为前后面对拉筋,拉筋可以为单根拉筋。2.2.2填充料施工(1)网箱的填充料规格质量,必须符合设计及标准要求。(2)网箱投放填充料前,为保证网箱裸露面的平整度,应在网箱裸露面绑扎竹竿、木棒、面板等,待填充料施工结束后拆除。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(1)须依次、均匀、分层的向同层的各箱格内投料,避免出现一次性填满单格网箱。(2)填充料施工中,应控制每坯投料厚度在30cm左右,一般0.9米高网箱分三、四层投料为宜。(5)填充料顶面宜适当高出网箱上部表面。(6)结构体容重≧1.80T/m3。(7)裸露面的填充料,必须人工砌垒整平,填充料间应相互搭接。2.2.3箱体封盖施工(1)封盖在顶部填充料铺砌整平的基础上进行。(2)必须先使用封盖夹固定每端相邻结点后,再加以绑扎。(3)封盖与网箱边框相交线,应每相隔10-15cm绑扎一道。3、质量控制1)一般规定①、建立健全完整的质量保证体系,严格执行质量“三检”制度及工序报验制度,实行全面质量管理。②、工程质量检测人员所需资质条件以及工程质量检验的职责范围、工作程序、事故处理、数据处理等要求,均应符合相应质量验收规范的规定。③、应保证检测成果、材料检验资料的真实性,严禁伪造或任意舍弃成果和资料;质量检测记录应妥善保存,严禁涂改或自行销毁。④、格宾防护工程质量应包括内在质量和外观质量。⑤、质量检测部位应有代表性,且应在上面均匀分布,不得随意挑选。⑥、隐蔽工程应会同监理一起检验,作好声像资料留存。2)材料质量控制(1)、格宾网的规格质量应重点检查下列内容:①、用于编织格宾网的材料的化学性能、力学指标是否符合-78-
青海省黄河干流防洪工程(贵南县)施工组织设计设计要求;②、网孔孔径是否符合设计及规范允许偏差要求;③、外涂树脂薄膜质量是否符合设计及规范要求。(2)、填充料的质量及规格应重点检查下列内容:①、填充料的质量是否符合设计及规范规定;②、填充料的粒径是否符合设计及规范规定。(3)、土工织物的质量控制,应重点检查下列内容:①、透水土工织物的质量和规格是否符合设计要求;②、防渗土工织物的质量和规格是否符合设计要求。3、安全控制1)加强施工作业人员安全教育,对作业人员作业进行安全技术交底。2)水下作业人员必须是具有专业资质的水下作业人员,在进行涉水作业时应配戴救生用具,同时在作业面外侧江面配备应急救援船只,在进行水下作业时应配备专人指挥。3)操作平台及外侧防护栏杆搭设应牢固,并在作业前进行经常性检查。4)平台作业人员与水下作业人员不得在同一垂直面上作业,水上水下需同步作业时,需错开一段距离。5)坡面下料时要防止卵石滚落伤人。当使用机械配合施工时要防止机械伤人。4、工程验收格宾石笼网工程施工完成后及时完成水下成像记录资料,检查装填质量及封盖质量,经检查符合要求后即可进行隐蔽验收,以利及时进行水上格宾护坡及相应工序施工。水下隐蔽工程验收可分段进行,完工一段验收一段。前道工序未经验收,不得进行下一道工序施工。整个堤防、护岸分部工程施工完毕后即可进行分部验收。5.2.7土工布施工方案-78-
青海省黄河干流防洪工程(贵南县)施工组织设计1、施工要点:(1)土工布的施工工艺为:平整场地——织物备料——铺设——回填和表面保护(2)平整碾压场地,清除地面一切可能损伤土工布的带尖棱硬物,填平坑凹,平整土面,或修好坡面。(3)备料。按工程要求裁剪、拼幅;避免土工布被损伤,保持其不受脏物污染。(4)铺设符合下列要求:①铺设时,互相配合,土工布力求平顺,松紧适度,防止崩拉过紧。土工布与土面密贴,不留空隙。②发现土工布有损,立即修补或更换。③相邻土工布拼接使用搭接或缝接。一般情况采用搭接。平地搭接宽度为30cm,不平地面或软土不小于50cm。④搭接处上游土工布盖在下游块之上。⑤坡面铺设顺序为自下而上。坡顶、坡脚按设计要求进行锚固。⑥铺设工人穿软底鞋进行作业,避免损伤土工布。⑦土工布铺好时,避免受日光照射。随铺随填。⑧与岸坡结构物连接处,不留空隙,结合良好。5.2.8块石回填工程:1、检验块石质量→分层铺筑块石→洒水晾晒)→夯实或振捣(平板振动器)→找平验收2、对块石进行技术鉴定,如是人工块石,应将块石拌合均匀,其质量均应达到设计要求或规范的规定。3、分层铺筑块石3.l铺筑块石的每层厚度,一般为15~20cm,不宜超过30cm,分层厚度可用样桩控制。视不同条件,可选用夯实或压实的方法。大面积的块石垫层,铺筑厚度可达35cm。3.2块石地基底面宜铺设在同一标高上,如深度不同时,基土面应挖成踏步和斜坡形,搭槎处应注意压(夯)实。施工应按先深后浅的顺序进行。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计3.3分段施工时,接槎处应做成斜坡,每层接岔处的水平距离应错开0.5~1.0m,并应充分压(夯)实。3.4铺筑的块石应级配均匀。如发现石子成堆现象,应将该处块子或石子挖出,分别填入级配好的块石。4、洒水铺筑块石在夯实碾压前,应根据其干湿程度和气候条件,适当地洒水以保持块石的最佳含水量,一般为8%~l2%。5、夯实或碾压夯实或碾压的遍数,由现场试验确定。用水夯或蛙式打夯机时,应保持落距为400~500mm,要一夯压半夯,行行相接,全面夯实,一般不少于3遍。边缘和转角处应用人工或蛙式打夯机补夯密实。6、找平和验收:6.l施工时应分层找平,夯压密实,并应设置纯块检查点,用200cm3的环刀取样;测定干块的质量密度。下层密实度合格后,方可进行上层施工。用贯入法测定质量时,用贯入仪、钢筋或钢叉等以贯入度进行检查,小于试验所确定的贯入度为合格。6.2最后一层压(夯)完成后,表面应拉线找平,并且要符合设计规定的标高。5.2.9砂砾石路面工程1、试验路段:面层开工前3天,向工程师递交一份完整施工方案的书面说明。通过试验路段确定施工机械组合、松铺厚度、施工方法及碾压遍数。试验段能满足设计要求后,写出试验段总结,打开工报告,经监理工程师批准后,才可进行天然砂砾石的施工。砾石的最大粒径不应超过37.5mm,浸水4天的CBR值不小于160%,压碎值应不大于35%,扁平颗粒含量不大于20%。(1)工艺流程:检验砂石质量→分层铺筑砂石→洒水→夯实或碾压→找平验收-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(1)对级配砂石进行技术鉴定,如是人工级配砂石,应将砂石拌合均匀,其质量均应达到设计要求或规范的规定。(2)分层铺筑砂石1)铺筑砂石的每层厚度,一般为15~20cm,不宜超过30cm,分层厚度可用样桩控制。视不同条件,可选用夯实或压实的方法。大面积的砂石垫层,铺筑厚度可达35cm,宜采用6~10t的压路机碾压。2)砂和砂石地基底面宜铺设在同一标高上,如深度不同时,基土面应挖成踏步和斜坡形,搭槎处应注意压(夯)实。施工应按先深后浅的顺序进行。3)分段施工时,接槎处应做成斜坡,每层接岔处的水平距离应错开0.5~1.0m,并应充分压(夯)实。4)铺筑的砂石应级配均匀。如发现砂窝或石子成堆现象,应将该处砂子或石子挖出,分别填入级配好的砂石。5)洒水:铺筑级配砂石在夯实碾压前,应根据其干湿程度和气候条件,适当地洒水以保持砂石的最佳含水量,一般为8~12%。6)夯实或碾压;夯实或碾压的遍数,由现场试验确定。用木夯或蛙式打夯机时,应保持落距为400~500mm,要一夯压半夯,行行相接,全面夯实,一般不少于3遍。采用压路机往复碾压,一般碾压不少于4遍,其轮距搭接不小于50cm。边缘和转角处应用人工或蛙式打夯机补夯密实。2、质量要求材料必须符合规范规定,碾压应先轻后重,先慢后快,洒水碾压至要求的密实度。垫层表面平整度密实,边线整齐,无松散现象。3、施工控制要点标高、砂砾质量、宽度、压实度、平整度、中线、横坡。5.2.10土地平整工程1.1技术准备工作1.1.1技术交底-78-
青海省黄河干流防洪工程(贵南县)施工组织设计工程开工前,项目经理部积极邀请设计单位代表、建设单位代表和监理工程师对设计文件进行会审,就设计标准及施工技术要求进行探讨,针对施工中应注意的事项提出具体意见,进一步完善技术交底工作。1.1.2施工放样在开工前,根据发包人和监理工程师提供的测量基本控制点、基线、水准点、测量标志和建设单位提供的图纸,按照有关规定及要求,校测其基本控制点和基线的测量精度,复核其资料和数据的准确性。用经纬仪、水准仪对本标段各单项工程及取土范围进行现场测量放样,标明轮廓,打桩并撒上白灰线。我方会按照本工程施工测量精度要求,负责施工所需要的全部施工测量放线工作。基线相对于邻近基本控制点,平面位置控制误差在50mm以内,高程控制误差±30mm以内。测量放线时,邀请监理工程师、建设单位驻工地代表和设计代表参加。测量后,整理测量记录资料按顺堤每50m为一断面绘制断面图,核算出工程量,将成果提交监理工程师审核。1.1.3表土清理开挖前将表层的杂质、植物根系及稀软淤土清除。工程施工前首先用人工挖除遗留树根,装车运至指定地点。表土清理采用土方清表采用推土机推运,配合10t自卸车施工,清基土方运至监理工程师指定的地点。清理时边界清理到开挖边线40cm外,清理深度不少于30cm。1.2土地平整施工流程施工准备→按设计图纸→分格田设计平整高程测量放样→田间施工便道布置→机械进场→沿渠道流向→,机械剥离土耕作→在格田内集体堆放耕土层→平整格田→若新造田块缺少覆耕作土,则翻松处理→验收表土耕作层加覆→复核平整后的格田高程1.2.1施工方法-78-
青海省黄河干流防洪工程(贵南县)施工组织设计⑴、测量放样:根据设计单位提供的坐标控制点及水准测量点,定出平整开挖区域和填筑区域,根据测量结果和设计图纸进行土方平衡计算,制定合理的土方调度方案。如存在较大差错时,应邀请建设单位及设计单位进行协调,研究解决方案,如有较大变更设计,应按国土资源厅规定的变更程序进行变更。高程复核完后,应对该田块底层基础进行检查,看田块耕作层底下是否为砂漏地或淤泥,如是应及早进行协调,保证施工机械及人员的安全和耕作侧防渗能力。⑵、土方平整施工:用推土机推土,配合人工挖土方机动翻斗车运输。考虑平整区域内的土方平衡,在推土机推土前,对开挖区域内的树桩、树根、杂草、垃圾、废渣等有碍物利用机械结合人工彻底清除,然后先把表层原田面耕作土用推土机分两层推土剥离后,堆放在格田内,暴雨时需用塑料布遮盖,避免暴雨淋刷使土壤大量流失。表面剥离后,再用平地机进行细平工作,局部高差较大处,由铲运机铲运土方回填,尽量做到挖填同时进行,格田平整后高程符合设计要求。平整时应采取就近原则,挖取高于设计田面标高的土方回填至附近低于设计田面标高田块,开挖及回填时应保证表土回填前田块有足够的保水层。防止表土层底部为漏水层,在施工时应注意田面高程的控制。并按照设计要求用机动翻斗车运土,推土机配合平整进行了耕作层回覆,新造田表土翻松则用推土机的松土器进行耙松处理。1.3格田土方平整施工-78-
青海省黄河干流防洪工程(贵南县)施工组织设计考虑平整区域的土方平衡,在推土机推土前,对开挖区域内的树桩、树根、杂草、垃圾、废渣等有碍物利用机械结合人工彻底清除,然后先把表层原田面耕作土25cm用推土机分两层推土剥离后,堆放在格田内,暴雨时需用塑料布遮盖,避免暴雨淋刷使土壤大量流失。表土剥离后,再用平地机进行细平工作,局部高差较大处,由铲运机铲运土方回填,尽量做到挖填同时进行,格田平整后高程符合设计要求。平整时应采取就近原则,挖取高于设计田面的土方回填前田块有足够的保水层。防止表土层底部为漏水层,在施工时应注意田面高程的控制。并按照设计要求用铲运机运土,推土机配合平整进行耕作层回覆,新造田表土翻松则用推土机的松土器进行耙松处理。田埂施工,表土恢复监理验收合格后,按设计要求进行田埂施工;田埂施工;田埂夯筑要顺直,防止漏水,在田埂内侧用粘性土涂抹夯实,放水试蓄。田埂外侧应选择粘性较强的土壤,逐层压实后修坡,拍打结实。1.4新材料、新技术、新工艺的应用现代管理技术与计算机应用,应用工程网络计划控制工期,采用微机对计划、技术资料、成本等进行施工全过程管理。重点控制好主要施工阶段管理各施工阶段管理,做好分区部位施工流水段划分及流水施工。集中优势人力、物力、财力进行连续施工,组织“快速”轮流作业队伍。加大工程施工的投入,使工程施工进度合理、有效尽量提前,为后续施工创造条件。在施工过程中全方位、全过程都要严格坚持各工序规范施工,混凝土浇灌办许可证和隐蔽验收。做好竖向稳步有序流水递进的施工管理,严格控制总工期,加强施工进度管理,严格坚持施工中的高标准、严要求、不合格立即返工决不放行的原则。严格坚持施工规范规程操作,克服管理和操作一般化,严格坚持正确程序,杜绝打乱仗现象,形成有统筹的良性循环局面,狠抓质量通病的防治。把质量目标管理落实到合同管理中来,将方针目标分解到各专业。编制好具有可操作性的并能指导各专业穿插施工作业的进度计划,保证各专业有序施工。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计在施工过程中,加强总体质量控制和细部处理完善保证成品质量观感良好,严格坚持治理质量通病保证一次成功,防止交叉污染,注重成品保护等施工管理。收尾施工管理工程进入收尾阶段工作重点是作好交叉施工、成品保护、竣工资料的整理并为工程验收做好一次详细质量自评。施工的主要工序作业效率的高低决定工期快慢的最重要因素,所以我公司决定在本工程中投入高效率新技术手段提高施工速度,确保工期目标的实现。根据本工程的结构特点、质量、工期等方面的要求,只有采用先进的施工技术和科技保证,才能实现优质、快速的承诺。5.2.11植物措施工程一、建植前的准备1.场地清理①建坪前应将40厘米厚的表土层进行耕翻、疏松、过筛处理、清除草根、草茎及碎石等杂物;②对于土质较差或者含有垃圾较多或其他污物众多的区域应将40厘米的表土层全部拖走,另换成土质较好的沙壤土或种植土。2.杂草处理杂草较少的区域直接将草根连根拔起清除即可,对杂草密集或大面积有杂草的区域可用化学方法进行灭杀,除草剂用量及使用时间因除草剂品种而异,使用时按其说明书操作。3.松土对清理干净后的土壤进行翻新,一是可再次确认地下有无妨碍草坪生长的杂物,二是有利于后续工作的开展。4.施肥①有机肥:为提高土壤肥力,结合场地清理时施入有机肥料作底肥,以保证草坪的长效性。A有机肥料种类:堆肥、牛粪、人粪尿鸡粪等;B施肥量:经充分腐熟的有机肥料每亩施肥量为2500~3000千克;C施肥方法:将已腐熟的有机肥料打碎、过筛、除杂,均匀施入土壤中。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计②无机肥与土壤改良剂:根据土壤检测的结果,有针对性的施入无机肥和土壤改良剂,以调节土壤中化学元素的平衡状态,达到适合植物生长的土壤酸碱度。A无机肥作基肥施用量:碳酸氢铵10千克每亩,过磷酸钙10~15千克每亩;B土壤改良剂:视土壤实际情况施用,如:泥炭土、腐熟的锯木屑、渣肥土等;5.防虫检查土壤内有无害虫情况,若严重,在场地清理后结合施肥,同时施入适量农药,灭杀地下害虫,保护新草坪草根。6.土壤整形对即将新植入草坪的场地进行土壤整平,并保持0.3~0.5%的排水坡度。7.表层种植土土壤整形后,在土壤上种植10cm适合草坪等植物生长的种植土。二、草坪的移植1.草源选择应选择生长健壮且无病虫害的草源,草根部做好多带些素土,铺砌草块前应将草块堆放在阴凉处,堆入要薄,并且经常喷水保持草根部湿润。2.草皮规格草皮规格尺寸宜为30cm×30cm的正方形草皮,厚度宜为3~5cm适宜。3.草皮铺砌①草皮移植前24小时修剪并喷水,镇压保持土壤湿润,较好起草皮;②将草皮块铺植于土壤之上,块与块之间留1~2指宽的缝隙;-78-
青海省黄河干流防洪工程(贵南县)施工组织设计③草皮移植后,用轻型碾压机(0.27t)压平,也可用圆筒或人工脚踩,使草皮与土壤结合紧密,无空隙,易于生根,保证草皮成活率;④草皮压紧后浇第一遍透水,保证坪床5—10cm湿润,使草皮恢复原色或失水不易过多,之后每隔3—4天浇一次水,以保证草皮的需水量。;⑤草皮压紧后浇第一遍透水,保证坪床5—10cm湿润,使草皮恢复原色或失水不易过多,之后每隔3—4天浇一次水,以保证草皮的需水量。⑥保证滚压和浇水,直到草皮生根而转到正常的养护管理。三、草坪施工后的养护管理1.灌溉草坪植物不能缺水,草坪施工后应及时灌水。在气温过高或降雨量偏少时必须进行人工灌溉或喷灌,喷灌时水速不要超过土壤渗水的速度,应避免坪表积水。①灌水时间:草坪施草缺水使会表现不同程度的萎恹,当表层土10~15厘米的土壤变干呈浅白色,此时要灌水,一般以黄昏和清晨为浇水的最佳时间。②灌水量:草坪的灌水应取决于耗水量。为保证草坪草的正常生长,对新植草坪除雨季外,每周浇水2-3次,水量要足,土壤湿润到地下20厘米时,草坪生长就有足够的水分供应。2.施肥为使草坪草生长茂盛,颜色鲜绿、覆盖度好,应根据草坪草的长势情况增施氮、磷、钾肥。5.2.12环境保护措施工程1、井池砌筑施工方法1)施工准备-78-
青海省黄河干流防洪工程(贵南县)施工组织设计混凝土的碱含量应符合《混凝土碱含量限值标准》的规定,当环境类别为Ⅱ类b时,混凝土强度等级为C25,最大水灰比为0.55。混凝土中可根据强度适当采用外加剂,采用外加剂时,执行《混凝土外加剂应用技术规范》(GB50119-2003)的有关规定。膨胀剂的选择须经设计单位确定。(1)明挖管道铺设接口强度达到设计强度80%;(2)选定好砂、石子、水泥、砖、钢筋等原材料,送样到试验室作原材料试验,依据图纸要求进行试配,现场按照试验室提供的配合比根据现场砂石含水量确定施工配合比。1)井体砌筑施工方法(1)井底基础与管道基础同时浇筑。(2)流槽一定与井壁同时砌筑。表面用砂浆分层压实抹光,流槽与上下游管道接顺,管内底高程符合混凝土管道基础及安装的允许偏差。(3)砌筑井室,用水冲净基础后,先铺一层砂浆,再压砖砌筑,做到满铺满挤,砖与砖间灰缝保持1cm。(4)与井体接连的所有管道端头,要经过凿毛处理并要清理干净,保证管道与阀门井井壁结合牢固。(5)砂浆拌合均匀,保证砌筑砖含水量为10~15%,砌体不得有竖向通缝,必须为上、下错缝,内外搭接。如井身不能一次砌完,在二次砌筑时,将原砖面上的泥土杂物清理干净,然后用水清洗砖面并浸透。(6)砖砌圆形阀门井时,随时检测直径尺寸,当需要收口时,如为四面收进,则每次收进不大于30mm;如为三面收进,则每次收进不大于50mm。砌筑井的内壁应用原浆勾缝,有抹面要求时,内壁抹面应分层压实,外壁用砂浆搓缝并严实。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(7)井体接入圆管的关口应与井内壁平齐,当接入管径大于300mm时,砌砖圈加固。管子穿越井室壁或井底,留有30~50mm的环缝,用油麻-水泥砂浆,油麻-石棉水泥或粘土填塞并捣实。(8)砌筑井内踏步时,随砌随安,位置正确。踏步安装后,在砌筑砂浆或混凝土未达到规定抗压强度前不得踩踏。混凝土井壁的踏步在预制或现浇时安装。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计6、雨季施工技术措施6.1总则6.1.1进入雨季,应提前做好雨季施工中所需各种材料、设备的储备工作。6.1.2项目部要根据所承建工程项目的特点,编制有针对性的雨季施工措施,并定期检查执行情况。6.1.3施工期间,施工调度要及时掌握气象情况,遇有恶劣天气,及时通知项目施工现场负责人员,以便及时采取应急措施。6.1.4施工现场道路必须平整、坚实,两侧排水设施流畅,主要路面铺设矿渣、砂砾等防滑材料,重要运输路线必须保证循环畅通。6.1.5对不适宜雨季施工的工程要提前或暂缓安排,土石方工程、混凝土工程等雨季不能间断施工的,要调集人力组织快速施工,尽量缩短雨季施工时间。6.1.6根据“晴外、雨内”的原则,雨天尽量缩短室外作业时间,加强劳动力调配,组织合理的工序穿插,利用各种有利条件减少防雨措施的资金消耗,保证工程质量,加快施工进度。6.1.7所有机械的操作运转,都必须严格遵守相应的安全技术操作规程,雨季施工期间应加强教育和监督检查。6.1.8各单项工程施工现场要组织防汛小组,遇有汛情及时、有组织地进行防汛。6.1.9各作业人员要注意防滑、防触电,加强自我保护,确保安全生产。6.2雨季施工技术措施6.2.1土石方工程、混凝土工程雨季施工措施①雨季进行土石方与混凝土工程时,要编制切实可行的施工方案、技术质量措施和安全技术措施,土石方开挖前备好水泵。②-78-
青海省黄河干流防洪工程(贵南县)施工组织设计雨季施工,人工或机械挖土石方时,必须严格按规定放坡,坡度应比平常施工时适当放缓,多备塑料布覆盖,沟槽上口3m范围内不得有堆放物和弃土,沟槽开挖验收合格后,及时组织浇注砼垫层,沟槽周围设排水沟,随时保护排水畅通。③施工道路距基沟槽口不得小于5m。④混凝土砼浇筑前必须清除模板内的积水,施工时考虑随时准备遮盖挡雨和排出积水,防止雨水浸泡、冲刷、影响质量。⑤砼初凝前,应采取防雨措施,用塑料薄膜保护。⑥混凝土施工时,如突然遇雨,要做好临时施工缝,方可收工。雨后继续施工时,先对接合部位进行技术处理后,再进行浇注。6.2.2模板工程雨季施工措施①施工现场模板堆施要下设垫木,上部采取防雨措施,周围不得有积水。②模板支撑处地基应坚实或加好垫板,雨后及时检查支撑是否牢固。③拆模后,模板要及时修理并涂刷隔离剂。6.2.3钢筋工程雨季施工措施①钢筋应堆放在垫木或石子隔离层上,周围不得有积水,防止钢筋污染锈蚀。②锈蚀严重的钢筋使用前要进行除锈,并试验确定是否降级处理。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计7、防汛度汛管理方案7.1防洪防汛责任制防洪防汛工作,实行“统一指挥、统一协调、统一部署、快速反应、科学应对、分级实施”的原则。防洪防汛工作责任重于泰山,必须建立健全各种防洪防汛责任制度实现正规化规范化做到各项工作有章可循,防洪防汛责任制包括以下几个方面:6.1.1明确项目经理防洪防汛责任制项目经理责任制是各种防洪防汛责任制的核心,是取得防洪防汛抢险胜利的重要保证,也是历来防洪防汛斗争中行之有效的措施。防洪防汛抢险需要动员和调动各项项目部各方面的力量,公司各部门、全体员工全力以赴,发挥各自的职能优势,同心协力共同完成。因此,防洪防汛指挥机构需要项目主要负责人亲自主持,全面领导和指挥防洪防汛抢险工作,实行防洪防汛项目经理责任制。项目经理责任制的主要内容是:①贯彻实施国家、省(部)、市、区有关防洪法律、法规和政策,组织制订本项目有关防洪措施;组织制订项目防御洪水预案并督促各项措施的落实。②建立健全项目防洪防汛指挥机构;③负责督促项目各项防洪防汛准备工作的落实和重大清障项目的完成;④组织制订项目防御洪水预案,并督促各项措施的落实;⑤贯彻执行上级防洪调度命令,做好防洪防汛宣传和思想动员工作,组织抗洪抢险,及时安全转移受灾人员和国家重要安全财产;⑥组织筹集防洪防汛抗洪经费和物资;⑦组织开展灾后救助,恢复生产,水毁工程修复,保持社会稳定.7.1.2落实项目管理人员岗位责任制-78-
青海省黄河干流防洪工程(贵南县)施工组织设计各级管理人员,防洪防汛人员,抢险队员等要制定岗位责任制。明确任务和要求,定岗定责,落实到人.对岗位责任制的范围、项目、安全程度、责任时间等,要作出明确规定.7.1.3实行防洪防汛值班责任制为了随时掌握汛情,防洪防汛指挥机构应建立防洪防汛值班制度,以便及时加强上下联系,多方协调,充分发挥水利工作的作用。对该重点防汛区段和部位设防汛监督岗,派专人看守,昼夜监护,落实雨前、雨中、雨后检查巡视制度,发现问题立即采取有效措施加以防范及处理。7.2防汛度汛预案7.2.1随时留意天气预报,与当地气象监测部门建立紧密联系,天气变化之前,做好应急处理,消除隐患。7.2.2进场后抓好排洪设施的修建工作,确保汛前如期完工。抢修截水坝,形成第一道防洪屏障,对冲沟整治及截洪沟配备强有力的施工队伍,争取在汛期到来以前具备正常行洪能力;二是根据实际需要,经业主、监理等各方同意,增设一些临时排水设施,以满足排洪泄洪的要求。7.2.3拦砂坝砌筑到一定高度时,将具有一定的挡水功能,如果在此之前现状冲沟整治工程还未完成,这时水流将会较大,将造成行洪困难,应预留泄洪口。同时,配备足够数量的排水泵,用于应急临时排水。7.2.4本工程土石方开挖工作量较大,因此开挖的土石方因选择合理的堆放区域,避免暴雨、山洪形成泥石流。7.2.5冲沟整治、截洪沟区域,防汛责任人要监守工地,坚持24小时班制,并根据渡汛方案进行调度。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计7.2.6成立防汛领导小组:为确保雨季期间的安全生产,落实防汛工作,责任到人,我单位成立防汛领导小组,并建立防汛期间干部值班制度,成立专门的防洪小队和抢险小队,遇雨水天气须上路巡视,确保排水畅通,有险情须立即上报,并及时采取相应措施。7.2.7对本工程牵涉到所有通讯输电线路进行合理布置,尽量不要步设在低洼地带,并及时进行全面检查,对存在隐患要及时处理。对可能落到低洼处的电缆要采取修筑浆砌石护墩、干砌石护坝、埋设附杆等多种形式进行加固处理,以保障洪水冲刷之际杆不倒、不拉沟、线不段、不断电。确保通信输电线路畅通,避免;由于通信中断,输电线路中断等造成信息不灵和人身伤亡事故发生。7.2.8临时交通设施的设置要合理,尽量避开低洼地带布置,特别要注意在汛期施工不要阻碍河道行洪,并要给抗洪抢险留足防洪通道,对施工场地两岸要修建临时性防护工程,以保障正常施工。7.2.9为现场施工人员配置雨具,为方便施工操作,雨具应为衣、裤分开的两截雨衣。施工场地内的走道板面应设置防滑条及走道栏板防止在雨天路滑的情况下人员行走时滑倒。进入雨期施工期间,必须对所有一线施工操作人员进行安全教育,组织各施工员进行雨期施工组织措施交底。加强安全意识教育和安全生产管理,严禁施工人员雨天在非通道部位行走。7.2.10据总体目标、施工进度、施工难度、环境等特点,充分利用以前的施工经验,提前预测有可能发生的工序间交叉配合不到位等现象,采取有效措施,抓住重点,优化资源组合方案,合理调配劳动力、机械设备及各种生产因素,技术调整偏差,保证工程进度按期完成。7.3防洪防汛物资准备防洪防汛工程,关系到国计民生,本项目的防洪防汛工程,直接关系当地老百姓生命安全和财产安全,为确保防汛防洪工作的顺利,做到“预防为主”,必须做好充足的物资准备。本项目防洪防汛的主要物资准备有:防汛挖掘机2部、自卸汽车2辆、500kw柴油发电机-78-
青海省黄河干流防洪工程(贵南县)施工组织设计2台、水泵10台、编织袋1万条、毡布10包、铁线100把、木杆500根、应急灯5盏。7.4安全渡汛措施7.4.1加强领导,健全机构成立项目防洪防汛领导小组,在防洪防汛领导小组的统一指挥下,统一行动、积极配合、加大投入、积极备战,做好各项防洪防汛工作。7.4.2开展汛前大检查,做好防汛的各项准备工作项目部将组织人员对项目沿线进行汛前安全检查,发现问题及时处理,并将检查情况和处理结果以及存在的问题以书面形式报公司。暴雨之前,及时告知当地老百姓,以确保老百姓的生命安全和财产安全。7.4.3主要安全度汛措施①暴雨到来之前,将户外作业的机械转移到较安全的停放间内,应对高耸独立的机械、未装好的钢筋及模板等进行临时加固。②暴雨过后要立即对模板、钢筋特别是边坡、电源线路进行仔细检查,发现问题要及时处理,经现场负责人同意方可复工。③做好施工场地的排水,保持排水设施的畅通。④配备充足的防洪防汛物资和器材,成立防洪组织,制定防洪措施。服从业主和地主政府对防洪工作的统一安排和调动。⑤防停电措施:工地配备2台500kw柴油发电机,以便在关键工序施工预防突然停电。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计8、工程质量管理方案8.1质量保证体系本计划编制必须符合相关标准及法律、法规、条例、标准的规定,并满足标书合同的有关要求。坚持“质量第一,规范施工”的目标。围绕明确的质量方针和目标,对各项质量活动加以规定,对质量问题采取的纠正或预防措施提供必要的依据。质量保证计划经工程项目经理审定并报经监理核准后执行,并与其它管理标准、规章制度保持协调一致。质量保证体系见图8-1。图8-1质量保证体系质量保证体系组织保证思想保证技术保证物质保证经济保证施工保证项目部质量工程师职工培训全面质量管理教育技术培训技术交底材料采购材料检查奖优罚劣最优施工方法质量检查施工队质检员实现质量体系目标8.2各组织机构管理职责与质量管理制度7.2.1各级员工质量管理职责表见表8-1。8.2.2部门质量管理职责表见表8-2。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计表8-1各级员工质量管理职责表员工名称管理职责内容项目经理负责领导、组织、检查工程全部质量管理工作;掌握质量动态,协调各部门质量工作关系;对不合格项有权处罚,负法律责任。项目副经理协助经理组织各部门严格按程序工作;负责施工质量、安全保障和文明施工;负责质量管理的保障工作。技术总负责人协助经理制定质量计划;组织技术人员编制工程技术措施,进行改进和技术攻关;负责制定质量事故返修方案和措施;协调组织制定各项质量文件;负责项目经理委托的有关工作。质量安全部主任负责制定质量保证手册并保证其执行的有效性;主持质保文件的审查、修订和颁发;负责员工质保培训和技术培训工作。负责质量保证体系的建立和有效实施;正确履行质保职责,认真纠正不合格项;负责全面质量管理工作及合同中质量保证有关事宜;负责质量审查记录和不合格项的纠正工作;工程技术部主任根据质量计划和质量程序,负责解释和组织实施;编制工程技术措施及设计文件;负责处理施工队、班、组提出的技术和质量问题;掌握工程全部技术和质量资料。专职和兼职质检员掌握工程质量动态;监督队、班、组自检互检,组织质量检查;对不合格项责令整修返工乃至停工;及时向上级通报质量事故。施工队组长负责队、班、组的质量意识教育;组织队、班、组保质保量完成施工;参加本工序本工种的质量检查;负责施工材料的筛选。操作工人掌握操作技术,理解质量安全要求;服从质检员和上级的检查监督;负责经手机械设备的维修保养;由个人原因造成质量事故,由其负责人赔偿。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计表8-2部门质量管理职责表部门名称质量管理部门的性质质量管理、职责内容质量安全部质量管理监督检查和工程施工安全保证部门贯彻质保手册,开展培训工作;参加质量设计,处理质量问题;对工程质量进行监督、检查;协助指导队、班、组等各单位开展“三检”工作;负责监督安全管理规定的执行,纠正违章现象;负责制订、修改有关施工作业管理安全管理规定。工程技术部质量管理的重要综合协调部门编制、修订、审查施工计划方案;贯彻质量计划,进行技术交底,做好技术保障工作;对质量问题提出技术补救方案;做好施工准备,科学组织施工;做好维护保养和用户回访工作。8.3质量保证的技术措施8.3.1材料的检验制度和方法(1)材料进场检验制度①本工程的水泥、钢材等各类材料需具备出厂合格证,并根据国家规范要求分批分量进行抽检,抽检不合格的材料一律不准使用,因使用不合格材料而造成的质量事故要追究验收人员的责任。②把好试验控制关。配足相关的试验仪器和设备,由专业试验工程师负责,做好各种材料的试验鉴定和各项配合比的选配,满足现场施工质量控制和质检的需要。③把好进料关:进入工程的材料严格按设计要求定货,所有材料做到先试验后使用,不合格材料不进场。所有外购材料有材质检验合格证书和试验室的检验证书,报监理工程师批准后,方可进料。(2)技术交底制度-78-
青海省黄河干流防洪工程(贵南县)施工组织设计坚持以技术进步来保证施工质量的原则。技术部编制有针对性的作业指导书。每个工种、每道工序施工前要组织进行各级技术交底。各级交底以书面形式进行。因技术措施不当或交底不清而造成质量事故的要追究有关部门和人员的责任。(2)工程材料的检验方法对进场的原材料如钢材、水泥、石料等质量严加控制。必须按检验标准进行检验,并在使用前报送业主或监理工程师审查。未经检验合格的原材料,不得投入使用。物资管理人员做好原材料检验和试验状态标识,避免施工误用不合格的原材料。8.3.2技术培训及交底在工程质量管理中,“人、机、料、法、环”这五要素,人是决定的要素。施工管理层的工程技术人员、专业管理人员、施工操作人员素质的好坏,对施工工程质量起着决定性的作用。必须通过培训学习不断提高。8.3.3质量检验控制措施(1)工程制度的质量保证①在项目经理、总工程师的领导下,质安科配备专职质检工程师具体负责本工程的质量管理工作。②施工队设专职质检员,作业班组设兼职质检员。③项目部质安科每月组织一次质量检查,每季度由总工程师组织一次质量大检查,召开一次工程质量总结分析例会。④项目部每月组织一次本单位的质量大检查,作业人员每天进行施工中间检查及竣工质量检查并评出质量等级。⑤班组坚持“三检制”,自检合格后,专职质检员进行全面检查验收,然后由项目部质检工程师终检,并请监理工程师验收签认。⑥发现违反施工程序,不按设计图纸、规范、规程施工,使用不符合质量要求的原材料、成品和设备时,各级质检人员均有权制止,必须时可以向主管领导提出暂停施工进行整顿的建议。⑦质安科每月向公司报当月工程质量报表,进行质量分析,建立健全各种工程质量台帐,收集整理各种工程质量资料。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计(2)施工操作的质量保证①施工操作者是工程质量的直接责任者。工程质量的好坏,除了设计方面的原因外,单就工序质量来说,施工操作者就是关键。②施工操作者必须具有相应的操作技能,特别是重点部位工程以及专业性质很强的工种工程,操作人员必须具有相应的工种岗位的实践技能。因此,保证施工操作质量,就必须按不同工序的质量要求,合理解决施工水平问题。对一些专业技术工种,必须要作到持证上岗。③施工操作中,要坚持自检、互检、交接检制度。对工程必须本着自我控制的指导思想。所有工序要坚持样板制,有隐蔽工程预检要求的还必须坚持预检制。要牢固树立“上道工序为下道工序服务”和“下道工序就是用户”的思想,坚持做到不合格的工序不交工。④要按已明确的质量责任制检查操作者的落实情况,各工序实行操作者挂牌,促进操作者提高自身质量意识,做到操作任务明确,质量责任清楚。施工操作者还必须做到“原材料把关制”,杜绝使用不合格的材料,做好工程成品保护。⑤在整个施工操作过程中,要贯穿工前有交底、工中有检查、工后有验收的“一条龙”操作管理方法。做到施工操作程序化、标准化、规范化,确保施工质量。(3)质量检查控制制度①本工程施工将按ISO9001的要求,建立质保体系,确保合格工程。②建立项目管理内部的工作联系单,施工整改管理制度,制定合理的施工流程、规范和质量方法标准。③建立质量否定制度,以专职质量监督员为主,与现场施工员一起加强对操作班组的监督,发现问题及时整改,不合格的工程量不与签证和确认。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计④认真按图纸施工,按规程操作,建立自检、互检质量保证体系。⑤技术、质量工程是应根据实际图纸及质量评定标准进行跟踪管理。对各道工序进行把关、评定,提出书面整改意见,处理一般技术和质量问题,重大技术问题影响总技术负责人汇报,并提出整改意见。⑥总技术负责人应对工程技术和质量进行抽查,并责令在规定时间内进行整改。重大技术和质量问题的整改结果,技术总负责人应进行复查。(4)施工过程“三检”制实行并坚持自检、互检、交接检制度,自检要做方案记录,隐蔽工程要由工长组织项目技术负责人、质检员、班组长检查,并做出较详细的文字记录。①施工队(班组)的质量初检:由施工队(班组的专职兼职)质检员进行初检,并按单元工程规定的检查(检测)项目进行检查与检测,真实地填写施工记录及单元工程质量检查评定并签字。一个单元工程或一道施工工序由几个施工队(班组)连续完工时,认真作好班组交接施工记录,由完成该单元工程(或该道工序)初检表。保证做到初检记录齐全、正确,将基本的质量保证关控制在初检过程中,无初检资料、资料不全或失实的单元工程不进入复检。②施工过程复检:搞好施工过程复检是考核评定施工队(班组)施工质量的依据,并可提高一次检查合格率。复检由专职质检员与施工技术人员一起进行,并填写复检意见。复检的主要内容是检查初检项目是否齐全,检验数据资料是否准确,检查结果与施工记录是否相符等。凡发现有检查项目不全或达不到质量标准的单元工程,在复检时处理完善。③-78-
青海省黄河干流防洪工程(贵南县)施工组织设计施工终检:这是保证施工质量的关键。终检将由质量安全部专职质量检查员邀请监理工程师一起联合进行。终检的主要内是检查经过复检后的单元工程的检验评定结果是否符合设计及相关规程规范要求,资料是否齐全,质量评定是否正确,检查结果与施工情况是否一致,同时检查所完成的单元工程是否存在质量隐患,单元工程在终检时完整地签署质量评定意见,对分工序施工的单元工程,在上一道工序未经终检或终检不合格时,不进行下一道工序的施工。(5)质量否决制度对不合格分项、分部工程必须进行返工。不合格分项工程流入下道工序,追究班组长的责任,不合格分部工程流入下道工序,追究工长和项目经理的责任,有关责任人员要针对出现不合格工程的原因采取必要的纠正和预防措施。8.3.4质量事故及处理单位工程施工中,遵循质量先于进度和在保证施工质量的情况下加快施工进度的原则,坚持工序、过程控制,执行三级质检制,严格按设计要求及规程规范组织施工,施工中杜绝质量事故。因我单位原因达不到约定质量标准,由我单位承担调查、补充、设计和维修,我单位还将承担相应的一切法律和经济责任,工期不予延误。8.3.5工程保修承诺对合同范围内全部工程负责进行质量保修,保修期一年,并严格按照《建设工程质量管理条例》规定执行,保修责任满足国家强制要求。对保修项目和可能产生的施工缺陷,我公司将按照业主的要求,在接到修理通知之日后,3日内派人进行质量保修和缺陷修复;若发生紧急抢修事故,我公司接通知后将立即派人到达现场组织抢修,其费用由我公司承担。我公司同时承诺:在国家规定的工程合理使用期限内,若是我公司施工质量问题造成人身和财产损失,我公司承担全部责任。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计9、安全生产管理方案9.1安全施工管理结构及安全检查流程安全施工管理结构见图图9.1安全施工管理结构图项目经理项目总技术负责安全管理小组安全主任资料员质检员施工员计量员工程师机械师专职安全员各施工工段兼职安全员-78-
青海省黄河干流防洪工程(贵南县)施工组织设计9.2施工安全管理(1)安全管理责任制①项目经理为安全施工的第一责任人。对安全施工负直接领导责任,组织制定安全生产制度。②技术总负责人,负责安全技术措施的编制和审核安全技术交底和安全技术教育。③施工员对分管施工范围的安全施工负责,贯彻落实各项安全技术措施。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计④工地设安全管理小组和专职安全员,负责安全管理和监督检查,各工班设兼职安全员,每个施工人员都有岗位安全责任。⑤对安全生产有检查、有落实、有记录、有追究,对违章作业执行“三不放过”原则。(1)安全教育①项目经理、技术负责人、施工员、安全员经岗位安全培训,考核合格后才能持证上岗。②在员工进入施工前必须进行岗前安全培训。③做好劳务人员的安全基本知识和规章制度的守纪教育。④特种作业人员和机械设备操作人员必须经培训和考核取得相应岗位的操作证后,方可上岗。⑤进行经常性的安全生产教育。(2)安全生产管理①安全生产管理是项目管理的重要组成部分,是保证生产顺利进行防止伤亡事故发生的重要手段。②现场施工要严格执行有关安全生产的各种规定和条例,要认真研究各种安全技术措施,改善劳动条件,消除施工中的不安全因素。③掌握施工中的安全状况,及时对安全隐患,采取措施整改。④安全生产管理要贯彻“安全第一、预防为主”的方针。⑤施工前,项目部要认真组织安全技术交底。⑥安全设施须经过安全检查验收,合格后,才可投入使用。⑦施工中应经常进行安全检查,班组必须坚持每天工前会议制度,工段每周组织一次安全检查,项目部每半个月组织一次安全检查,安全检查结果须以书面形式向单位报告。检查中发现的问题应及时整改,不留隐患。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计⑧一旦发生事故,应以严肃、正确、科学的态度去认识事故,不隐瞒、不虚报、为避重就轻。科学分析事故,找出事故原因,教育广大员工吸取教训,提出整改措施。(4)安全技术管理①项目成立安全生产领导小组,建立安全生产管理网络,设专职安全员1名,负责工地安全生产管理工作;制定项目安全目标对策表,并认真实施。②贯彻“安全第一,预防为主”的安全生产方针。执行《安全生产法》等规定;坚持班前、班后会制度和专业安全教育制度。③开工前做好项目职工安全教育培训,对全员进行安全教育考试和安全技术交底,考试成绩合格方可上岗。④配齐各种安全防护设施,进入施工场地必须穿工作服,戴规定颜色的安全帽,落差大于两米作业必须系好安全带。⑤做好开工前的安全检查工作,检查内容列出对策表,达不到安全工作要求的,立即整改,发生责任事故,按《项目安全奖罚规定》进行处罚。⑥项目定期召开安全生产例会,解决生产中存在的安全问题。⑦定期开展安全生产检查活动,对查出的问题及时按“三定一落实”原则进行整改。⑧特种作业人员必须持证上岗,非特种作业人员不准从事特种作业。⑨实行24小时安全巡回值班制,定期开展安全生产活动,定期检查,查出隐患,立即整改,安全管理领导小组每周召开一次例会,研究解决施工中存在的安全问题,做好安全检查记录和安全会议记录。9.3安全施工保证措施-78-
青海省黄河干流防洪工程(贵南县)施工组织设计在施工过程中,应按照安全技术要求,建立完善的安全制度,安全保障措施要到位,确保施工的安全。安全员要持证上岗,对职工进行安全教育,严格检查和监督,排除安全隐患,杜绝违反安全管理制度的行为。(1)一般保证措施①施工现场的布置应符合防火、防爆、防雷电等安全规定和文明施工的要求,施工现场的生产、生活办公用房、仓库、材料堆放场、停车场、生产车间等应按批准的总平面布置图进行布置。②进入施工现场的作业人员,必须认真执行和遵守安全技术操作规程。③各类房屋、库棚、料场等的消防安全距离应符合国家或公安部门的规定,室内不得堆放易燃品;严禁在料库、油库等处吸烟;现场的易燃杂物,应随时清除,严禁在有火种的场所或其近旁堆放。③施工时应时刻注意山坡的变形,发现预警信号,立即组织人员和设备撤离工地。④临时边坡一定要保证安全稳定,严防边坡局部失稳,伤害施工人员。⑤在边坡开挖、清理过程中,如出现裂缝和滑移迹象,立即暂停施工并采取应急抢救措施,使危害减到最少,并及时通知监理工程师。必要时,按照监理工程师的指示设置观测点,及时观测边坡变化情况并做好记录。⑥施工区内设置一切必需的安全警示信号装置,施工现场安全难点部位均挂安全警示牌,警示安全;公路通过工区的两端均设专人值班,负责安全。(2)施工机械的安全控制措施①设备搬迁、安装、拆卸必须分工明确,专人负责,统一指挥。②人员严禁接触机械运转的任何裸露部件,不得靠近、跨越、拆卸和清洗运转中的设备。处理故障、更换部件,设备局部调整,清洗设备,调整皮带时均应停车断电,并由专人看护。在启动任何动力和关闭动力前,必须确认无误,并通知孔口操作人员。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计③各种机械操作人员和车辆驾驶员,必须持有操作合格证,不准操作人员操作与操作证不相符的机械;不准将机械设备交给无操作证的人员操作,对机械操作人员要建立档案,专人管理。④操作人员必须按照本机说明书规定,严格按照工作的检查制度和工作中注意观察及工作后的检查保养制度,做到工作前检查、工作中观察、工作后检查保养、认真填写机械运转记录。⑤驾驶室或操作室应保持整洁,严禁存放易燃、易爆物品,严禁酒后操作机械,严禁机械带病运转或超负荷运转。⑥机械设备在施工现场停放时,应选择安全的停放地点,夜间应有专人看管。⑦严禁对运转中的机械设备进行维修、保养调整等工作。⑧指挥施工机械的作业人员,必须在操作人员可以看到的安全地点,并用明确规定的指挥联络信号进行指挥。⑨定期组织机电设备、车辆安全大检查,对检查中查出的安全问题,按照“三不放过”的原则进行调查处理,制定防范措施,防止机械事故的发生。(3)安全用电保证措施①所有外电输电线路必须架空,电杆距离为50m,电杆埋设必须牢固。②用电线路拆、装一律由专业电工负责,其他人员不得随意拉设线路和接用电气设备。③采购的各种电器设备、元件必须是国家正规厂家生产,有产品合格证,不得使用假冒伪劣产品。④电器开关操作标识要齐全,清晰,拉闸检修时必须挂“严禁合闸,有人作业”标志牌。多人在一条停电线路上作业时,应由专人负责,统一指挥。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计⑤施工用电必须安装符合要求的配电箱、漏电保护器设备要有接地线,电缆要求不破损,并用绝缘杆架空,严禁拖入泥水,运输道上的电缆应外套金属管或埋设保护,并设有标志牌。⑥实行“一机一闸”制,严禁用同一开关控制2台以上用电设备。电动机动力线必须与设备及底座可靠绝缘,严防水、油侵入电气设备。⑦不得用串联金属棒或其他导电物体将电压引入焊件。⑧露天配电箱、开关箱、主控电箱等必须加防雨设施。在带电导线、设备等附近,不得有损坏电气绝缘或可能引起火灾的热源。⑨做好消防防火工作,在林区作业,要控制好火源,配好消防器材,工地不准有明火,不准抽烟,生活区要做好火源隔离措施,防止放生火灾。⑩做好创建安全合格班组和青年安全监督岗活动,专职安全员每周检查一次安全活动记录。推行项目安全目标管理,安全职责落实到每个人,工程结束认真进行总结评比。9.4安全责任制及安全奖惩措施(1)建立健全安全生产管理责任制,使项目部每个人清楚自已的安全责任,提高安全意识。①项目经理为安全施工的第一责任人。②分管生产的项目副经理,对安全施工负直接领导责任,具体组织制定安全生产制度。③分管技术的项目副经理,负责组织安全技术措施的编制和审核,安全技术交底和安全技术教育。④施工员对分管施工范围的安全施工负责,贯彻落实各项安全技术措施。⑤工地设安全管理小组和专职安全员,负责安全管理和监督检查,每个施工人员都有岗位安全责任。(2)安全奖罚措施-78-
青海省黄河干流防洪工程(贵南县)施工组织设计①提取工程总价的2%作为安全奖励经费,工程安全达到预定目标后,对工程质量先进班组和个人进行奖励。②每月进行一次安全检查评比活动,对在安全检查评比中表现较好单位或个人进行奖励。③对各施工队,凡一次由项目部组织的安全检查不合格,对施工队处以500-1000元罚款;安全检查不合格达3次,则对施工队进行安全整顿,更换施工队负责人。④发生一般事故或施工中发生民工伤亡事故,将追究责任人的法律、经济责任并扣除项目部该年安全奖金。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计10、工程进度管理方案10.1工期保证体系我公司一旦中标后,将充分发挥各专业工种配套齐全,机械化施工水平高及现代化科学管理的优势,保证做到“三快”即:进场快、安家快、开工快。在保证重点,照顾一般统筹安排,全面开展的原则下,抓好有利季节不断掀起施工高潮,高质量、高标准地严格按施工组织设计的工期全面完成本项目的施工任务,保证体系框图见图10-1。图10-1保证体系框图机械管理制度:配件计划、维修保养制度、完好率使制度保证组织发动,思想动员开展保工期,创优质竞赛活动总公司:生产副经理→工程处项目部:生产副经理→工程部→计划调度员→工段长总公司:年度计划→季度计划项目部:总计划→月计划→周计划→日调度会调度会制度:日生产检查、汇报、协调落实计划进度考核制度:每月考核与工资奖金挂钩劳动力管理制度:劳动力计划、调配管理、定额管理考核制度材料管理制度:供应计划、材料库存保管、供应施工组织设计、工艺先进合理、技术交底新技术、新材料、新工艺推广应用总公司:总工程师→工程处材料保证:混凝土制备等满足施工进度要求劳动力与设备保证:满足施工进度要求资金保证:工程进度款定期审核签认到位思想保证组织保证计划保证制度保证技术保证资源保证工期保证体系-78-
青海省黄河干流防洪工程(贵南县)施工组织设计10.2工期的组织保证措施①实行项目经理负责制,抽调经验丰富,年富力强的技术管理骨干组成项目管理人员,做到分工明确、责任到人、管理到位;抽选技术较好、工作积极、素质较高的熟练工人作为主要施工操作人员。施工期间,加强员工的培训,以确保工程进度顺利进行。②在配备充足的施工机械的基础上,同时加强施工机械的维护保养,提高机械的完好率,配备充足的机务管理人员和维修人员,配齐充足的配件和易损件。调配一批灵活性强,机动性大的设备以满足施工的需要。③合理安排施工顺序,优化施工程序,加强现场调度,发挥机械作业效率,充分利用人、材、物等资源,加强信息管理工作和统计分析制度,尽量缩短工期。④做好进度控制,合理划分施工流水段,按照施工总进度计划进行控制,安排好月、旬、日计划,做好流水作业施工。⑤加强各方面的协调工作,使各环节密切配合,减少施工干扰,提高施工效率。搞好检查工作,发现问题及时解决;加强生产调度工作,根据实际情况,组织新的平衡;⑥进行工期计划动员,把工期计划变成职工的行动;推行经济承包制,把计划批准的执行情况与部门、施工队、班组、个人的经济利益挂起钩来。对作业人员给予适度的赶工激励。10.3工期的技术保证措施10.3.1挑选精兵强将,早进场,早开工①为加快本工程的施工进度,保证工期,将组织好精干的施工管理人员和施工队伍,集中挑选了配套的机械设备。接到中标通知书后,迅速做好施工前的各项准备工作。做到施工设计、桩位复测、熟悉设计文件和技术交底同步进行。压缩施工准备时间,上足劳力和机械设备,为主体工程施工创造条件。保证按期开工。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计②合同签订后,立即组织队伍,设备上场,作好施工便道及临时房屋的修建工程。架设、配备、修建电力、通讯线路和供水设施,突出重点工程项目的施工任务,保证按期开工。10.3.2加强对全体施工人员的思想教育树立一个“干”字,立足一个“抢”字,确保一个“好”字,好中求省,好中求快。树立时间就是效益,进度就是信誉的思想,以战斗姿态的投入工程施工。10.3.3加强宏观控制,重点工程重点突击根据施工工程的特点,从设备配备和队伍的选择上,都要严格挑选。在人员、资金、物资、机械上优先保证重点工程施工。10.3.4加强组织管理、科学安排施工选用会管理、懂技术、年富力强的同志担任各级主要负责人,严格各方面规章制度,上令下行。各级组织机构要高质量、高效率地运转,科学地安排施工,控制工程必须最大限度的安排平行作业,抓好工序衔接,做到环环相扣,有条不紊,加速工程进度。10.3.5搞好内部经济责任制,提高工作效率①加强各级领导,建立健全岗位责任制,签订包保责任状,以天计划保旬计划,以旬计划保月计划,确实保证各项工程按计划完成。②完善奖惩制度,落实好按劳分配的原则。实行不同形式的计件工资、计时工资、承包工资,以经济为杠杆,充分发挥施工人员积极性和主动性,提高生产效率,提前工期有奖,延误工期受罚。同时对班组加强施工现场管理,做到文明施工。10.3.6作好设备的选型及配件供应工作①充分发挥我们施工机械化程度高的优势,在施工中科学地组织机械化一条龙作业和流水作业,加强对施工设备的管理,组织好机械设备配套的采购、供应,提高设备完好率和利用率,保证机械化生产顺利进行,保证工程质量和工程进度的落实。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计②设备的选型力求实用、多效、耐用的原则,防止待机误工。在施工中要有计划地备足易损件,加强机械设备维修保养,做好随坏随修,确保施工机械按计划正常运作。项目部设立机械维修小组,确保发生故障时在2小时内修复。10.3.7抓好材料供应工作①确保材料供应满足施工需要,合理安排施工顺序。②做到统筹安排资金,专款专用,集中调运大宗材料,周转材料。采取有效措施,确保供货商在预定的时间内保质保量供货。10.4关键工序进度保证措施为确保工期目标,我单位对各分项和关键工序进行科学、合理的搭接,以确保施工流水能按计划正常运行。(1)石方工程石方工程是本工程中的重要任务之一,因为石方工作量较大,约9500m³,并且影响到其他后续工程的施工,因此不能够延误工期。在场地合理安排布置的情况下多班组有步骤地施工,并必须保证不延误工期而影响后续工程的施工。确保不影响总工期。(2)混凝土工程①混凝土工程是本次工程的重要工序,因其工作量大,工作面分布广,必须进行科学合理的统筹安排,进行多层次的流水施工,并保证多种工作的衔接和协调,同时作好场地安排和材料供应。②在施工进程中,一旦发生偏移,适时进行修正,充分利用总时差及自由时差进行调整,对关键线路上的工序进行调整追赶,必要时加强人力物力,使关键线路上的工序不拖后一天。10.5其它工期保证措施10.5.1关心员工的生活,根据施工强度相应调剂员工的饮食,加强饮食卫生管理,减少疾病。现场设立医务室、定期做好饮食卫生的消毒工作,防止恶性传染病的发生而影响正常施工。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计10.5.2做好雨天、夜间施工的措施和周密的准备工作及防洪抗灾保证工作,确保施工的顺利进行。10.5.3搞好与业主、监理工程师及当地群众的关系,创造一个天时地利人和的施工环境,大力配合业主的清场工作,为尽早提供施工现场作努力。10.6建立施工进度监测系统10.6.1工程施工进度监测系统见图10.2;10.6.2工程施工进度调整系统见图10.3。工程进度实施过程建立进度数据采集系统数据的整理统计和分析实际进度和计划进度检查是否出现进度偏差否进入施工进度调整系统10.2工程施工进度监测系统图工程施工进度实施过程工程施工进度出现偏差分析产生进度偏差的原因统分析该进度偏差对后序产生的影响统确定影响后序工作的限制条件采取施工进度调整措施形成经调整的施工进度计划采取相应的组织、技术和经济措施实施调整后的施工进度计划图10.3工程施工进度调整系统图-78-
青海省黄河干流防洪工程(贵南县)施工组织设计10.7工期的奖罚办法在施工中,充分利用经济手段对工期进行控制,对提前完成的施工队和机组进行物质奖励和精神奖励,对每提前一天完成的施工班组给于100-500元奖励,对未按时完成的施工队和班组每推迟一天罚款100-500元。进度计划详见附表四:施工进度计划横道图-78-
青海省黄河干流防洪工程(贵南县)施工组织设计11、文明施工管理方案11.1文明施工保证体系文明施工保证体系见图11-111.2文明施工组织管理措施-78-
青海省黄河干流防洪工程(贵南县)施工组织设计11.2.1组织管理措施施工现场应成立以项目经理为组长,项目副经理、项目技术负责人、各工区负责人、生产、技术、质量、安全、消防、保卫、材料、环保、行政卫生等管理人员为成员的施工现场文明管理组织。11.2.2个人岗位责任制文明施工管理按专业、岗位、工程位置场地等分片包干,分别建立岗位责任制度。11.2.3经济责任制把文明施工列入单位经济承包责任制中,将"包、保"检查与考核相结合。11.2.4检查制度工地每月至少组织两次综合文明检查,按专业、标准全面检查,按规定得出结果,制表张榜公布。施工现场文明施工检查是经常性的管理工作,也可采用定期检查与随时抽查相结合;集体检查与个别检查相结合等方法,组织实行班组自检、互检、交接检制度,要做到自产自清、日产日清、工完场清的标准管理。11.2.5开展"5S"活动在施工现场开展文明施工竞赛活动,围绕"5S"进行,即对施工现场各生产要素所处状态不断地进行整理、整顿、清扫、清洁和素养。①整理:对施工现场现实存在的人、事、物进行调查分析,按照有关要求区分需要和不需要,合同布设,把施工现场的不需要的和不合格的人、事、物及时处理。②整顿:通过上一步整理后,把施工现场所需要的人、机、料按照施工现场平面布置图规定的位置,并根据有关规范、标准、科学合理地安排布置和堆放,使人才合理使用,物品合理定量,实现人、物、场所在空间上最佳结合,从而达到科学施工,文明安全生产,提高效率和质量。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计③清扫:主要是对施工现场的设备、场地、物品勤加维护打扫,保持现场环境卫生、干净整齐、无垃圾、无污物,并使设备运转正常。④清洁:就是维护整理、整顿、清扫是前三项活动的继续和深入。职工要注意个人卫生,而且要注意精神文明;要进一步消除施工现场的空气粉尘、噪声、水源污染,达到规定要求。⑤素养:就是努力提高施工现场全体职工的素养,养成遵章守法和文明施工的习惯。开展"5S"活动,要特别注意调动全体职工的积极性,自觉管理,自我实施,自我控制,贯彻施工全过程、全现场,由现场职工自己动手,创造一个整齐、清洁、方便、安全和标准的施工环境,使全体职工养成遵守规章制度和操作规程的良好风尚。11.3文明施工设施11.3.1施工现场、生产、生活用临时设施,要按文明施工要求设置。11.3.2拟定在对外交通比较方便处设一个安全防护大门,按标准做成彩门,装饰美观,以充分体现施工企业的风貌。11.3.3根据现场施工场地布置情况,设置临时公共厕所(有化粪池,用砖砌)。11.3.4在施工现场布置安全标志、标语,在施工大门口布置平面布置图,注明工程概况及各种制度要求。11.3.5布设各类安全防火设施。11.3.6场区道路要平整、坚实、畅通、排水良好、无灰尘、有较完好的照明设施。11.3.7在施工现场设一垃圾站,集中垃圾,派专车运到垃圾处理场或按要求进行掩埋或焚烧处理。11.4文明施工管理措施11.4.1成立文明施工领导小组,项目经理为第一责任人。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计11.4.2做好施工现场的文明宣传工作,尊重当地的民风、民俗,与周围居民友好相处。11.4.3积极开展文明施工窗口达标活动,做到“两通、三无、五必须、便民利民不扰民”。11.4.4施工现场道路整洁畅通,排水设施齐全有效,场内无积水保持干燥。11.4.5施工时同有关的环卫和交管部门联系,服从其规定,争取地方政府的支持。11.4.6现场实行标准化管理,挂有“七牌一图”,使整修施工区域处于五种动态管理之中,争创文明施工样板工地。11.4.7施工人员配带工作卡进入工地。11.4.8施工器材要堆放整齐有序,所有施工机具保持整洁机容,每天进行维护保养。11.4.9弃土、渣及时运出场地,堆放到指定位置。11.4.10设立专职卫生巡视员,发现问题立即处理解决。11.5文明施工目标与承诺按文明施工标准进行施工管理,创建文明施工工地,并达到文明施工现场标准。在施工期间将严格按文明施工现场标准进行施工现场管理,做到不出现违法乱纪行为,按国家相关法规做好施工场地及邻近周边地下管线、建、构筑物的保护工作;若有违约行为,我公司承担相应责任。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计12、环境保护管理方案12.1环境保护体系建立健全环境保护管理体系,项目部由项目经理分管环保,下设环保组专职落实环保措施,检查、监督各工程分部对环保措施的执行,监察收集各项环保数据,并与当地环保主管部门建立联系,不断完善施工期间的环保措施,使得保护环境得到真正落实.12.2环境保护措施12.2.1防止水污染的措施①清洗机械和运输车辆的废水经过沉淀后,方可排入污水管线,亦可回收用于洒水降尘。②凡进行施工作业的污水,必须控制水流向,防止蔓延,并在合理的位置布置沉淀池,经沉淀后方可排入污水管线。③施工中按污水处理方案,妥善保护各种管道和排水沟,并派专人检查保护措施的可靠性。④现场存放油料的库房,必须进行防渗处理。存储和使用都要采取措施,防止跑、冒、滴、漏、污染水源。⑤施工过程中严禁将含有污染的物质或可见悬浮物的水排入长江,未经处理的污水严禁外排。⑥所有机械废油应回收利用或妥善处理,严禁随意泼倒。12.2.2防止大气污染的措施①严格遵守《中华人民共和国空气质量标准》(GB3095-1996),确保施工产生的空气悬浮颗粒不超标,不污染环境。②设备选型时,选择低污染设备,对可能造成粉尘污染的设备安装空气污染控制系统与设备同步运行。③材料搬运过程中,可能产生粉尘的材料喷水湿润,工地安装定喷管,装卸前湿润多尘物料。④运送水泥和砂石料的车辆,其装载量不超过挡土板,上面用干净的防水布盖严密。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计12.2.4其它环保措施①遵守国家和地方有关环境保护的法令,在合同规定的施工界限之外的植物、树木尽力维持原状,严防有害物质污染工地。②及时清理施工现场垃圾,不得在场内焚烧垃圾,保持施工区周围的环境卫生。③搞好与当地居民的关系,树立良好的企业形象,不打架斗殴、不聚众赌博,遵章守纪,尊重当地乡风民俗。12.3环境保护承诺严格遵守国家和地方有关环境保护的法令,维护周边居民正常生活秩序和良好的生态环境以及施工所在地的人文景观等。保护周边环境,生产生活用地合理规划,进场材料,生活及生产垃圾有序堆放,做好环保、水保工作。如造成对施工场区及周围环境的污染破坏,我方承担相应经济、法律责任外。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计13、水土保持管理方案13.1严禁将挖方弃土随意堆放,需按照设计要求并与当地水保部门共同协商确定放置位置。施工作业不得损坏用地范围外的耕地、树木、果林及水电设施,临时用地应事先将表层耕植土集放,完工后复整平。13.2施工期间始终保持土地的良好排水状况,修建一些临时排水设施,并与永久性排水设施相结合。13.3采取必要措施防止所占地及河流、水道或灌排系统和堤坡底岸的土壤受到冲刷,并保证在任何河渠排灌系统中不产生淤积。施工过程中严禁将含有污染的物质或可见的悬浮物的水排入长江,并保护原有的防护设施。13.4保护本工程沿线的树木免遭损坏。13.5认真做好环境绿化工作。永久用地范围内裸露地表用植被覆盖,临时用地要进行复耕,裸露部分要植草或种树。施工过程中,对树木、农田、果林注意保护。13.6遵照国家的法律条例和规定,施工时采用必要的措施,确保土地不受灰粉、沙尘、废气、化学制品污染的损害,特别保护好民用水源、水产不受破坏和污染。13.7在本工程施工中和完工后,对破坏的环境及时整治,防止水土流失,接受各级环保部门对本工程环境保护工作的日常监督和管理。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计14、农民工工资支付保证措施一、严格执行国家劳动和社会保障部关于保障农民工工资支付的四项基本措施:1、是建立工资支付监控制度,全面监控和重点监控相结合,列为重点监控对象的,要定期向劳动保障部门报送工资支付情况;建立企业工资支付信息网络,完善监控手段。2、是推行工资保证金制度,被重点监控的建筑施工企业和有过欠薪行为的企业,要缴纳一定数额的工资保证金,以保证农民工工资不因企业资金状况而被拖欠。3、是全面实施小时最低工资标准,防止一些企业以计件工资名义压低和克扣农民工工资。4、是推行企业劳动保障诚信制度,规范企业用工和工资支付行为。全面推进劳动合同制度实施行动计划,用人单位招用农民工都依法订立书面劳动合同,建立权利义务明确、规范的劳动关系。二、为了保证民工工资,我公司做了多项保证措施。1、俗话说,一份辛劳一份收获,我公司各有关部门积极采取措施,保证农民工工资及时发放、让农民工劳有所得,也促进了建筑施工企业的发展。为了保证工人工资得到保障,我公司单独开设了农民工调查小组。专门调查解决农民工拖欠、纠纷等现象,一经发现公司将对其严厉处罚,做到“工程清工资清”,决不拖欠民工一分钱。2、我公司为民工设立了绿色通道及意见箱,民工有意见或事情可以直接到公司找相关单位,并且为其大力解决难题。3、在县建设行政主管管理部门的管理下,我公司及早与民工签订了劳动合同,保证民工及时拿到自己的辛苦钱,也保证了建设的顺利进展。4、我公司设立民工工资专用帐户,预存工资款,避免了由于工程中一些复杂问题而造成资金困难,使的工资迟迟发不下去。建立专用帐户正是能保障工程在危急时候能够保证民工工资。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计5、保证按月发放工资,每月5日准时发放民工工资。6、我公司采取“举证责任倒置”办法,即由用人单位负责举证,企业拿不出工资发放证据就视为欠薪,解决了农民工讨薪时“举证难”的问题。在目前农民工讨薪难的大环境下,不失为一种方便农民工的行政举措。一、不拖欠农民工工资的承诺书公司在多年的市场经营中,始终坚持“保质守约、薄利重义”的企业宗旨。为认真贯彻落实各上级主管部门关于切实解决建设领域拖欠工程款的民工工资问题的要求,我公司承诺:若有幸中标,决不拖欠民工工资。具体措施为:1、与所有民工签订劳动合同。2、开设专门帐户,由公司财务派专人专管,保证工程款的专款专用。3、根据工程进度计划,制订出民工工资支付计划表。4、将民工工资的支付情况纳入项目经理部的各项考核指标中进行统一考核。特此承诺!5、严格按县行政主管部门规定,足额缴纳农民工工资保证金,如果发生农民国工资拖欠现象,无条件接受上级主管部门处罚。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计15、施工总平面图布置说明15.1布置依据15.1.1本工程施工招标文件。15.1.2对现场及周边环境进行实地考查情况的现场条件。15.1.3本工程采用的主要施工技术措施、进度安排和拟投入的机械设备。15.2布置原则15.2.1本工程工期短、工作内容多,工作战线长,工作面广,在确保工程施工的安全、质量、进度的前提下,根据现场尽可能地简化施工布置。15.2.2充分利用公司的资源优势,配备足够的专业施工机械设备器具和附属设施。15.3施工供水、供电布置工程区生活、施工用水、日常照明及部分小型机械用电接当地居民点供水、供电系统15.4施工营地布置根据本工程施工实际情况,为了照顾全线施工,为了便于管理,考虑到施工交通,。在项目区内搭设一定面积的临时建筑,布置器材仓库、工棚、项目部、宿舍等作为本工程施工营地。15.5施工道路布置本项目区内交通条件方便,施工过程中利用现有道路和施工便道作为交通网来满足施工材料和设备的供应,确保工程按期完工。施工总平面布置图详见附表五,临时用地表详见附表六。-78-
青海省黄河干流防洪工程(贵南县)施工组织设计附表一:拟投入本项目的主要施工设备表序号设备名称型号规格数量国别产地制造年份额定功率(KW)生产能力用于施工部位备注1砼搅拌机YJ3503武汉201118kw良好混凝土工程2插入式振捣器JS-5003武汉20131.1kw良好混凝土工程3挖掘机液压1m³2瑞典2013良好土石方工程4自卸汽车5t3襄樊2013良好材料运输5推土机FX-41001武汉201174kw良好土石方工程6砂浆搅拌机JS-2501武汉20111.5kw良好冲沟、截洪沟、拦砂坝7蛙式打夯机BX-5223无锡20122.8kw良好混凝土工程8风钻手持式3武汉2011良好石方开挖9风水枪6m³/min3武汉2014良好混凝土工程10钢筋切断机GAM40B1无锡201120kw良好冲沟、截洪沟、沉砂池11钢筋弯曲机Φ6~401无锡201113kw良好冲沟、截洪沟、沉砂池12电焊机交流25kVA1无锡201140kw良好冲沟、截洪沟、沉砂池13对焊机电弧型150kVA1无锡201125kw良好冲沟、截洪沟、沉砂池14空压机VY-9h3苏州201218kw良好冲沟15混凝土输送泵30m³/h1武汉201220kw良好混凝土工程16液压履带钻2武汉2012良好锚杆工程-78-
青海省黄河干流防洪工程(贵南县)施工组织设计附表二:拟投入本项目的试验和检测仪器设备表序号设备名称型号规格数量国别产地制造年份已使用台时数用途备注1砼试件模具150*150*1503组武汉2014检测砼2坍落度筒1套湖南2013检测砼3含水量快速测定仪HKC-303台湖南2013300测砂含水率4磅称1台武汉20135卷尺10宜昌20146靠尺3套武汉20137全站仪GTS-332N1日本2014780测量8DS3水准仪DZS21武汉2014560测量9办公电脑联想1武汉20141200办公10打印机佳能1宜昌2012650办公-78-
青海省黄河干流防洪工程(贵南县)施工组织设计附表三:拟投入本项目的劳动力计划表工种按工程施工阶段投入劳动力情况土方开挖回填及土地平整工程混凝土工程浆砌石工程格宾石笼网工程填石工程土工布工程砂砾石路面工程植物措施工程环境保护工程竣工验收工程管理人员10101010101010101010测量员6666666666机械操作工12121212121212121212砼工15151515151515151515钢筋工10101010101010101010模板工8888888888瓦工520205555555水电工8888888888普工20202020202020202020-78-
青海省黄河干流防洪工程(贵南县)施工组织设计附表四、施工进度计划网络图-78-
青海省黄河干流防洪工程(贵南县)施工组织设计-78-
青海省黄河干流防洪工程施工组织设计附表五、施工总平面图投标人应递交一份施工总平面图,绘出现场临时设施布置图表并附文字说明,说明施工营地、料场、临时设施、加工车间、现场办公、设备及仓储、供电、供水、卫生、生活、道路、消防等设施的情况和布置。-78-
青海省黄河干流防洪工程施工组织设计附表六临时用地表用途面积(平方米)位置需用时间门卫20见施工总平面图开工至竣工现场办公室200见施工总平面图开工至竣工生活区域(职工宿舍)200见施工总平面图开工至竣工机械停放场地200见施工总平面图开工至竣工卫生间120见施工总平面图开工至竣工食堂150见施工总平面图开工至竣工材料堆放场地300见施工总平面图开工至竣工综合加工区域150见施工总平面图开工至竣工库房100见施工总平面图开工至竣工会议室200见施工总平面图开工至竣工-78-