• 276.50 KB
  • 80页

施工组织设计-主题演绎秀1207

  • 80页
  • 当前文档由用户上传发布,收益归属用户
  1. 1、本文档共5页,可阅读全部内容。
  2. 2、本文档内容版权归属内容提供方,所产生的收益全部归内容提供方所有。如果您对本文有版权争议,可选择认领,认领后既往收益都归您。
  3. 3、本文档由用户上传,本站不保证质量和数量令人满意,可能有诸多瑕疵,付费之前,请仔细先通过免费阅读内容等途径辨别内容交易风险。如存在严重挂羊头卖狗肉之情形,可联系本站下载客服投诉处理。
  4. 文档侵权举报电话:19940600175。
施工组织设计世博会城市之光主题演绎秀新建工程施工组织设计编制单位:上海鸿硕建设开发有限公司编制日期:2009年11月7日nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第一章编制说明一、本施工组织设计编制依据:1、世博会城市之光主题演绎秀新建工程项目的招标文件、初步设计及有关资料;2、现行施工技术规范和施工质量验收规范;3、作业指导书及有关施工质量、技术管理、安全生产、文明施工等文件。二、本施工组织设计为世博会城市之光主题演绎秀新建工程项目工程提供较完整的纲领性文件,指导工程施工与管理,确保优质、高速、安全、文明地完成该工程建设任务。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二章工程概况第一节总述一、工程概况工程名称:世博会城市之光主题演绎秀新建工程工程地点:上海世博园区临时剧场用地面积:6100平方米建筑面积:约6100平方米建筑层数:地上1层结构类型:钢网架结构。二、工程内容(一)网架:(二)门窗工程:(三)地面:1、细石混凝土地面。2、防滑地砖地面。3、聚氨酯彩色涂料地面。4、水泥砂浆地面。(六)顶棚:1、板底抹灰2、铝扣板吊顶(用于管理用房与公共厕所)(七)油漆工程:1、所有金属制品露明部分(除铝铜制品、电镀制品外),均刷防锈漆一度,深灰色调和漆两度;未露明部分刷防锈漆两度。2、室内木门框刷米黄色调和漆一底两度。3、公共楼梯木扶手刷棕色调和漆一底两度。2.2内墙:水泥砂浆找平层、水泥砂浆光面、乳胶漆饰面。3、顶棚:基层处理、白色乳胶漆饰面。三、结构部分:1、建筑结构安全等级及使用年限:1.1建筑结构安全等级——二级;nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计1.2设计使用年限——5年;1.3建筑抗震设防类别——丙类;1.4框架结构抗震等级——四级;第二节现场环境及施工条件一、气象条件据上海市气象台历年对气象特征值统计,属亚热带海洋性季风气候区,四季分明,温湿适中,雨量充沛,光照宜人。年平均气温为17.8℃,极端最高温度为40.8℃。平均每年降水量1680mm,雨水以梅雨和夏秋季为多,冬季较少。常年风向以NNE向为主,其平均风速达3.7m/s,次为NNW向,其平均风速达2.9m/s。每年夏季和秋季为台风季节。二、施工条件目前,“三通一平”、进出道路、施工用水水源、施工用电电源均已在积极准备中。第三节引用的规范及标准1、工程施工招标文件2、施工图3、踏勘现场所掌握的现场情况及答疑等会议纪要4、施工所在地的气象情况5、国家建设行业现行的规范、规程、标准及规定等6、国家现行的安全施工及文明施工的有关规定7、同类工程的施工经验8、工程所涉相关规范和标准(1)工程建设标准强制性条文——房屋建筑部分(2)《建设工程施工质量验收统一标准》GB50300-2001(3)《建筑装饰装修工程质量验收规范》GB50210-2001(4)《建筑给水排水及采暖工程施工质量验收规范》GB50242-2002(5)《建筑电气工程施工质量验收规范》GB50303-2002(6)《工程测量规范》GB50026-93(7)《建筑钢结构焊接规程》JGJ81-2002(8)《钢筋焊接及验收规程》JGJ18-2003nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计(1)《普通混凝土配合比设计技术规程》JGJ55-2000(2)《施工现场临时用电安全技术规程》JGJ46-2005(3)《建筑施工高处作业安全技术规范》JGJ80-91(4)《建筑机械使用安全技术规程》JGJ33-2001(5)《建筑变形测量规程》GB/T50262-97(6)《建设工程项目管理规范》GB50326-2001(7)《建设工程文件归档整理规范》GB/T50328-2001(8)《建筑涂饰工程施工及验收规程》JGJ/T29-2003(9)《混凝土泵送技术规程》JGJ/T10-95(10)其它相关配套图集、图况等nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第三章工程施工目标根据我方的质量方针和质量目标,结合本工程的重要性,本项目列为我方重点工程,要达到如下施工目标:一、质量目标确保本工程质量等级为一次性验收合格。二、工期目标确保140日历天完成合同约定的全部建设任务,争取竣工综合验收合格并力争提前完成。三、施工现场管理目标严格贯彻执行上海市人民政府关于建筑工地文明施工综合治理有关规定,积极落实文明施工的各项操作规程和措施,争创整洁有序的文明施工标化工地。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第四章施工管理组织方案及其保证措施第一节施工总体管理组织方案一、我们针对此工程项目成立工程项目部。公司的配套部门随叫随到,支持世博会城市之光主题演绎秀场馆的建设。二、我们郑重承诺:针对此工程项目,我们推选的项目班子一律持证上岗,并且配备项目经理对本工程质量、工期、安全、成本及文明施工全面负责,各施工管理职能部门分别在项目经理的带领下做到有计划地组织施工,确保工程质量、工期、安全等方面达到目标要求。三、本工程紧紧围绕“施工质量好、安全无事故、文明施工佳、施工速度快”和“高标准的科学管理,严要求的施工技术,重落实的措施手段,争一流的企业精神”进行部署。1、实行统一的项目经理负责制在项目经理的领导下,组织精干的管理班子,统一领导,统一归口,统一计划,统一调度,统一管理。2、确立合理的施工程序本工程大体可分为网架工程和舞台工程、装饰工程、安装工程、及室外附属工程五个阶段,为加快施工进度,各个施工阶段尽可能相应衔接,立体交叉作业。室内外装饰、门窗、楼地面等工程自上而下搭接流水施工,各配套工程按统一的网络计划,交叉作业,协调施工。3、发挥我方的协调优势整个工程施工采取场外预制和现场施工相结合方法。所需机具和施工力量由我方确保重点,统一调配。四、先结构、后装修,水、电、暖通、消防等安装紧跟土建同步进行”的总体施工原则,各主体施工同步展开,整体施工实行分区分段流水作业,分段结构中间验收。同时按工程量的大小、施工难度确定施工的重点、难点,在施工时各采取相应的措施。1、施工区域的划分前期网架结构及粗装修工程加快施工速度,尽早交付各专业机电设备班组安装。2、在整体工程施工中,安装工程要与网架工程nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计密切配合,安装应根据网架工程的施工进度同步上升,同时网架工程要为安装创造良好的施工条件和工作面。做到目标一致,行动一致,为实现目标共创良好条件,确保在140日历天内全部完成施工任务,交付代建商使用。3、各个施工班组在生产上互相独立,同时密切配合,合理进行流水作业。在施工时必须加强前方和后方的组织配合、机械调配、材料供应,合理有效地进行施工组织,确保前方施工需要,整个工程在项目经理全面领导下,形成一套完整的施工体系,使整个工程的建设有计划、有步骤地顺利进行。第二节施工管理组织保证措施一、网架工程与水、电、消防施工的协调配合1、协调施工:网架工程施工和水、电安装必须紧密配合,互相穿插,协调一致,以不影响网架工程进度为准。2、加强事前控制:在网架结构施工阶段,水电舞台各专业必须注意协调施工,合理利用网架工程搭设的脚手架。3、加强成品保护:照明电气系统,在网架结构施工中的护线管,开关盒均应位置准确、牢固,4、每周例会:每周由项目部经理负责召集各有关人员及职能部门就工程有关方面问题与代建商、协作单位采用例会形式进行协调。5、合理安排施工:合理安排施工的每个阶段,坚持按正确的施工顺序施工。6、联合检查验收:搞好网架与安装的联合检查验收工作,每项工程先由网架、安装联合自检,验收合格后申报建设单位、监理单位共同验收。7、奖优罚劣:从全局出发,密切各施工单位的协作关系,对配合施工好的个人、班组予以表扬和奖励;对配合施工差的进行批评,必要时给予处罚,直至退出施工现场。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计二、网架与专业施工队伍的协调配合鉴于本工程的特殊性,本工程的特殊分项工程必须由其它专业施工单位来完成,网架施工单位将积极配合建设单位,认真做好施工过程中的协调配合工作。1、资质管理:施工人员必须是其企业固定职工,不得乱招乱雇,其资质须满足施工质量要求,进场后提交职工花名册,以便核查,同时必须持证上岗,严格遵守工地各项规定。2、计划管理:专业施工计划管理包括进退场计划、交叉施工协调计划、水电使用计划等。专业施工队伍的进退场由专门的协调部根据总体施工网络的专业施工顺序和施工进度安排,提出详细的进退场计划,计划中列出专业项目合同工作量、计划施工周期、进退场日期、各专业与各施工单位的交叉工序安排。3、专业工序及交叉施工协调:专业施工队伍按计划进场后,按规定的工序施工,施工过程中或遇工序改变,协调部及时进行协调,经项目经理批准后执行。4、技术质量管理:项目经理部协助建设单位与监理单位管理专业施工单位的技术及质量工作。质检人员严格按照国家质量验评标准监督检查专业施工单位的工程质量,并提出提高专业施工质量的方法。三、总包与监理的协调配合1、严格执行监理审批的施工大纲:在施工全过程中,严格按照建设单位及监理师批准的“施工大纲”、“施工组织设计”进行对作业队组的质量管理。在作业队组“自检”和总承包专检的基础上,接受监理师的验收和检查,并按照监理要求,予以整改。2、对整个工程质量负最终责任:建立质量控制、检查、管理制度,并据此对各分包施工单位予以检控,确保产品达到优良。对整个工程质量负最终责任,任何作业队组工作的失职、失误均视为我方的工作失误。3、严格见证取样:nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计所有进入现场的成品、半成品、设备、材料、器具,均主动向监理师提交产品合格证或质保书,且按规定在监理见证下取样检测并主动递交检测报告,确保工程使用优质材料、设备。4、坚决服从监理的检查:按部位或分项、工序检验工程质量,严格执行“上道工序不合格,下道工序不施工”的准则,使监理师的工作顺利开展。对可能出现的工作意见不一的情况,遵循“先执行监理的指导后予以磋商统一”的原则,在现场质量管理工作中,维护好监理师的权威性。四、总包与作业队组(供应商)的协调配合项目部会同建设单位、监理单位、设计单位对拟定的作业队组(供应商)予以考察,并采用竞争录用方法,使所选择的作业队组(供应商)在资质、管理、经验上符合工程要求。责成作业队组(供应商)所选用的设备、材料必须在事前通过建设单位、监理单位和项目部的审定,严禁擅自代用材料和使用劣质材料。责成各作业队组(供应商)严格按施工总进度计划和《施工大纲》编制实施进度计划和施工方案,建立质保体系,确保“大纲”所规定的总目标的实现。各作业队组(供应商)严格按照项目部制定的总平面布置图“按图就位”,且按项目部制定的现场标准化施工的文明管理规定,做好施工现场的标准化工作。作业队组(供应商)进场前均与项目部签订合同,严格以合同之条款来检查落实作业队组(供应商)的责任、义务。我方将以各个指令,组织指挥各作业队组(供应商)科学合理地进行作业生产,协调解决施工中所产生的各类矛盾,以明确的责任制制度,来追究贻误方的失责,尽可能地减少施工中出现的责任模糊和推诿扯皮现象,避免贻误工期或造成经济损失。项目部不断加强对施工人员及各供应商的教育,增强全体施工人员对成品和半成品的保护意识,做到上道工序对下道工序负责,完工成品对代建商负责。五、总包与周边的协调配合1、服从周边领导,遵守周边纪律。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计组织职工认真学习有关交通、环境、治安等法规文件,坚决服从交通、环保、环卫、派出所、居委会的指导。2、积极参加联防等活动:积极参加如创建卫生城、治安联防等活动,并力所能及地做好各项配合工作。3、及时办理关手续:进场后专人办理有关暂住手续,及时通报施工人员名册情况。4、及时与周边联系,求得谅解:夜间不加班作业,不得已需适当延长工作时间,应及时与当地居委会联系,得到其支持谅解后,尽可能提前结束作业,尽量做到少扰民,不扰民。六、协调方式1、以阶段计划为依据:按总进度计划划定的控制节点,组织协调工作会议,检查本节点实施的情况,制订、修正、调整下一个节点的实施要求。2、以周时间为工作单元:由业主或监理牵头,以周为单位召开协调会,检查本周完成的工作情况,落实下周各项工作计划,解决施工中存在的有关问题。3、定期全面检查:项目部会同建设单位定期(半月)或不定期地组织对工程节点、工程质量、现场标准化、安全生产、计量状况、工程技术资料、原材料及电器具等检查,并制定必要的奖罚制度,奖优罚劣。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第五章施工管理网络及人员配备第一节施工管理网络图项目经理技术负责人项目副经理文明管理员现场、仓库预算员材料员资料员施工员质量员安全员砼班油漆班架子班网架专业舞台专业防水班机修班普工班钢筋班泥工班 nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二节质量管理体系网络图质监员建设、监理项目经理工程部公司总经理各班组(兼职质检员)施工员、项目质检员技术负责人、送检员nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第三节安全管理体系网络图施工员、项目安全员技术负责人、各班组(兼职安全员)安全员建设、监理项目经理安全部门总经理nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第四节工地治安管理网络图当地派出所各工种班组治安门卫夜间巡逻员治安值班员工地治安员保卫员工地项目负责人园区安委会公司nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计施工管理人员表项目主要成员组成表序号单位姓名职称现场承担工作1施工单位唐健屹一级建造师项目经理2吴联虹二级建造师技术经理3王明华安全员安全员4卢小丹施工员兼资料员施工员兼资料员5678nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第六章施工准备第一节施工现场准备1、场地平整及临时道路根据总平面布置,本工程为了给整个施工区域提供方便,施工现场道路均采用目前宝冶公司提供的临时道路。2、临时设施生产、办公设施的搭设,以整洁、简便、实用为原则,尽量精简现场临设,采用集装箱,用于现场办公和开会。为便于安全、文明施工管理,生活区域在施工区域场地外单独设置,生活区域内设置齐全的宿舍、食堂、卫生间、淋浴房、活动室等生活设施。3、控制点以规划单位提供的座标、水准点为基准,若需引测,则应经建设单位、监理单位复核认可,并做好保护措施。根据设计要求,及时在建筑物相应部位埋设水准观测点,并及时观测及整理。4、施工用电现场设备用电量结构施工阶段的设备用电量(详见机械设备表)要求现场设置3台变压器,每台输出功率达到300KW,(对焊等大功率设备尽量避开用电高峰期),即满足施工要求。施工用水根据建设单位提供的水源,用直径Φ100管子接入,然后按施工平面布置图要求敷设场内设施临时用水管线。每隔30M留一接头供接支管用,主干线埋入地下50cm作为冬季防冻需要,施工用水采用30米长的橡胶管和给水管连接供水。5、主要材料供应施工所需的主辅材料,无论甲供和自行采购,均先按图提出概算用量的备料计划,然后详细制订主辅材料、预制件及零配件的供料计划,有计划采购供应,做到及时组织供应,严格材质检验。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二节技术组织准备措施1、熟悉图纸本工程施工工期紧,因此接到图纸后,将立即组织有关人员熟悉、会审图纸,领会设计意图,研究施工方法,提出合理化建议,减少施工中的问题和矛盾,保证工程施工顺利开展,要求各施工员严格按图纸施工,按规范操作。2、编制主要分部、分项的施工技术方案脚手架工程、网架工程、门窗工程、舞台工程、机电安装及装饰工程等均在本施工组织设计基础上,根据工程进展的实际情况编制、修正、补充、完善。并根据施工方案和作业指导书全面交底,认真贯彻。3、密切建设(监理)单位与施工单位的配合图纸资料及设计变更联系单,由建设单位按规定数量及时提供,施工与设计的相关事宜,由建设(监理)单位协调。在施工过程中,工程质量验收、材料复试、试运转等请建设(监理)单位人员参加。4、实行样板示范检验制重要部位、关键工序应坚持做样板、定措施,按照设计和规范要求明确标准,对照检查。做到标准统一,工艺一致,质量稳定,细部精致,色泽协调。5、加强成品保护(1)建设单位、监理单位、施工单位共同协调,制订措施,加强成品保护。(2)材料进场按指定部位合理堆放,重要材料点数计量,专人保管,保温、易燃、易碎材料注意防水、防火、防潮等。(3)已完门窗框、楼梯踏步、地面、墙面及各类装饰装潢和安装管道设施均采取保护措施,做好交接手续。能封闭的及时封闭,并设专人看管。(4)配合土建预埋的强弱电保护管及给排水管道上的管口都采取临时封堵措施,以防杂物进入。并对已安装的成品、半成品要配合保卫部门严格防范、监护、以防偷盗、损坏,消防箱、配电柜等安装后,及时关好箱门。6、做好技术档案管理nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计测量定位、预埋预设、隐蔽验收、设备检查、调试记录、材料试验、质量评定、会审记录、技术复核、设计变更、质量处理等各类资料一经形成即行积累、整理、立卷保管,切实做到竣工资料齐全、准确、可靠。同时,本工程严格实行施工日志制度和做好班组施工记录,有关部门定期进行检查。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第七章现场总平面布置根据总平面布置为加快施工进度缩短施工工期,方便施工中设备安装的穿插,每个工程项目部分别设立独立的施工机械设备,以大大加快工程的施工速度,又互不影响。施工临时用电采用埋地三相五芯线,设标准配电箱,实行三级漏保TN—S保护。临时用电采用埋地金属管接地。用水根据需要,沿水线敷设多个临时消火栓,仓库、办公等临设设置干粉灭火器。本工程根据各阶段不同的施工特色和现场平面布置的要求,分阶段分布总平面图,以提高总平面管理工作的有效性,加快施工进度。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第八章施工进度网络计划及单项进度安排按建设单位招标要求在保证质量前提下努力加快施工进度,缩短工期,根据施工顺序与施工规律,结合本工程特点,科学选取关键线路,编制进度网络计划。我方确保140日历天内完成建设项目全部工作内容,并力争提前完工及确保工程质量达到国家验收规范要求,一次性验收合格。具体详见附页中施工进度计划网络图及单项进度安排表。为科学组织施工流水作业,加快施工进度,提高施工效率,并最大限度地利用工作面,先主体,后装修施工原则,合理安排各施工区段内的施工作业流程,为质量、进度、安全、文明施工等各方面进行相互促进,形成你追我赶的良好局面。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第九章劳动力、主要物资、机械设备和临时设施布置配备计划第一节劳动力供应计划我方将指派精干施工班子进场施工,选择技术水平和综合素质高及做过同类工程有丰富施工经验的施工班组。现场施工人员的需用量和各专业工种的人员搭配,根据总进度和分段进度计划在各施工阶段工程量的大小和作业时间的长短进行合理安排,即做到各工种均衡兼顾,防止人员的大起大落。劳动力配备计划序号工种网架工程舞台工程机电工程装饰工程高峰期人数人数班组人数班组人数班组人数班组1架子工681////682网架专业701////703舞台专业//451//454木工//////281285泥工//////251256油漆工////201207电工241841288防水工//////4149电气工4141201413210管道工////201612611电焊工2016161613912普工201302302213其他工nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二节施工机械设备配置计划序号机械设备名称规格型号数量国别产地制造年份定额功率(KW)计划进场时间1交流电焊机DX1-33020国产200723开工进场2木工刨床MB-5033国产20082.2开工进场3木工锯床MJ2253国产20082.2开工进场4临时配电箱总分配20国产2009/全过程5高压镝灯3.54国产20093.5开工进场工程开工以后上报供应计划,根据工程进度需要,随时组织进场安装,各类施工机械及仪器配备如下表:质量检测仪器配置一览表序号名称规格型号数量检测、测量范围1激光经纬仪JJ2a1台工程导线测量2光学经纬仪J21台工程导线测量3水平仪S21台三等水准4台秤TGJ-1000A1台1T5长度检测器JGW-50210把50m6长度检测器GW-55810把5m7长度检测器GW-30310把3m8垂直检测尺JZC-210把表面垂直度9内外直角检测尺JZC-210把墙柱阴阳角10对角检测尺JZC-210把门窗安装11游标塞尺JZC-22把表面平整12百格网JZC-22把砂浆泡满度13小铁锤JZC-220把整体、块料面层密实度nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第三节施工主要物资供应计划1、本工程主要物资的供应,由预算人员计算出主要材料的数量,根据工程部位及进度,由我方材料部门统一采购、供应。2、物资采购供应按计划联系采购和订货,严格控制质量。3、按工程进度需用量提出材料进场入库日程,并及时组织材料进场验货(质量和数量)4、各种材料分批进场数量及时提交各种质保书和出厂单,货、单符合。5、周转材料供应具体见下表:周转材料供应计划表序号周转材料名称单位网架舞台装饰施工阶段总需用量1钢管T201010402扣件千只42283脚手片块4000200020008000nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第四节材料、设备质量保证措施1、我司会详细编制各种材料及施工周转材料的需用量计划和分批进场时间,并按照分批进场时间及时组织进场,按照施工总平面布置图指定的位置堆放整齐。2、采购质量保证计划(1)项目经理部在项目分项分部工程施工前,依据施工进度计划和《合格物资分供方名录》,编制物资采购计划,并由项目经理审批。(2)物资采购计划注明物资名称、规格、数量、供应时间、质量标准或质量要求以及拟选用的分供方。1)凡有标产品标明类型、型号等级和标准编号;2)凡非标产品标明规格、图纸、标样等。3、为便于材料供应商及时备料,中标后5天内向供应商提供不同规格的材料需用量及供应时间要求。4、对在工程中使用的设备,设立专人管理保养及操作,每日下班后都做到清洗干净。5、工程材料进场后,及时提交出厂合格证或质保书,需要进行复验的材料及时通知技术部门和监理单位进行材料取样复验,经复试合格并经监理单位认可后挂牌使用。材料的出厂合格证和试验报告及时送项目技术部门妥善保管。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第十章主要分部分项工程施工技术方案第一节测量控制1、轴线控制按照业主提供的建筑红线及规定定位基准点,测设主控制轴线于施工现场,作为工程轴线控制依据。由于本工程造型各异,拟采用多点矩形控制网与角度前方交会法相互补测的控制网,作为控制轴线和施工放样的依据。根据本工程的地理环境,采用外控法控制建筑物的垂直度,即在建筑物外设立控制网,在组成控制网的控制点上进行竖向投测,将控制轴线传递至任一楼层,对建筑物进行垂直控制和施工放样。控制网的布设由基准点测至建筑物附近,作为垂直度和施工测量的首级控制,再由首级控制点在建筑物施工范围内布设次级控制点,作为放样及检核的依据。2、高程控制高程控制由场地水准点引测至建筑物,并标±0.000标记。标高传递利用钢尺直接丈量,四角标高复核后,于每层柱墙面弹0.500m线,作为该层墙身砌筑、门窗安装、地坪、吊顶等标高的控制依据。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第六节脚手架工程一、工程概况本工程为地上一层,钢网架结构,最高处16.8米。二、施工方法根据本工程特点决定均采用扣件式满堂钢管脚手架。三、脚手架设计1、钢管落地架采用建筑钢管Φ48mm,壁厚3.2mm,立杆横距为1.5m,步距根据标高确定控制在1800mm以内,立杆纵距为1.5m,采用0.8*1.3m竹脚手片。钢管选用外径48mm,壁厚3.5mm,A3钢管,表面平整光滑,无锈蚀、裂纹、分层、压裉、划道和硬弯,搭设架子前进行保养、除锈并统一涂色,立杆采用黄色,底排架子及扫地杆、防护栏杆、剪刀撑采用红白漆。钢管脚手架搭设防护扣件采用与钢管配套的,可锻铸铁、无裂缝、气孔、缩松、砂眼等锻造缺陷,贴和面平整,活动部位灵活,夹紧钢管时开口处最小距离不小于5mm。2、脚手片与防护栏杆脚手片必须不细于18#铅丝双股并联绑扎不少于4点,要求绑扎牢固,交接处平整,无探头板。脚手片完好无损,破损的要及时更换。3、小横杆与大横杆设置按立杆与大横杆交点处设置小横杆,两端固定在立杆确保安全受力,小横杆两端各伸出立杆长度不少于10m,并保持一致。大横杆宜设置在立杆内侧,长度大于3跨,纵向水平杆应采用直角扣件固定在横向水平杆上,并应等间距设置,间距不应大于400mm.4、构造要求钢管脚手架立杆必须采用对接,大横杆可以对接和搭接,剪刀撑和其它杆件采用搭接,搭接长度不小于1m,且不少于三只扣件紧固。相邻杆件搭接、对接必须错开一个档距,同一平面上的接头不得超过50%。四、交底和验收nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计脚手架搭设前对架子工(架子工必须持证上岗)进行安全技术交底,交底内容有针对性,交底双方履行签字手续。脚手架搭设后由有关职能部门组织分段验收(每搭三步架验收一次),办理验收手续,验收表中写明验收的部位、结果等,验收人员履行验收签字手续。并在验收合格后挂上合格牌方可使用。对脚手架进行定期和不定期检查,并按要求填写检查表,及各项内容,履行检查签字手续,对检查出的问题及时进行整改,项目部每半月进行检查并有书面记录。五、脚手架的搭设与拆除脚手架的搭设:1、所有作业人均要技术培训合格持证上岗。2、搭设顺序:放垫块立杆大横杆小横杆扫地杆防护栏杆踢脚杆脚手板验收。3、搭设要点搭接不得在同一水平线或垂直线应错开参差布置。脚手板必须步步满铺,并不少于三步。4、脚手架拆除拆除的顺序正好与搭顺序相反,自上而下逐步拆除一步一清,不准采用踏步式拆法,严禁高空抛掷,拆下钢管扣件应分类堆放。六、安全措施1.搭设前应严格进行钢管扣件选择,凡严重锈蚀、薄壁、弯曲、变形、裂缝及螺栓、螺纹已损坏的钢管扣件严禁使用。2.分段搭设:分段验收,未经验收合格的脚下手架不得使用。3.不准在脚下手架上堆放多余的钢管、钢模等材料。严禁在脚手架处攀高上下,及在上面往下抛物。带电线路无安全措施一律不准通过脚手架。严格控制脚手架的施工荷载。采用材料:建筑钢管Φ48mm,壁厚3.2mm,钢管间用扣件质量按建设部钢管脚手架扣件标准要求,规格与钢管配套。脚手片采用0.8*1.3米竹脚下手片。搭设参数:立杆步距取1.8米,立杆纵距La=1.5米,立杆横距Lb=1.5米。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第十四章装饰工程施工技术方案为了能保质、保工期完成装修工作,项目经理部将精心组织吊顶、隔墙、面砖、木做、涂料等多种专业班组,施工前,对各作业班组进行详细的技术交底和必要的操作培训,施工中保持人员稳定。一、主要工序交叉施工原则及措施1.工作交叉装修插入后要与结构工作适当隔离,划分区域、有一定的独立性,避免过多的干扰。应以不影响结构施工为原则。2.装修与水电安装之间的交叉施工装修与水电通风之间的交叉施工较多,交叉工作面大,内容复杂,如处理不当将出现相互制约,相互破坏的不利局面,解决的原则为:2.1在技术准备阶段就把装饰、安装的协调图绘好,如卫生间、吊顶等协调图,各专业根据该图纸安排施工,不得打乱施工顺序抢先施工,造成双重破坏,留下质量隐患,每个分项工程的协调图应包括水、电等安装专业有关工作,协调图绘好后,应按《文件控制程序》执行。进行审批、修改与分发工作,使各专业有关人员做到心中有数。3.2各专业人员根据协调图进行施工。每天上午8:30开碰头协调会,安排同一工作面上有关专业的施工顺序问题,并形成会审纪要,每个专业进入工作面上施工,必须有上道工序传来的专业会签单,和项目部的“施工许可证”方可进行施工。3.3做好总进度控制计划。水电安装应根据计划合理进行穿插作业,要在统一的协调指挥下施工,使整个工程形成一盘棋。3.4明确责任,划分利益关系,建立固定的协调制度。3.5一切从大局出发互谅互让,水、电、安装各专业要尽可能为对方创造施工条件,并注意保护对方成品和半成品。二、主要分部工程1、在室内,原则上按先上后下,先内后外的施工顺序,每道工序完成后,必须经专业人员按验收标准严格检查验收后,才能转到下一道工序施工。2、在施工中每层每个房间都要提供,标高线(50cmnthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计线)和十字中心线。(十字中心线既弹在地板上,又弹到顶棚上,十字线上下一致)以供土建、装饰和机电安装等专业共同使用,方便施工。3、房间装修施工顺序:放线→穿套管→墙面修整→安电器管线盒→顶棚腻子→乳胶漆→设备、开关安装→墙面饰面→地面饰面板施工。4、卫生间装修施工顺序:放线→机电管线→墙、地面孔洞修整(第一次灌水实验)→地面防水(第二次灌水实验)→防水保护层→地面防滑砖(第三次灌水试验)→墙面瓷砖→卫生洁具→电气安装→五金配件→门油漆。5、内墙涂料施工由于混凝土表面平整、光滑,局部进行修补后可进行刷乳胶漆。施工要点:基底应干燥,否则会影响涂料颜色均匀一致。涂料应符合设计及规范要求。乳胶漆涂刷前门窗框应进行保护,以防污染。涂料应随用随开,尽量一次用完。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第一节内墙装饰内墙面装饰施工工艺程序墙面清除余灰选做样板立门窗框做坍饼冲筋墙面浇水湿润砂浆拌和运输砂浆层刮糙第二层砂浆随括随抹平干燥后批刮腻子涂料(面砖)选料成品保护及干燥墙面排列弹线由上至下由里往外贴面砖做样板外墙刷涂料质量自查嵌缝及清理成品保护验收成品保护nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计1、内墙抹灰1.1做水泥护角室内墙面、柱面的阳角(高度不低2米),应作水泥护角,作法一般应采用1:3水泥砂浆打底,1:2水泥砂浆罩面,压光做明护角,护角厚度与墙面一致,一般做小圆角,待面层砂浆收水稍干后用专用工具(呈小圆角的)捋成。如做成尖护角,观感挺直有力,但使用功能差,不宜采用:水泥护角的宽度在墙面、柱面的阴角部位,每侧宽度为50mm,水泥护角表面光滑垂直,与抹灰墙面面层接槎平顺,手摸有捋感,清晰美观。1.2抹底灰墙面抹底前,先有清理基层,提前一天浇水湿润墙面,确保砖墙浸水深度达8-10mm,对基层凹凸较大的部位,必须剔凿铺平,过深凹坑要提前浇水,湿润墙面后分层补平(不要一次完成,以免产生墙面收缩裂缝),然后找规模,贴灰饼,墙面冲筋一般情况下,冲完筋二小时后即可抹底灰(间隔时间不宜过长),先薄薄抹一层底子灰。接着抹第二遍与冲筋找平(中层),用大杠刮平,对底子灰作全面检查(及时做好跟踪检查工作),查看底子灰是否平整,阴阳角(中级抹灰阴角方正不要检查)是否方正,阴角交接处,墙面与顶板交接处是否光滑平顺,必要时用靠尺刮平,用阴角器槎平顺,使室内四周做到方正顺直。做好与安装装顶的配合。在做墙面抹灰时,要对已完成的地面踢脚线、水泥墙裙等成品做妥善保护。1.3抹罩面灰待底子灰六、七成干时,即可抹罩面灰,罩面也应两遍完成,赶光压实,最后宜用塑料抹子压光,以做到不漏压,不漏底,表面光滑洁净,接槎平整,线角顺直清晰为好,对孔洞、槽、盒和管道后面的细部,更要精心捷足先登,务必做到边缘镶贴整齐,光滑,管道后面平整,并与基它分墙面观感一致。1.4顶棚抹灰顶棚抹灰前应做完上一层地面及平屋地面,将顶清扫干净,对光滑的基层面进行凿毛,或做“毛处理”nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计,顶板砼如有峰窝麻面缺陷要用1:3水泥砂浆预先修补平整,凸出部位也要剔凿平整,管道水电预先安装的管线要有保护,顶棚抹灰前在靠近顶板的四周墙面弹出一条水平线,作为顶棚抹灰的水平控制线,然后按设计要求的作法分层抹压,做到表面顺平压光压实,不得有抹纹、气泡、接槎不平等现象。顶棚与墙面相关的且阳应呈角线,与管道交接处要顺平,这类顶棚宜采用在砼基础层上直接刮腻子刷浆的作法,效果较好。2、室内涂料工程饰面为防止影响涂料层的质量及预期的装饰效果,不仅要了解涂料的标准、型号、性能和用途外,还要掌握涂料在使用上的四大配套性:涂料与基层表面的配套,各涂料层间的配套,涂料与溶剂,助剂的配套,涂料与施工方法的配套。2.1涂料对基层湿度的要求;基层表面含水率≤10%。2.2涂料配套材料——腻子。在涂料涂刷前,先用白乳胶:滑石粉:2%羧甲酸纤维素溶液=1:5:3.5(重量比)配制的腻子将基层表面的缺陷,不平之处嵌实填平,并用砂子打磨光滑平整。2.3抹灰面基层处理:用毛刷、铲刀等工具清理灰尘、砂浆溅物、流痕等,找平和修补空鼓、酥松、起皮、起砂等缺陷。对于露筋将露出钢筋头用砂轮打平,然后涂刷二道防锈涂料。2.4涂刷涂料:环境应当清洁干净,余相关工程须全部完工,环境湿度≤60%,温度≥±10℃,遇有大风、雨雾及基层表面不干燥,应停止施工。设立样板间,直保存到竣工为止。具体施工工序:清扫→填补缝子→局部刮腻子→砂皮磨平→第一遍刮腻子→磨平→第二遍刮腻子→磨平→第一遍涂料→填补腻子→第二遍涂料→局部涂料。3、内墙瓷砖墙裙施工3.1底子灰抹完后,一般养护1-2d方可镶贴面砖。3.2统一弹线分格.排砖,确定缝子的大小,做米厘条,一般控制在8-10mm。3.3用面砖做灰饼,找出墙面.柱面.门窗套等横竖标准,阳角处要双面排直,灰饼间距不应大于1.5m。3.4nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计镶贴时,在面砖背后满铺粘结砂浆,镶贴后,用小铲把轻轻敲击,使之与基层粘结牢固,并用靠尺方尺随时找平找方。贴完一皮后须将砖上口灰刮平,每日下班前须清理干净。3.5在砖镶贴完成一定流水段落后,立即用1:1水泥砂浆(砂子需过窗纱筛)勾缝。3.6整个工程完工后,可用浓度10%稀盐酸刷洗表面,并随即用水冲洗干净。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二节外墙装饰1、外墙抹灰1.1施工准备1.1.1抹灰前,清除基层表面的灰尘、污垢和油渍等,并洒水湿润,满刷界面剂一道。1.1.2在砌体与梁、柱结合处钉挂300mm宽1.2×9的钢丝网,用射钉每200mm加铁片固定,挂网应做到平整、牢固。1.1.3抹灰用的原材料必须试检合格。1.2操作流程基层处理→浇水湿润基层→找规矩、做灰饼→设置标筋→阳角做护角→抹底灰、中灰→抹窗台板、墙裙或踢脚板→罩面→清理。1.3施工要点1.3.1找规矩用一面墙做基准先用方尺规方,在地面上先弹出十字中心线,再按墙面基层的平整度在地面弹出墙角线,随后在距墙阴角100mm处吊垂线并弹出垂直线,再按地上弹出的墙角线往墙上翻引,弹出阴角两面墙上的墙面抹灰层厚度控制线,以此确定标准灰饼厚度。1.3.2做灰饼在墙面距地1.5m左右的高度,距墙面两边阴角100-200mm处各做一个5O×50mm的灰饼(采用材料与抹灰墙面相同),再用线锤以此饼面挂垂直线,在墙面的上下各补做两个灰饼,灰饼离顶棚及地面距离200mm左右。再用钉子钉在左右灰饼两头墙缝里,用小线拴在钉子上拉横线,沿线每隔1.5m补做灰饼。1.3.3冲筋在灰饼间抹灰(水平方向)厚度、宽度与灰饼同。上下水平冲筋应在同一垂直面内。阴阳角的水平冲筋应连起来并应互相垂直1.3.4护角护角做在室内的门窗洞口及墙面、柱子的阳角处。护角高度2m,每侧宽度大于50mm,采用1:2水泥砂浆抹护角。1.3.5抹底灰待标筋有了一定强度后,洒水湿润墙面,然后在两筋之间用力抹上底灰,用木抹子压实搓毛。底灰要略低于标筋。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计1.3.6抹中灰待底灰干至七成后,即可抹中灰。抹灰厚度稍高于标筋,再用木杠按标筋刮平,用木抹子搓压,使表面平整密实。1.3.7抹面灰待中灰干至七成后,即可抹面灰。如中灰过干应浇水湿润。先在墙面上用钢抹子抹砂浆,再用刮尺刮平,然后再进行抹平。1.3.8清理抹灰完毕,要将落地灰及时清除,打扫干净。1.4抹灰质量要求:一般抹灰的允许偏差和检验方法项次项目允许偏差(mm)检验方法1立面垂直度4用2m垂直检测尺检查2表面平整度4用2m靠尺和塞尺检查3阴阳角方正4直角检测尺检查4分格条直线度4拉5m线,用钢直尺检查5墙裙上口直线度4拉5m线,用钢直尺检查2、外墙涂料2.1外墙面涂料涂刷工程施工工艺为:墙面基层处理→弹线、分格、粘条、涂刷准备→刷涂→起分格条→养护。2.2基层处理:基层为预制混凝土时,应事先将其缺棱角的板面上凹凸不平处刷水湿润,修补处刷掺水重10%107胶的水泥浆一道,随后抹1:3水泥砂浆勾抹平整。基层为砖墙、现浇混凝土墙避的基层抹灰,应按外墙抹水泥砂浆工艺执行。水泥砂浆面层要求大杠刮平,木抹子搓平,表面无孔洞、无砂眼,面层颜色均匀一致,无划痕,面层垂直度、平整度应符合施工规范规定要求。2.3根据图纸要求分格、弹线,并依据缝子宽窄、深浅选择分格条,粘条位置要准确,要横平竖直。喷涂施工时,应将不需要施涂的部位遮挡好,防止造成污染。2.4涂刷准备:检查处理基层空鼓及表面有无沥青、白灰膏等油污,同时清除混凝土渣。涂料浆可预先配制,也可在施工现场临时配制。配料比要准确,调匀,静置4皮上,涂刷前要充分搅拌。2.5刷涂:应选择好天气施工,白天墙体基面温度在5℃nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计以上,夜间墙体基面温度在0℃以上,以防固化不好受冻。施工后12H内避免着雨。同一分格条块之间应自左至右横向刷涂,切不可无规则乱刷。要与其他部位厚度一致,以保持颜色一致。门窗、玻璃等不刷涂部位,若已溅上涂料要及时用湿布擦净。喷头、勺子、搅拌器和桶以及档板等工具要及时用水刷洗干净。2.6起条、修理、勾缝:喷完后及时将分格条起出,并将缝内清理干净,根据设计要求勾缝。3、外墙局部干挂花岗石施工3.1根据设计尺寸,进行石材钻孔。石材背面刷胶粘剂,贴玻璃纤维网格布增强。3.2按大样图要求,用经纬仪测出大角两个面的竖向控制线,在大角上下两端固定挂线的角钢,用钢丝挂竖向控制线,并在控制线的上.下作出标记。3.3支底层石材托架,放置底层石板,调节并暂时固定。3.4结构钻孔,插入固定螺栓,镶不锈钢固定件。3.5用嵌缝膏嵌入下层石材上部孔眼,插连接钢针,嵌上层石材下孔。3.6临时固定上层石材,钻孔,插膨胀螺栓,镶不锈钢固定件。重复工序4和5,直至完成全部石材安装,最后镶顶层石材。3.7清理石材饰面,贴防污胶条、嵌缝、刷罩面涂料。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第三节楼地面工程一、室内地砖、瓷砖镶贴工程基层必须清理干净,露出混凝土的本色,粘结材料选用8407胶,此胶自身有较好的防水性能,粘结效果良好。操作要点:1.地砖及瓷砖使用前要精心挑选,按大中小分类,并挑出不合格品,分类后在清水中浸泡24h阴干备用。2.镶贴前进行试排,确保接缝均匀。同一墙面上的横竖排列均不得有一行以上的非整砖行,非整砖行应排于次要部位或阴角处。3.墙面排砖由门口向里排,内侧阴角处允许出现半砖,但不允许出现半砖以下的条砖。内窗口两侧要对称,窗台下口尽量避免出现半砖。铺贴范围要弹线规方,按其标高要求先铺贴标砖,标砖可条形布置。砖缝控制宜为2—3mm,嵌缝材料应根据砖的颜色而定,涂色砖要使用与砖近似的颜料调制的胶泥。4.镶贴时如遇突出的管线、灯具、卫生设备的支撑架等,应用整砖套割吻合,不得用非整砖拼凑,镶贴墙裙、浴盆、水池等上口和阴阳角处时,应使用配件砖。5.铺好的地砖要注意成品保护,控制上人时间,避免强烈震动。二、细石砼地面施工1、当铺设细石砼时,其表面应粗糙,洁净和湿润,并不得有积水现象。2、细石砼应采用机械搅拌,必须拌合均匀。3、铺设前应按标准水平线用木板隔成宽度不大于3m的条形区段,以控制面层厚度。4、铺设时,先刷以水灰比为0.4-0.5的水泥浆,并随刷随铺砼,用刮尺找平,浇筑水泥砼的坍落度不宜大于30mm。5、细石砼采用人工捣实时,滚筒要交叉滚压4-5遍,直至表面泛浆为止,然后进行抹平和压光。6、水泥砼面层不宜留置施工缝,当施工间歇超过规定的允许时间后,在继续浇筑砼时,应对已凝结的砼接搓处进行处理,用钢丝刷刷到石子外露,表面用水冲洗,并涂以水灰比为0.4-0.5nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计的水泥浆再浇筑砼,并应捣实压平,使新旧砼接缝紧密,不显接头槎。7、砼面层应在水泥初凝前完成抹平工作,水泥终凝前完成压光工作。8、当面层表面出现渗水时,可加搅拌的水泥和砂进行撒匀,其水泥和砂的体积比重为1:2-1:2.5(水泥:砂),并进行表面压实抹光。9、水泥砼面层浇筑完成后,应在12h内加覆盖和浇水,养护时间不少于7d,浇水次数应保持砼具有足够的湿润状态。三、水泥砂浆地面施工1、铺设水泥砂浆面层时,基层表面应粗糙,洁净和湿润,并不得有积水现象。2、水泥砂浆应采用机械搅拌,拌和要均匀,颜色一致,搅拌时间不应小于2mm。3、施工时,先刷水灰比为0.4-0.5的水泥浆,随刷随铺随拍,并应在水泥初凝前用木抹搓平压实。4、面层压光宜用钢皮抹子分二遍完成,并逐遍加大用力压光,压光工作应在水泥终凝前完成。5、水泥砂浆面层铺好后一天内应覆盖,并在7-10d内每天浇水湿润进行保养。6、对卫生间和厨房间的地坪在施工完成后按规定做盛水试验,并做好盛水试验记录。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第四节油漆工程1、配料:每工程所用油漆应有专人负责集中配料,以求得保证颜色一致。2、样板制作:不同品种不同颜色均应根据设计与图纸要求规定,必须先做油漆深浅不同样板,再配样油漆,同时要做好深浅不同油漆配方计量记录,并编好号留出油漆样品。根据认可的样板和样板油漆计量记录配制油漆材料,配料时要对照与留样油漆是否相同。符合后方可装桶备运。3、一般操作要求:打磨砂皮应顺木纹砂磨,对有的部位如横向砂磨后,最后应顺木纹砂磨平整,各道腻子面上打磨要掌握“磨去残存,表面平整”,“轻磨慢打,线角分明”;要掌握嵌批洞要求的腻子、稠稀和需要的硬度。应做到批刮嵌实饱满,残余腻子要收净;配料要掌握“有余而不多”,“先浅而后深”,“少加而次多”的操作要领。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第十一章安全生产、文明施工管理保证措施第一节安全生产管理保证措施本工程安全规章制度及有关安全职责如下:一、施工现场安全管理制度1、开工前办理所有从事危险作业人员的保险,各特殊工种作业人员均需执上岗证上岗,无证人员不得从事特殊工种作业(后附特殊工种上岗证)。2、制订施工方案时,编制详细的现场施工平面布置图,对运输道路,临时电力网,各种其他临时建筑设施的安排符合防火、安全、卫生、以及有关规程的要求。3、施工现场变配电设施和架设电线悬吊高度,与电业部门取得联系,按规定执行。4、施工现场交通运输道路,经常保持畅通,运输频繁的交叉路口,设临时交通指挥人员及临时标志。5、施工现场内如有深坑和施工中预留洞孔等处,设立防护设施或设置危险标志,以示警告。6、开挖土方之前,事先向建设单位主动提出,并会同建设单位与地区的供电、供水、煤气、电讯等部门联系,摸清地下是否有电缆、水管、煤气管、通讯网等,如影响施工安全的,催促建设单位负责迁移,创造施工条件,防止触电和损坏管道,确保安全施工。7、在编制生产计划和施工方案时,同时编制安全技术措施计划,改善劳动条件,防止伤亡事故发生。8、在施工过程中,如生产进度和安全工作发生矛盾时,首先服从安全,如现场发生险情时,各级领导及施工人员,立即坚决的予以制止及纠正,绝对不听之任之不负责任。9、施工现场做好落手清,拆除的模板、钢管等物及时整理堆放,大批量模板、架子拆卸时,现场设专人监护。二、施工生产安全技术措施管理制度1、所有施工组织设计(施工方案),均有安全技术措施,特殊工程编制单项安全技术措施。2、nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计根据文明生产的要求和施工平面的布置,对现场材料堆放、管道铺设、电线架设、机械道路、仓库和其他临时设施的场地安排,做到符合安全规定,并有可靠的安全设施。3、逐级进行安全技术交底工作。开工前,技术负责人将工程概况、施工方法、安全技术措施等情况,向全体职工进行详细交底,两个以上施工队或工种配合工作时,项目经理和施工员按工程进度,定期或不定期的向有关班组长进行交叉作业的安全交底,班组长对班员进行施工要求、作业环境的安全交底。4、加强对防暑降温、防寒保暖、防台风、防雷电、防毒等设施的检修,制定抢险和防范措施,改善劳动条件。5、施工现场安全设施严格执行《建筑施工安全检查评分标准》JGJ59-99和各级有关安全生产、文明施工的规定。6、自觉遵守安全生产六大纪律,严格执行十项安全技术措施。7、施工现场用电符合建设部JGJ46-2005《建筑施工临时用电安全技术规范》,严格执行“三相五线制”、“一机一闸一漏保”原则。8、井字架搭设所用的材料和搭设方法,做到符合安全要求,严格按照建设部JGJ88-92《龙门架井字架物料提升机安全技术规范》进行搭设。9、易燃易爆物品不同氧气混放,堆放保证有一定的安全距离和隔离措施。10、坑槽施工,按规定放坡,并经常检查边壁土质稳定情况。11、高空作业时,不穿硬底和带钉易滑的鞋靴,上下时,不攀登脚手架及井字架。三、安全教育制度1、加强安全生产宣传教育,提高干部、职工对安全生产的思想认识,切实有效地进行法制和遵章守纪教育,进行法令、法规教育,广泛宣传劳动保护条例。2、加强暑季、冬季、雨季、夜间施工和节假日前的安全生产教育,使职工牢固树立安全第一的思想,自觉遵守安全生产操作规程和安全生产规章制度。3、宣传教育的方法:利用报纸、黑板报、录像、安全标语等多种途径进行宣传,表扬安全生产的先进事迹,真正使干部、职工认识安全生产的重要性,懂得安全生产、文明施工和有关科学知识,努力做到人人重视安全生产。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计4、新工人必须经过三级(公司、项目部、班组)安全教育,经考核合格后,才能准许上岗操作,教育内容包括安全技术知识、操作规程、机械设备性能等;教育累计时间在30小时以上;教育者和受教育者须本人签名方可通过。5、班组长或安全员要经常性的介绍分析各操作岗位的作业环境,本岗位易发生事故的不安全因素及使用机械设备、工具的安全要求,并提出其防范对策。6、对特殊作业人员,都要进行安全技术培训,并经考核合格取得操作证后,方可独立操作,持证人员每二年须进行一次复审培训。特殊工种包括:电工、焊工、司炉工、起重工、起重机司机、起重机指挥、登高架子工等。7、在遇采用新工艺、添置新设备或调换工作岗位等情况,及时进行操作方法学习和岗位安全教育。8、积极组织参加上级有关部门组织的业务培训和学习,配合上级部门的考核、发证工作。四、安全生产检查制度1、坚持六查制:查领导、查思想、查制度、查纪律、查现场、查隐患。2、坚持月查、旬查、日查和抽查。每月由指挥部安全生产领导小组进行一次性检查;每旬项目部组织有关人员进行一次检查;班组则应每日进行检查;各级安全员要经常深入工地进行抽查。3、检查依据:《建筑施工安全检查标准》JGJ59-99和各级有关文明施工、安全生产的规定。4、检查重点:4.1检查各项安全制度、措施落实情况;4.2检查现场安全防护规范执行情况;4.3检查施工人员的安全行为和文明施工及用火安全,发现隐患及时提出整改意见,并要求被检查者定人、定时、定措施进行整改;对查出的隐患,不能立即整改的,要建立登记、整改、检查、销项制度;在隐患没有消除前,及时采取可靠的防护措施,如有危及人身安全的紧急情况,立即停止作业。通过检查推动各项制度的落实。五、施工现场安全生产奖罚制度nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计1、职工进入施工现场都要遵守安全技术操作规程,服从专职安全员的统一指挥,违者罚处50元。2、进入现场必须戴好安全帽,正确使用好劳动保护用品,不戴安全帽的人员(或未扣牢帽带者)禁止上岗工作和给予罚款20元/次处理。3、高空作业时,不准往下或往上乱抛材料、工具等物,违反或造成后果者,根据情节轻重分别承担部分或全部责任。4、禁止施工现场穿拖鞋、高跟鞋、赤脚、赤膊和带小孩,违反者将处罚20元/次。5、禁止不懂电气或机械人员使用和玩弄机械及电气设备,违反者将处罚50-100元,并赔偿相应损失。6、禁止在工地明火烧饭菜、拷火、玩火等,违者将没收餐具并处罚50-100元。7、禁止在架子上睡觉,违者将罚款50元/次。8、禁止在工地内用电热快(除规定允许使用外)。违者将没收此物,并处以20元罚款。9、连续发生三次违反上述规定的将从严处理,及至辞退出项目部。六、安全管理措施1、坚决贯彻“安全第一、预防为主”的方针,以防为主、防管结合,专职管理和群众管理相结合,做到精心组织、文明施工、杜绝重大伤亡事故。2、实行项目部、施工队、班组三级安全保证体系,坚决贯彻“管生产必须管安全”的基本原则。3、成立以项目经理为组长的安全生产领导小组,认真实施安全例会制度和安全生产否决权,深入开展安全教育,强化“安全生产”意识,并充分发挥安全监督职能作用。4、坚持安排生产的同时,安排安全工作目标、措施及安全要点,并落实到人,在向班组下达生产任务的同时,下达书面安全措施交底,并说明施工中的安全要点。5、实行领导安全值班制度,定期组织安全大检查,对不安全情况,限期整改,并落实到部门和个人,对重要施工部位,推行安全哨责任制,加强巡回检查。6nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计、安全生产做到标准化:高空作业标准化、临时施工用电标准化、临时防护措施标准化、安全标志标准化,开创良好的安全施工环境,坚持文明施工。7、坚持三级安全教育,提高自我安全防范意识和安全施工知识。8、对事故严格做到“四不放过”的原则,避免事故的重复发生。9、主要消防措施:消防工作列入现场管理重要议事日程,加强领导,健全组织,严格制度,建立现场防火领导小组,统筹施工现场生活区等消防安全工作,定期与不定期开展防火检查,整治隐患。对消防员进行培训,熟练掌握消防的操作规程。请专职消防员对现场所有管理人员及工人进行消防常识教育,演示常用灭火器的操作。在施工现场,每层楼梯设大容量灭火器,确保消防安全。施工现场可燃气体及助燃气体如乙炔和氧气、汽油、油漆等不混乱堆放,防止露天暴晒。按施工现场有关规定配备消防器材,对易燃、易爆、剧毒物品设专库专人管理,严格控制电焊、气焊地盘位置,采取保证消防用水的措施。设置足够的消防设备,易燃、易爆、剧毒物品不进入现场,少量存入专人管理,楼层采用低压行灯变压器,不使用碘钨灯。七、安全技术措施1、安全防护内容及方法1.1“三宝”三宝内容指安全帽、安全带、安全网。工人进入现场统一佩戴安全帽。现场设置安全稽查人员巡回检查,发现有不戴安全帽者则予以记名登记并罚款10元。安全帽由项目部统一购置,统一颜色,符合《安全帽》(GB2811-1989)。发现不合格安全帽作报废处理。凡在2m及2m以上的高空作业,无防护时,人人做到系好安全带,安全带由项目部按《安全带》(GB6095-85)验收合格,并证件齐全后使用。现场设置安全稽查人员巡回检查,发现有不戴安全带人员则处以50元罚款并登记通报批评。安全带佩戴过程中,安全带上的各种部件不得随意拆除和更换,出入仓库应严格进行登记和检查。本工程围护均采用密目式全封闭安全网,安全网的使用部位为建筑外侧全封闭,此部位下部为行人通道,除按要求封闭安全网以外,行人通道上部搭设安全通道。通体建筑外侧全部悬挂安全网,直到建筑物顶部。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计物料提升机架体外侧使用立网防护,电梯口、扩散井在井口内、首层及每隔两层(最多10m)设牢固平网。外封闭的安全网采用密目式,安装时每个环扣都做到穿入符合规定的纤维绳或12~14号钢丝。系绳绑在支撑物(架)上,符合打结方便,连接牢固,易于拆卸的原则。安全网支设完毕,经过检查验收后使用。2、“四口”本工程楼梯口、通道口、预留洞口数量较多,为保证施工操作人员安全出入,对上述部位进行封护。2.1楼梯扶手要求建设单位单位及时定货,力争楼梯踏步护栏拆除后及时安装,如不能及时到货,则设置1.2m高的钢管防护栏杆与埋铁焊接。2.2预留洞口采用ø12钢筋作肋、∟45等肢角钢焊接成平面结构放在洞口上部予以固定,每边宽出洞口150mm以上。2.3通道口搭设防护棚。棚的宽度每边大于出入口500mm,长度为8m,棚顶采用300mm×55mm×6000mm的木板满铺,侧面采用密目安全网围护。2.4对通道口、楼梯口、预留洞口设置红色警示灯。2.5楼梯防护措施:踏步混凝土浇筑以前,将埋件埋入,每跑楼梯埋三处,即底部、中部、上部,拆模后将1.5m短钢管竖向焊接就位,然后将斜向长杆采用扣件连接。预留洞口防护措施:将焊制好的钢筋网架水平套入埋好的Φ22钢筋中,通道口安全防护措施:采用ø48×3.5钢管、扣件,搭设8m长防护棚,上铺55mm厚木板。八、雨期安全施工措施1、雨期安全施工预防措施1.1根据现有工程的施工情况,结合工期、进度要求,合理安排施工。雨期到来之前来不及完成但不影响工期的项目安排到雨期后进行。1.2项目经理是雨期施工生产质量、安全第一责任人,对质量、安全全面负责。成立以项目经理为组长的雨期施工生产领导小组,明确小组成员的各自职责。设专人负责与气象部门联系,及时收听气象台(站)天气预报,随时掌握气象变化情况,以供施工参考。1.3积极做好雨期施工的各项准备工作,制定切实可行的雨期施工方案,对全体职工进行一次全面的雨期施工质量、安全生产教育。1.4保证雨期临时道路畅通无阻。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计1.5备足、备齐防雨、防汛、防潮、防暑、防台风等各种雨期施工器材物资。1.6雨期到来前对生活和生产设施进行一次全面的防雨、防汛、防潮、防风暴、防雷击检查,并及时予以维修加固。1.7在钢筋林立的场所,雷雨时不操作和站人。1.8雨天、雾天及六级以上大风停止一切高空作业。1.9高空作业的工人穿防滑鞋,戴安全帽,系安全带,安全带挂在牢固可靠的地方。1.10雨期施工前对塔吊、井架、龙门架、人货两用电梯等垂直运输设备及脚手架安装可靠的接地防雷装置,并采取防风暴措施。1.11搅拌机、电动卷扬机、钢筋加工等机械,设置防雨棚。各种电闸、配电盘设置在标准电闸箱内。1.12基坑回填土工程:基坑回填土的材料为普通粉质土,由场外运入,土方回填时避开雨天。待雨后回填土面上能走车和压路机时继续回填,每层回填厚度不大于300mm。1.13怕水、怕潮的物资,做到按计划小批量进场,先进场的先用、后进场的后用,做到周转循环,不长期积压。1.14一旦发现钢筋加工、堆放场地和进入楼内的通道没有覆盖好,要随时处理。1.15在暴风雨期间,所有高空作业均停止施工,施工人员全部退到安全地方。塔吊、电梯、及其他较高的设备均停止运转,施工人员尽可能地转入室内施工(如拆修模板、砌墙、抹灰、钢筋成型等)。1.16高压电和接地避雷线附近严禁站人。有专人查看基坑有无滑坡现象,脚手架、塔吊、电梯有无危险情况,所有电器设备是否漏电等,如发现有异常现象立即进行处理。1.17各种怕水、怕潮的材料查看是否安置妥当,若漏雨受潮,则立即采取措施。不使用受潮、见水的外加剂、粉煤灰。1.18雨、雾天不允许施焊。拆下的模板、方木若不能及时用上,尽量安放在避雨处存放,如必须堆放在露天地方,则盖上雨布。1.19雨天浇筑混凝土时将塑料布盖好以免水泥浆被雨水冲走,并根据砂石含水率随时调整混凝土配合比。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计2、雨期施工纠正措施2.1安全检查2.1.1沿现场四周检查有无闸刀箱倾倒、电缆线泡水、电缆拉开、破皮等现象,确保无误后,恢复现场供电。2.1.2检查外围基坑有无积水情况,如有积水及时将积水抽排清除。2.1.3检查落地外脚手架地基有无软化下沉和松动现象,如有下沉、松动则进行加固处理,处理办法为先将落地杆区域600mm×600mm范围内的淤泥挖除至老土层,换填以1:1.5级配砂石,并分层夯实,然后再重新加固好垫板。2.1.4检查施工现场外围护设施,重点检查安全网、围护网有无拉脱、破损情况。2.1.5检查现场大型机械设备的安全状态、机械性能,重点检查塔吊及搅拌站和各种电器是否正常。2.2质量检查2.2.1钢筋有无锈蚀,如锈蚀严重则采用铁刷子进行除锈处理,除锈干净后用于工程中。2.2.2检查模板的拼装及平整度,现场拼装好的模板如发现有翘曲、起拱、开裂等现象,进行更换或修整,以保证混凝土的截面尺寸及平整度。2.2.3混凝土搅拌以前,对现场砂石进行含水率的测定,通过调整用水量来保证混凝土拌合水的计量准确。九、地下管线及其地上地下设施的加固措施1、施工范围内的各种地下管线包括上水、下水、煤气、通讯缆、电缆等隐蔽设施,按设计图纸标注的种类和位置,在施工前与有关单位联系,弄清具体管线种类、尺寸、位置、覆土深度,重要管线插牌标记;2、在进行土方施工前,沿开挖的长度方向采用人工开挖沟槽,确定开挖周围管线及设施预埋情况后,采用机械开挖。道路施工时,沿道路横断面方向,设计路面高度以下1m每50m开挖一条沟槽;3、对各种地下管线、检查井、收水井、各种人孔等,妥善保护,不损坏,对地下管网种类、尺寸、位置、高程了解清楚,施工时除向全体施工人员、班组交底、插牌标志外,另请所属主管单位派人员现场监督,防止出现意外事故;nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计4、各种管道井、电杆、构筑物周围离开适当距离,必要时配合人工刨除;5、地上各种架空线路采取妥善保护措施,离工地周边5m以内线路必须搭设保护架加以保护;贯穿主体的架空线路在施工前与相关部门取得联系,进行妥善处理,不私自处理。6、对建设单位分包施工队的一切设施根据其布置图做好妥善保护,以免出现意外。对于其布置或设施不符合要求的,通过建设单位协调解决。第二节文明施工管理保证措施1.贯彻执行文明施工有关管理规定,配备专人负责工地文明施工管理工作。2.设立专人负责每日对施工范围内的清理打扫,保持四周的清洁与环境卫生工作,并对进出施工场地的运输车辆进行控制、监督,对车身车轮较脏的运输车,材料车等车辆进行冲洗后方可进出场内场外,对已散落在场内外的散体物料:如泥,石子、黄砂等要及时清理,打扫,确保场内外的清洁,做到文明施工。3.现场办公室做到窗明地净,文件、报表、杂志悬挂整齐,报纸和用具、椅子等放在固定地点。4.现场在醒目的位置处设宣传企业精神的本工程奋斗目标的标语口号。在主要出入口悬挂安全生产六大纪律和十项措施等固定标牌,设立宣传好人好事的以及生产信息等方面的黑板报。悬挂工程透视图,注明建设、施工、设计单位、工程规模和工程管理网络。5.严格按施工组织设计规定的总平面布置图位置搭设临时设施,安排机具,堆放材料.构件及半成品,并在场地里安置部分盆景装饰。6.材料堆放整齐,不到处乱堆乱倒。7.建筑垃圾、渣土,装入临时设置的垃圾桶或利用垃圾道溜下,或用灰斗、小车吊下,不向窗口抛掷,防止飞物伤人。8.现场的机械设备,按施工组织设计定点安置,摆放整齐,定机定人机身经常保持清洁、安全可靠,所有机械设备均不带病运转。在搅拌机周围设排水措施。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计9.现场施工用电符合安全用电操作规程,电线敷设整齐美观,尽可能将架立线改为埋线。机电设备都设有防雨、防潮安全措施。10.加强文明礼貌教育和宣传,不在建筑物上乱涂乱画乱刻、在建筑物内随地大小便、吐痰。第三节冬季施工《建筑工程冬期施工规程》规定:当室外日平均气温连续5d低于5℃即进入冬期施工。上海大约每年的11月15日到次年的3月15日为冬期施工时间。进入冬期施工以后,及时了解天气情况,提前做好气温突然下降的防冻准备工作。组织有关人员学习冬期施工规程,编制冬期施工领导小组、责任人,把冬期施工的各种措施、制度贯彻好、实施好。准备好冬期施工用具:聚苯板、旧麻袋、塑料薄膜、草垫子等保温材料。nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第十二章施工技术资料、安全台帐一、施工技术资料规范整理1、根据本工程的建筑、结构施工特点,我方选用了以下施工技术规范:工程建设标准强制性条文——房屋建筑部分《建设工程施工质量验收统一标准》GB50300-2001《砌体工程施工质量验收规范》GB50203-2002《混凝土结构工程施工质量验收规范》GB50204-2002《屋面工程技术规范》GB50345-2004《建筑地面工程施工质量验收规范》GB50209-2001《建筑装饰装修工程质量验收规范》GB50210-2001《建筑给排水及取暖工程施工质量验收规范》GB50242-2002《建筑电气安装工程施工质量验收规范》GB50303-2002《工程测量规范》GB50026-93《屋面工程质量验收规范》GB50207-2002《建筑钢结构焊接规程》JGJ81-2002《钢筋焊接及验收规程》JGJ18-2003《多孔砖砌体结构技术规范》JGJ137-2001《塑料门窗安装及验收规程》JGJ103-96《普通混凝土配合比设计技术规程》JGJ55-2000《施工现场临时用电安装技术规程》JGJ46-2005《建筑施工高处作业安全技术规范》JGJ80-91《建筑机械使用安全技术规程》JGJ33-2001《建筑变形测量规程》GB/T50262-97《建设工程项目管理规范》GB50326-2001《建设工程文件归档整理规范》GB/T50328-2001《建筑基坑工程技术规程》DB33/T1008-2000J10036-2000《混凝土多孔砖建筑技术规程》DB33/1014-2003J10295-2003《地下工程防水技术规范》GB50108-2001《建筑涂饰工程施工及验收规程》JGJ/T29-2003《玻璃幕墙工程质量检验标准》JGJ/T139-2001《混凝土泵送技术规程》JGJ/T10-95nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计2、项目经理部建立信息情报室,平时所有资料存入电脑,统一编号,由专职项目资料员负责对工程进度、质量、安全、投资等信息全部纳入微机管理,并与指挥部进行联网,随时接受市领导和指挥部的检查督促,工程交工后,资料员负责在一个月内完成文件分类整理、装订和移交(市档案室)工作,移交主要文件资料有施工技术管理资料、工程质量保证资料、工程质量评定资料三大部份,除交建设单位要求的文字材料外,另外提供施工过程所有记录的影像资料两套。资料员按照我方文件和资料管理规定,在项目工程师领导下工作,施工期间负责所有往来文件的收发与传递及分类整理保管工作。所有工程技术资料我方将按下列所要求的项目进行检查,并要做到“及时、真实、完整、齐全”。二、施工安全台帐规范整理1、安全规范整理:工程建设标准强制性条文——房屋建筑部分《施工现场临时用电安装技术规程》JGJ46-88《建筑施工高处作业安全技术规范》JGJ80-91《建筑机械使用安全技术规程》JGJ33-2001《建设工程项目管理规范》GB50326-2001《建设工程施工现场供用电安全规范》GB50104-93《建筑施工安全检查标准》JGJ59-99《龙门架及井架物料提升机安全技术规范》JGJ88-92《建筑施工门式钢管脚手架安全技术规范》JGJ128-2000《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2001《密目式安全立网》GB16909-1997《安全帽》GB2811-1989《安全网》GB5725-1997《安全带》GB6059-19852、施工现场安全资料台帐2.1安全生产管理制度各项安全生产管理制度;各种安全技术操作规程;nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计2.2安全生产责任与目标管理企业主要人员及主要职能部门安全生产责任制;项目部管理人员安全生产责任制;安全生产目标责任书或经济承包协议书;项目部安全管理目标责任书;项目部安全生产组织网络;项目部安全生产责任制考核规定与记录;项目部安全目标责任考核规定与记录;2.3施工组织设计施工组织设计(含工程概况表);施工现场总平面布置图和安全标志布置平面图;专项安全施工方案;2.4分部(分项)工程安全技术交底各分部(分项)工程、各工种及其他安全技术交底记录;2.5安全检查安全生产检查记录表2.6安全教育职工花名册;职工三级安全教育登记卡;变换工种教育登记表;职工安全知识考试;项目管理人员年度培训记录表及有关岗位证书复印件;特种作业人员和机械操作人员花名册;特种作业人员和机械操作人员上岗证;2.7班组安全活动记录表班组安全活动记录表2.8工伤事故处理安全生产月报表;伤亡事故报表;2.9工地安全日记工地安全日记2.10施工许可证明和产品合格证nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计有关部门批准的施工文件;安全防护用品合格证书及准用证;机械产品合格证及准用证;专项施工资格证书;人身以外伤害保险证明;2.11文明施工文明施工技术措施;文明施工技术要求和验收表;施工现场消防安全管理检查记录表;施工现场动用明火审批表;2.12分项工程安全技术要求和验收施工机具;脚手架;施工用电;“三宝”、“四口”防护;nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第十三章质量保证体系和确保工程质量措施第一节质量保证体系1、质量管理网络图各施工班组、全体操作人员电气工程质量责任人管道工程质量责任人装饰工程质量责任人屋面工程质量责任人门窗工程质量责任人砌体工程质量责任人材料机具设备质量责任人项目资料员项目材料员项目施工员项目工程师项目质量员项目副经理项目经理nthemainterminal,andthetelephoneOfficeisresponsibleforprovidingtheappropriatesizeadapterpatchpanelsandelectricalprotectionunit.(Shuttlebus)wiring(IDF)setupintheworkshoponthesecondfloorofthebuilding,locatedintheDistrictofweakelectricalcabinets(well).EngineroomplacedinsidetheCabinet,IDFplacedastandard40Ucabinetsforinstallationofnetworkandwiringdevices,managementcomputerandtelephoneinformation.CabinetdistributionframearemadeofSuperfiveRJ45patchpanelhorizontaltwistedpairconnections.Computerinformationmanagement,adminareausingthejumpers,whichusesprivateRJ45-RJ45softjumpersfornetworkdeviceswithjumpershoppingbetweenallswitches,changes,expansionandmaintenanceweredonequicklyinthewiringcloset.TwistedlengthCentreroomislocatedonthesecondfloor,outwardradiationofeachline(exceptsomepointsmayexceed)doesnotexceed100metresinlength,allinformationforthevariousfloorsallrooms(distributionCabinet)unifiedmanagement.Districtworkshopbuildingdistributionlines(IDF)viafiberopticcablesconnectedtothetotalroomcabinets.Fiberlengthwere:workshopstwoIDF:totalmorethan1200squaremeters,doublethenumberofstrandscanbecalculatedbymultiplyingtheaveragelengthofthenumberofinformationpointsare.Averagelevelofeachlengthofcable:L=[(S1+S2)/2]+L1+L2l:averagelengthofcable;L1:MDFcableallowance;L2:otherallowancesS1:minimumhorizontalcablelength;S2:maximumhorizontallengthofcable;Officebuildingofinformation:aminimumof26meters,thelongestwas92meters,L=[(28+92)/2]+2.5+1=62.5m;Totallengthof62.5mx792=49500-meterineachbox(KFT)by300meterspercarton;Thetwisted-paircableboxyouwant=49500÷300=165(KFT);lossesnotincluded,eachabout15meters.Metallineslot,andmetallinetubeof53 施工组织设计第二节确保工程质量措施一、保证质量的组织措施:1、建立权威的质量管理小组,项目经理任组长,成员由技术负责人、施工员、质量员、班组长等组成,配备专职质量检查人员。1.1项目经理质量职责a、代表我方对项目全面负责,在项目上实施我方的质量方针和项目上的质量目标,全面履行工程承包合同;b、组织制定并批准项目质量计划,确定或调整本项目的各项管理职责,组织实施项目质量计划;c、确保我方质量保证体系在项目上有效运行,接受指挥部和有关方面对项目进行的质量审核,负责对出现的不合格项制定纠正措施并实施整改。d、对工程符合设计、验收规范,工程建设强制性标准和验评标准要求及达到优良等级和创名牌负责;e、参与和组织工程交工后保修期内回访和保修工作。1.2项目技术负责人质量职责a、对项目经理负责,协助项目经理控制管理本项目质量体系的运行;b、主管项目经理部技术、质量工作;c、负责过程控制的质量策划,主持项目质量计划的编制工作并审核定稿;d、负责施工技术准备。组织编制并审核专项施工组织设计,确保关键工序、特殊工序技术交底工作及时到位,组织参加图纸会审和设计交底工作。e、负责对本项目人员质量教育和技能培训工作。1.3质量员质量职责a、负责对工程质量进行监督控制;b、负责对原材料、半成品和设备标识的检查监督;c、负责对合格原材料及工程设备的确认;d、负责对分部分项工程的质量核定;e、负责联系代建商、质量监督部门、监理公司对工程质量的监督,隐蔽工程验收、签证及参加单位工程的质量评定。f、负责对质量技术措施实施的监督、验收;g、负责检查监督相关特殊岗位人员的上岗资格;79 施工组织设计h、负责对工程分包方工程质量的监督;I、负责本项目检验和试验状态标识工作;j、负责本项目轻微不合格品的确认,对可能属于一般、严重不合格品按规定上报,对不合格品处置后进行重新验证。1.4材料员质量职责a、按《物资采购程序》规定进行采购,负责对进场的原材料、外购件的验收、退货、索赔,对原材料按有关规定进行委托送检,并进行产品标识。b、对代建商、分供方提供的物资,负责按合同规定进行验收。c、对分包方的物资进行监督控制。1.5施工员质量职责a、负责所管部位和分项工程施工全过程的施工管理,使其符合图纸规范和标准的要求,有设计变更符合设计变更要求,有特殊规定符合特殊规定要求;b、确保不合格的材料、设备不投入使用,确保不合格的工序不转序;c、工程竣工时确保提供完整、准确的有关施工技术资料,并对移交资料的符合性负责;d、负责对代建商提供的工程设备按规定要求进行验收、标识;e、负责施工现场的成品保护及交付工作。1.6技术员质量职责a、保证本岗位编制的各种技术文件、资料的质量,对差错引起的质量事故负责;b、实施技术状态管理,对技术状态更改的设计依据,可行性及执行结果负责;c、制定关键工序和特殊工序的质量控制要求,编制关键工序、特殊工序作业指导书并进行交底及技术指导;d、参加工程质量事故的处理,工程施工过程中不合格项的纠正措施、原因、责任的落实负责;e、负责检查工艺的执行情况;f、协助技术负责人搞好各种技术培训工作。1.7生产班组长质量职责a79 施工组织设计、认真执行施工工艺技术文件和质量验收标准,负责对班组成员的质量教育,落实操作规程;b、负责对施工过程质量控制,对班组交付检验的工序质量负责严格执行质量“三检制”,保证不合格品不出班组。认真组织填写各种质量记录。2、由我方生产副经理、总工程师、技术、质量管理部门组成有效的质量监督检查机制,审核工程实施过程。3、广泛开展QC小组活动,对技术难题进行攻关。4、所有参加施工人员具备“质量第一”意识、良好的职业道德、高超的技艺。二、保证质量的管理措施:1、工程质量管理网络(见下页)79 施工组织设计电气工程质量责任人管道工程质量责任人内装饰工程质量责任人外装饰工程质量责任人屋面工程质量责任人门窗工程质量责任人砌体工程质量责任人材料机具设备质量责任人资料员材料员施工员技术负责人质量员项目副经理项目经理各施工班组、全体操作人员2、技术负责人召集相关部门技术人员共同进行施工图纸会审和技术交底、统筹、平衡各专业之间、部门之间,各分部工程衔接关系,并记录、存档。79 施工组织设计3、各类原材料、半成品,择优选放,并备齐材料证明文件,专职检查,不符合材质标准,不得进场,拒绝使用。材料的运输、保管等环节严加控制,注意时效性,分类堆放相结合。4、科学、合理选配施工机械、器具,满足质量过程控制之目的,做好维护保养,保证机械设备正常的良性运转。5、落实质量岗位责任制,建立质量信誉卡,谁作业谁负责,奖优罚劣,重奖重罚,定期进行质量评比。6、严格执行分部、分项工程质量检验制度,每项工程完成后在质量员的指导监督下,由单位工程施工员,具体组织班组长进行质量评定工作,每月及时填报质量评定表上交指挥部,以便抽查复核,一经发现问题,必须及时进行整改处理。7、做好隐蔽验收工作,根据工序编制分层、分段预检计划,不漏项,隐蔽验收在组织验收前施工员应填写好验收单,及时通知建设、监理和设计单位进行验收,按照规定做各项技术资料的积累,由资料员汇总,及时归档。8、建立班组自检、互检和交接检制度,由班组质量员、现场施工员在操作过程中及时进行自检、互检,若发现问题,及时纠正,并严格贯彻执行班组间,安装与土建间的交接质量检验制度,不合格要立即纠正,否则应停止施工下一道工序。9、加强技术复核、技术交底制度,对定位灰线、轴线标高必须进行严格复核,再通知技术部门复核。对新材料、新工艺、施工前必须做到书面落实技术措施,交底要做好记录,交主管人签字。10、加强对砼的拆模强度,轴线位移,砖砌体质量的控制,若出现问题,要做好记录并及时研究处理,贯彻质量样板制、挂牌制,三检制。三、保证质量的技术措施:针对工程的特点,我们将认真加强技术管理和贯彻我方通过认证的ISO9001:2000质量体系,严格把握质量动态,确保工程优质、安全、文明、高效地完成。将采取如下技术措施:1、严格按设计施工图纸和施工图纸会审纪要及国家有关施工规范、规程及建设工程强制性标准施工,工程施工前认真组织学习图纸和进行图纸自审,尽量把图纸存在的问题在图纸会审中解决掉。79 施工组织设计2、根据工程特点和现场情况编制好工程施工组织设计,对重点部位和项目制定好有针对性的专项施工方案以及具体保证施工质量的技术组织措施,报指挥部总工程师批准后实施,并认真贯彻落实。3、严把进料关:对工程所使用材料,积极采购国优、省(部)优、市(地)优名牌产品,并认真做好原材料进场检查复验工作,钢材、水泥、防水材料等均具有出厂质保书和合格检验单及各种试验报告,未经检验合格的材料不在工程中使用,并作为一个制度进行认真贯彻,以保证结构的安全和使用功能。4、现场施工技术管理人员认真做好技术、质量交底和技术复核工作及隐蔽工程的自检验收工作并及时通知有关各方进行验收,经验收合格方可进行下道工序施工。5、严格按照砼、砂浆配合比,安排专人负责按规定制作砼、砂浆试块和按规定标准进行抗压及抗渗试验,同时严格实行现场取样见证制度,在现场安排专人负责做水泥、砂石料等正确计量工作。6、砼浇捣完成后安排专人负责并按规定时间进行养护,冬期施工浇筑砼采取掺早强剂和用保温抗冻材料覆盖好。7、钢材对焊和电渣压力焊及电弧焊接均按规定截取试件进行检验,合格后再投入使用。8、严格按设计和规范要求留设、处理好柱、梁、板等的砼施工缝,浇筑砼前做好施工缝的清理清洗工作,并用与砼同标号砂浆套浆后再用砼浇筑密实。9、各分部分项工程超前示范,样板引路。从工程基础开始,直至竣工,全部以样板开道,重点抓主体工程的“样板墙”,装饰工程的“样板套”,以点带面,优良先行,对达不到样板标准的坚决返工重来。10、严格工程技术资料管理,认真及时做好施工中各项记录,确保工程技术资料与工程进度同步。竣工技术资料做到及时整理、齐全、规范,同时做到正确、全面、系统、真实,符合规定要求。11、对各细部技术措施:在施工过程中坚持做到样板引路,例如在今后的装饰工程中楼梯踏步阳角、内墙阳角、八字角、钝角阴角嵌铜条保护,以避免缺棱掉角现象,做到顺直挺括,光滑美观实用。79 施工组织设计第十三章确保工期施工组织管理措施由于本工程施工工期紧,为确保如期完成本工程建设任务,将确保一下工作:1、在人力上,我方将在本工程组建一个作风优良、业务精干、诚实刻苦的项目经理部,选派优秀的项目经理到场指挥、协调、管理工程。配备责任性强、精通业务的技术人员作为项目管理人员。作业层的操作班组选择,亦考虑以往工程的施工质量、配合默契程度等因素综合评定,确保优秀施工班组进场作业。另外,从制度上明确所有进场人员“职、权、利”关系,真正做到“谁施工,谁负责”。制定管理人员工作责任制,做到职责明确,奖罚分明。进一步健全经济承包责任制,把责任落实到班组。在施工高潮期,特别是砼浇捣期,在尽量不影响当地居民生活和取得夜间施工许可证情况下,集中优势劳动力,实行二班制、三班制连续施工。另外,选派一支多功能的机修、电工及其他机械操作工,保证现场机具运行正常,并随时进行维修和保养。2、在财力上,我方在资金上将全力支持本工程建设,工程款专款专用,任何人不得将工程款移作他用,严格资金管理制度,确保工程建设不因资金问题而影响进度。每月底把下个月工程进度计划及月报表报送给监理公司和指挥部,以便三方能顺利协调工程进度,合理安排工程建设资金。3、在物力上,我方将优先满足本工程所需施工机械及周转材料,工地项目经理部在月底把下个月需用施工机械、周转材料、工程需用材料的计划报送给公司,公司及早与有关部门、单位签订合同,确保施工机械、周转材料、工程需用材料保质保量按期进场。施工机械进场前根据要求进行检查,保证进场施工作业时能顺利进行。工程所用材料,在进场前,按规定做好各种测试,测试合格的材料用于工程,减少中间环节,加快工程进展。4、在技术方法上,贯彻“科技是第一生产力”79 施工组织设计的精神,积极采用新工艺、新技术、新材料,突破常规的施工速度;采用网络计划控制工程施工进度,在总进度计划的基础上,认真细致地编写月、旬作业计划,开具施工任务单;做好工序前的准备工作,在工序前由施工员负责落实各方面的准备工作,如工作面、施工机械、主要材料,技术复核和隐蔽工程验收等,并检查落实;计划人员随时检查监督进度情况,分析影响施工进度的各种因素,及时讨论解决,调整网络计划;实行边施工边检查,进行全过程控制,采用分段分部位验收。强化通讯联络、交通运输、施工整体调度等各种手段,高效、科学指挥施工;集中力量抓好竣工扫尾工作,制订成品保护措施。5、在内、外协作上,工程项目经理部主动搞好内、外协作关系,施工机械、周转材料、工程用材料、资金、操作班组等,预先搞好计划,及时与内部有关部门协调,待工程需用时及时进场。与设计院、质监站、安监站、监理公司、指挥部等有关部门,事先主动联系,按规定做好各种工作,避免在施工过程中出现影响工程质量、安全因素,确保工程能顺利进展6.管理体制和组织机构本工程强化项目法管理,推行项目法施工,实行项目经理负责制,组建合理实效的机构,配备素质高、能力强的管理人员,择优选择技术素质高的专业队伍。建立奖罚激励机制,充分发挥职工积极性,提高工作效率和劳动生产率,确保项目各项目标的实现。7.采用微机技术加强调度管理合理安排工序穿插和工期,建立主要形象进度控制点,运用组织计划跟踪技术和动态管理方法,坚持月平衡、周调度,确保总进度计划实施。按施工总进度原则,科学调度生产、协调土建、安装、装饰交叉作业和分段流水施工。8.建立例会制度建立如下会议制度:每月一次的工程总结会,做阶段性总结;每周一次的工程例会,安排检查进度;每日一例会,检查作业进度,并做日报、周报,控制保证计划的层层落实。79 施工组织设计第十四章工程总包管理、配合服务措施本工程专业施工队伍多,交叉作业频繁的施工特点,如何履行总承包职责,合理、有效地处理好与各专业分包单位之间的协调配合,是关系到工程能否顺利进行,工程质量、工期、安全文明等施工管理目标能否顺利实现的关键。一个工程的顺利完成,需要代建商、设计、监理、施工等各方主体的长期密切配合。虽然建设各方利益关系所处角度不同,但最终目标是一致的,就是要为社会奉献一个精细完美的建筑作品。哪方的作用和定位发生偏位都会造成整体工程的不顺利与缺憾。因此,在此前提下,协调处理好总承包与各参建方的关系显得十分重要。我公司处理各方关系的原则是:对工程负责,对业主负责,对社会负责,积极配合、争取支持、换位思考、多出思路、主动沟通、达成共识。根据本工程特点和施工类似大型公共建筑的总承包管理经验,按照合同文件要求的总承包责任,本工程的总承包管理主要从以下几个方面做好工作:一、总承包管理模式为了有效地对本工程的施工进度、施工质量、安全文明施工等方面进行全面控制,顺利完成各项施工管理目标,我们在本工程施工组织管理中,建立以项目经理为首的项目经理部,采取矩阵制管理模式,实行项目经理负责制。并在项目经理部内设置测量、施工、技术、安全、质量、材料、计划、预算、财务、行政保卫等职能部门。项目管理人员的设置以公司管理骨干组成,从施工计划的协调、施工场地的综合安排、施工工期工序搭接、施工协调、施工质量的控制监督及施工现场的管理等各方面进行总承包管理。二、总承包管理职责(一)79 施工组织设计首先项目经理把施工图的联络协调作为施工总承包的主要工作,配合专职人员全面负责施工图的联络协调,积极地协助业主管理,提出施工图中可能出现的问题,协调各工种之间施工中可能出现的问题,提交设计认可,组织实施及处理方案。(二)全面负责管理本项目的施工运行,确保项目建设顺利开展。(三)全面负责项目资源配备,保证各部门职能的实施,保证承包管理体系的运作。(四)保证项目总质量方针和目标的实施,负责施工过程的全面质量监控及施工过程监控。15.2.5全面负责施工现场的文明标化管理和协调工作。三、与代建商的配合、协调在实施本项目的过程中,我们将绝对服从代建商在施工进度、质量、文明施工等各方面和环节进行的项目管理,通过良好的合作,全面地履行合同,以保证与代建商的密切配合和协调,以保证工程的顺利进行和竣工。明确与业主的关系:就是服从与服务,发挥自身的主观能动性,确保总进度计划、总质量目标的实现。(一)对于代建商所提出的工程总进度、工程质量目标、现场文明施工管理、施工力量配备、机具设备材料的管理、精神文明建设和安全管理等方面的要求。我方将不折不扣的予以执行,并制定相应措施予以保证落实。(二)对于代建商在机电、设备材料选型、采购、仓储、运输对系统承包商进行招标等各方面提出配合的要求时,我方要积极主动地提建议、想方法,在必要时也可以抽调专业人员组成供应组,订立实施方案,其目标是一切服从工程,保障到位。四、对设计院、监理单位的协调配合(一)为了保质按期完成本工程,本着为业主着想的宗旨,在施工全过程中,应加强与设计院、监理单位的密切联系。79 施工组织设计(二)组织设计图纸会审和设计优化,技术咨询工作,及时将政府部门和有关部门的审核意见提供业主,并反馈给设计单位。(三)组织设计院和施工单位进行设计交底,进行设计、施工方面的工程技术协调,负责审查施工方案,并提出书面意见。(四)及时向设计单位和监理单位书面提出就施工图设计可能出现的疏漏缺陷,或尺寸差异,或资料不足(如施工所需之节点图等),及时报请监理及设计单位确认后按设计单位修正或补充的施工图指导施工单位进行施工。(五)由项目部经理根据现场施工的情况不定期召开由设计、监理参加的协调会,及时解决设计变更或施工搭接中出现的疑难问题,以保证施工顺利进行。(六)由项目部技术员、质量员按有关技术和质量标准、设计要求进行工程的测量定位、轴线、标高的复测和验收,并按要求及时通知设计方共同参与验收。(七)按照项目部的检验与试验计划,由项目施工员开具隐蔽工程验收记录单,专职质量员会同监理单位共同进行验收签字盖章,不经验收,不得进行下道工序施工。(八)对施工过程中出现的质量问题,首先查明质量产生的原因,督促和检查各施工单位处理方案的实施,及时向设计、监理反馈,坚决做到不留隐患,不影响工程质量等级。(九)每月组织一次由监理方参加的工程质量抽查和质量管理考评,并针对施工现场存在的质量问题进行会诊。(十)79 施工组织设计根据合同和图纸要求,审查各分包单位提供的材料,设备清单及质保书,并对工程中使用的原材料、构件及设备进行必要抽检,对施工单位提交的各类材料样品经复核后,送监理方人员审定,并及时采取相应保护措施。五、对分包单位的总体协调管理(一)无论土建分包、安装分包、还是指定分包,均纳入总承包的协调管理范围。(二)以合同规定的施工总承包范围、工程质量、工期、安全、文明施工等要求。作为施工总承包我们将编制详细的施工组织设计,经业主及现场监理确认后,进行实施。(三)督促各分包详细阅读施工图,提出施工图中可能出现的问题,并提出处理方案,并报请业主经设计认可后组织施工。(四)以合同规定的总工期要求,编制本工程施工总进度网络计划,并考虑安排各分包单位所要求进场、施工的时间,并报请业主和监理审批,以此有效地对工程进度计划进行总控制。(五)以总工期为依据,编制工程进行分阶段实施计划(施工准备计划;劳动力进场计划;施工材料、设备、机具进场计划;进口设备、材料进场计划;各分包工程分包队伍进场计划等)。(六)将总合同条款要求,分解纳入相对应的分包合同中,使分包合同对质量、工期、安全、文明施工等完全处于总包的控制状态之下,确保工程如期完成。(七)分包应按与总承包签约的合同要求,编制出分包工程分部分项详细的施工组织设计,报请总包审批同意后才能进行施工。(八)作为总承包我们将每周定期与分包单位召开一次协调会,解决生产过程中发生的问题和存在的困难。按总承包周计划要求检查分包每周完成情况及布置下周施工生产计划。(九)79 施工组织设计总承包现场管理人员与各分包管理人员在施工高峰时每天应收工前开一次碰头会,协商解决当天及第二天生产过程中发生的问题,应由总承包负责协调解决的问题决不拖延和延期。(十)施工过程中各类业务联系,除必要口头通知外,总承包以书面形式,报请业主及时发给各分包执行。(十一)各分包单位与总承包业务交往过程中,以业务联系单、备忘录等书面形式与业主进行联系。由总承包解决的事应立即处理。(十二)总承包诚恳接受业主及监理单位对总承包分包管理工作的指导性意见和要求,相互紧密合作,确保工程顺利进行。六、总承包对工程进度的管理作为本工程的施工总承包方,我们将对工程进度的控制分为事前、事中、事后控制三个方面。(一)施工进度事前控制(1)编制本工程施工总进度网络计划,紧扣本工程关键节点,同时以总工期为依据,编制工作进度分阶段实施计划,包括施工准备计划,劳动力进场计划,施工材料、设备、机具进场计划,各分包单位进场计划等。(2)对关键过程或特殊过程编制相应的施工进度计划,指定相应的节点,编制节点控制计划以及施工节点实施细则,明确搭接和流水的节拍。(二)施工进度事中控制(1)审核施工(各供货、配合等)单位进度计划、季度计划、月计划、并监督施工单位按照已制定的施工进度计划进行实施。(2)总承包每周定期与各分包单位召开一次协调会,协调生产过程中发生的矛盾和存在的问题,按业主每周施工进度要求检查各分包完成情况,并布置下周施工生产进度。(3)总承包管理人员与分包管理人员在施工高峰时,每日施工结束前,召开一次碰头会,协商解决当天生产过程中和第二天生产中将会发生的问题,应由业主负责协调解决的问题决不拖延。(4)根据施工现场实际情况,及时修改和调整施工进度,并定期向业主、监理和设计单位通报工程施工进展情况。(三)施工进度事后控制79 施工组织设计(1)根据施工进度计划,及时组织有关部门进行分项施工验收工作,加强工程项目竣工验收管理。(2)定期整理有关施工进度的资料,汇总编目,建立相应的档案。七、总承包对施工技术的管理(一)根据总承包技术管理的要求,发挥计划、组织、指挥协调和控制功能,积极贯彻国家和当地的技术政策和法规。建立良好的项目技术管理秩序,使项目管理过程能符合技术规范、规程,科学、有效地组织各项技术工作的顺利开展。(二)接到施工图纸以后,配合业主及时组织有关人员熟悉图纸,并将图纸中存在的问题汇总整理,在图纸会审前提交设计单位。使得这些问题在各工序施工前将图纸上存在的问题及时解决。(三)在图纸会审后一周内,由我公司编制详细的施工组织总设计,并经公司总工程师审批后送交业主和监理审核批准,根据批准的施工组织总设计再按各单项、工程各阶段编制分阶段施工组织设计,均将经公司总工程师批准后再报送代建商和监理后组织实施。(四)对经代建商和监理批准的施工组织设计,我公司由项目经理组织有关人员认真学习并严格执行,随时接受业主及监理的监督检查。(五)轴线、标高等施工现场的关键工序进行复核,负责各分包单位技术方面的协调,在不同施工阶段协调各分包单位调整场布,满足施工的需要。对于施工中发生的一般技术问题及时解决,如有重大技术问题,则组织有关方面共同参与解决。(六)及时做好总承包的各项技术资料汇总工作,定期归档,并定期对各分包单位的技术资料进行检查,发现问题及时落实解决。(七)我公司根据施工的实际情况,设置相适应的计量管理机构,要求各分包单位也配备专职计量管理人员,开展计量工作。我公司定期对各分包单位的计量工作进行检查,监督各分包单位做好计量器具的送检工作,确保工程质量。八、总承包对质量和安全的管理(一)管理的目标1、工程质量管理目标:按照国家、有关行业和上海市颁发的标准、规范,抓好施工质量、原材料质量、半成品质量,以确保本工程质量符合国家施工验收规范合格标准。79 施工组织设计2、安全施工目标:安全生产重大事故为零,把安全管理工作贯穿于施工管理中,设立专责安全员,突出安全生产在生产活动中的重要地位。3、管理网络的建立为了及时将施工过程中的质量信息反馈给监理,我公司成立以项目经理为组长,技术负责为副组长的全面质量管理小组,对于施工过程中的关键过程(如:屋面工程、土建与安装各专业工种配合等),设立质量控制点,定期开展活动,并运用PDCA循环原理,做好计划、实施、检查、总结、提高等质量控制工作。对于施工过程中的质量问题,采用排列图方法,即找出偏差频率最多的质量缺陷,从而找出最易产生的质量问题,以便采取措施进行避免。对于生产质量问题,由全面质量管理小组再运用因果分析法进行分析,找出主要原因和次要原因,从而找出解决问题的方法,使整个过程始终处于稳定受控状态。(二)质量管理措施1、督促和检查各分包单位严格按照现行的国家规范、标准和设计图纸要求进行施工。2、根据合同和图纸要求,审查各分包单位提供的材料、设备清单及质保书,并对工程中使用的原材料、构件及设备进行必要的抽检,对施工单位提交的各类材料样品经审核后,送监理、报业主审定,并及时封样和采取相应保护措施。3、检查工程施工质量,每周一次书面同业主和监理单位提供工程质量月报,并组织好各项工程验收。4、对于施工过程中间验收、隐蔽工程验收等,我公司将先组织自行检查,对于不符验收标准的,项目部技术负责人实行质量否决制,在自查符合要求后以书面通知监理,在监理认可并书面签字前提下方可进行下道工序施工,对于监理在检查中提出的问题,整改后及时通知监理记性验收,待验收批准后方可进行下道工序施工。5、协助代建商确定本工程甲供设备和材料的定版、造型和提供承包商所需的有关技术数据、资料、样品及推荐有关材料。6、处理各分包单位的工程质量事故,查明质量事故原因的责任,并督促和检查各施工单位事故处理方案的实施,做到不留隐患,不降低工程质量等级。79 施工组织设计7、为了便于分阶段验收,总承包单位定期将所有与质量情况有关的资料整理成册,并定期送监理进行审核。8、工程质量竣工验收时,总承包单位将先进行自检,验收合格后移交监理验收,符合要求后积极配合政府质量监督部门。9、工程竣工验收后,我公司将设立专门回访服务小组做好竣工以后的产品保护及竣工后的服务工作。(三)安全管理措施1、督促和落实各分包单位严格按照国家、建设部、上海市政府和本工程中被认可的施工组织设计中有关的安全生产的规定规程进行操作。2、审查各分包单位方案中有关现场安全管理内容,提出修改意见。3、督促、指导、检查各分包单位搞好安全生产管理工作,严格执行安全生产管理规定;设备、脚手架验收挂牌和操作人员持证上岗制度;对危险区域重要过道处均设置防护措施;对重点部位落实专人监控等。4、督促各分包单位建立起安全生产台帐;同时每月组织对施工现场的安全工作进度检查,善于在动态中采取照片,实物取证等有效手段发现并处理施工中违章和不安全因素,并采取强有力的手段落实整改,并作好书面记录。5、每月汇总一次现场安全情况,根据施工进度及采用的施工方法,提出阶段安全要点,并进行分级安全教育和技术交底工作。九、总承包对文明施工的管理(一)总承包的文明施工管理目标本工程文明施工目标确保达到浙江省文明标化工地。(二)总承包文明施工管理形式1、加强创建文明工地工作的组织领导,将创建工作纳入总承包管理的整个过程,派专人负责主管现场的文明施工。并建立健全总分包创建文明工地的组织管理网络。2、按照我公司有关要求结合工程实际。制定出本工程文明工地标准和评分标准,通过定期和不定期检查相结合。每月对各分包单位和班组的检查进行打分,对评定好的给予一定的奖励,差的则给予处罚,并要求其及时整改。3、负责对上级机关和业主进行有关生产、文明施工管理检查的接待、联系、汇报等工作。79 施工组织设计4、优化现场平面布置,强化堆场划块管理。建筑材料区域堆放整齐,并采取安全保卫措施,必要时派专人看护材料物品;施工区域与生活区域严格分隔;工地上必须做到三通一平。污水入市政管理网前必须经过三级沉淀。十、总承包对作业人员的管理(一)根据工程的进度计划,及时制定劳动力月的使用计划(同时审核各分包单位的劳动力使用计划)。(二)严格按计划使用劳动力,如发现实际情况与计划不符合时,总承包及时查明原因,并采取相应的积极措施解决。(三)为了便于管理和识别,对在工程中进行施工的人员均要求佩带有总承包统一制作、编号的胸卡。管理层(包括分包的施工管理人员)均戴黄色的安全帽,土建的劳务工人戴白色的安全帽,安全的劳务工戴桔红色的安全帽,施工现场机修人员戴深蓝色的安全帽。(四)安排有丰富项目后勤管理经验的人员负责管理劳动力的吃、住、行等工作,解决劳务工的后顾之忧。(五)对业主或监理提出要求辞退的劳务工人(或其管理人员),总承包经验证后,要求分包方在三天之内清退,同时总承包也及时清退各分包单位中不能达到本工程合同及国家有关规范要求的劳务工。十一、总承包对档案信息的管理(一)文件、材料、图纸和有价值的信息资料收集内容齐全,能反映基建活动的全过程和结果,与施工过程的实际相一致,准确真实;在工程竣工后,向业主提供完整的工程档案资料。资料的分类、排列、组合具有逻辑性和整体性,保持相互间的有机联系。(二)加强档案基础工作的建设,建立健全资料收集的组织管理网络,为竣工资料的完整准确提供条件。(三)施工总承包安排专职档案管理员,照要求和有关制度,认真收集日常资料和有关信息,并做好竣工归档资料。(四)项目资料员平时就要做好预立卷工作,及时收发各项在施工、管理中形成的文件、资料、图纸、照片等,建立分台帐,借、查、阅资料有签收制度。(五)竣工档案的封面、卷内目录、备考表、案卷目录、装册盒子都由承包方统一规定,对资料的分类编号,我公司将采用计算机编号系统进行统一编号,以便查询和调阅。79 施工组织设计(六)每月组织检查考核,以保证各档案和信息管理工作的正确有效。在单位工程结束以前,技术负责人和档案管理员,应对工程档案资料认真自检,为单位工程竣工验收做好准备工作。十二、与政府职能部门的关系协调(一)高度重视并正确处理与政府职能部门之间的关系,争取得到相关部门的支持和配合,对于确保工程的顺利进行和完工具有重要的作用。(二)进场后,要充分了解国家、省、市的各项法规、制度的内容和要求,认真严肃的执行政府的各项工程管理规定。对于有关部门下达的指令和通知,必须立即贯彻实施,并及时反馈实施情况。(三)工程施工时,必须严格按照政府相关主管部门的规定要求,办理工程的报批、开工、监检、验收、审批、竣工等各项手续。(四)与政府相关职能部门的关系协调内容:1、与政府质量监督部门的协调:质监站参与工程报建和各阶段的验收工作,并对项目工程质量进行评定。施工过程中,必须服从其对工程质量全过程的监督管理,及时落实各项整改意见和建议,确保优良工程。2、与政府行业管理部门的协调:主要包括消防、供电、自来水、煤气、公安局技术防范中心、技术质量监督局、广电局等部门。施工时,必须根据国家和各部门的相关管理规定,呈送各专业施工图纸和技术文件,办理各项审批手续。3、与政府环境管理部门的协调:执行市区有关环卫环保、市容监察的各项规章制度,加强环境管理和保护,做好现场文明施工,创建市文明标化工地。4、与政府交通管理部门的协调:根据有关交通管理规定,合理安排本工程各类设备材料的进出场时间和运输路线,对于可能造成影响的路段,及时与交警部门协调,以确保工程物资的按时和正常运输。5、与政府治安管理部门的协调:加强员工和现场管理,保持与所属警局的日常联系,处理各类突发事件,保证工程财产和人身的安全。6、与政府社会管理部门的协调:进场后应及时到所属街道居委会办理施工人员的暂住证,并听取对工程施工的合理建议,减少扰民和民扰现象。79 施工组织设计(五)正确处理与政府职能部门的关系,必须以遵纪守法为原则。遇到争议时,应耐心解释,避免冲突,根据相关的法律和政策,力求对方的理解和认同并获得批准。79 施工组织设计第十五章与分包单位的组织、协调、配合工程施工需要各方主体的支持、配合,同样也需要参加工程施工的各分包单位的配合。我公司处理与分包单位关系的原则是:主动协助各专业分包单位处理好工程中碰到的问题,凭对自己信誉与对业主负责的精神做到尊重人、理解人、服务人,为业主和社会奉献精品工程。在具体操作上,以规范为准绳,按照施工工艺、操作规程施工。本工程施工期间,与分包单位的组织协调、配合从以下几个方面做好工作。一、施工协调与配合(一)工程施工配合1、提供合格的作业现场和工作面;2、在现场提供水、电及排水的接驳点;3、提供准确和标识清楚的控制轴线及控制标高;4、现场道路及临时排污设施等,为分包单位施工的顺利进行创造条件。(二)工程施工协调项目经理部负责对分包合同约定的工期计划,总平面管理,各专业施工交叉平衡调度,安全生产和文明施工,以及劳动力状况进行统一协调管理,以便均衡施工,保证工期按合同完成。具体措施有:1、对分包单位提交的现场施工组织机构进行审查和建议,在满足业主要求和现场需要的情况下,及时进行完善;2、提供分包工程施工所需的临时用水、用电接驳点;3、提供工地内合适的临时施工道路,以便分包单位运输材料、机械及人员出入;4、召集施工总分包协调会,解决工地工作面交接、工作配合等问题;5、督促各分包参照经理部的各级工程施工进度计划提交相应的计划,并对其不合理部分进行修改和完善;79 施工组织设计6、对各专业分包的安全生产和文明施工进行监督管理,督促其遵守现场由经理部制定的安全生产规章制度和文明施工守则,为工程施工创造良好的环境和条件;二、对专业分包单位的一般要求(一)进入现场施工的必备条件:1、提交由业主确认为指定分包商的证明文件:(1)分包工程的投标书及投标过程情况说明。(2)中标通知书(或具有等同效力的暂行施工协议)。(3)指定分包商的经营范围及资质登记证书复印件。2、填写指定分包商情况登记表:(1)分包商按国家法律、法规、法令取得合法地位和资质登记证书(2)提交施工许可证复印件,确保施工队伍能进入现场施工3、提交分包工程的“施工组织设计方案”:(1)施工方案简介(2)分包工程施工进度计划(3)主要技术措施方案(4)质量保证措施(5)安全保证措施(6)材料设备进场计划(7)劳动力进场计划(8)做到有方案再施工4、提供分包商工程施工简历5、提供分包商施工组织体系简况6、按合同规定做好分包工程保险等事宜(二)分包工程的施工质量过程控制要点1、提供本分包工程的质量计划编制书(1)质量计划与目标(2)图纸会审情况及技术交底(3)作业知道书及工序控制点(4)过程参数和产品特性的监控(5)对人、机、料、法、环五大因素的控制79 施工组织设计(6)产品的验收交付2、施工过程的质量监控要点(1)对作业人员进行工艺过程技术交底,并做好交底记录(2)实施有关质量检验的规定,并做好质量检验记录3)对工序间的技术借口实行交接手续4)复验原材料、半成品、成品的产品合格证及质保书5)做好不合格品处理的记录及纠正和预防措施工作6)加强产品保护和施工现场落手清工作7)接受业主和监理单位的指导8)认真做好本分包工程的验收交付9)接合同规定做好本分包工程的回访保修工作10)重大质量事故应及时向业主报告,并作出事故分析调查及处理善后事宜(三)分包工程的进度控制要点(1)编制本分包工程总进度计划1)制定施工方案,明确施工方法的确定,施工机械的选择,施工顺序的安排和流水施工顺序2)编制施工项目进度计划,以保证项目施工的均衡进行3)编制资源供应计划,包括物料供应计划、机械设备的进场计划、劳务计划4)进行图纸深化(2)做好协调照管工作1)参加有关分包工作协调会议,积极参与总工期的协调2)及时根据业主工作指令作出进度的调整计划3)在进度上有重大提前及延误应及时同业主报告4)分包在施工过程中向总包提出的建议、要求,总包及时解决(3)工程进度款的收取按合同规定在业主的监督下由总承包予以签证,所有指定分包商的中期付款或结算款均经总包部确认,并按有关程序予以执行(四)有关安全、消防、现场标准化管理等工作(1)遵守各种安全生产规程与规定1)签订本分包工程的安全协议书79 施工组织设计2)完善和健全安全管理各种台帐,强化安全管理软件资料工作3)开展安全教育工作,做好分部分项工程技术安全交底工作4)特殊工种必须持证上岗5)接收总包的安全监控,参与工地的安全检查工作,并落实整改事宜6)重大伤亡事故发生应及时向业主报告(2)做好消防与治安管理工作1)开展消防与治安的教育工作2)配合总包做好治安管理工作3)严格执行动火审批制度(3)做好现场标准化管理工作1)按总包指令做好场容场貌管理工作,建筑材料设备划区域整齐堆放,施工区域内工完料尽场地清2)遵守文明施工的有关规定,维护安全防护设施的完好3)保持工地卫生文明,努力做好宿舍卫生工作三、对专业分包单位的技术管理(一)安装专业项目经理部由参加过类似工程和大型公共工程施工的各专业技术人员进行对口管理、检查、指导工作。(二)精装修专业项目经理部由参加过类似工程施工管理的专业设计、施工技术人员,从装饰总体效果图设计、施工节点图设计、地面、吊顶块料面层的分块设计等进行顾问管理,并进行施工过程控制,齐心协力确保装饰工程的最终效果。四、对专业分包单位的质量管理(一)质量保证79 施工组织设计公司为QES管理体系认证单位。分包单位应按照项目经理部的要求执行QES标准、质量保证手册、程序文件,进行过程控制,进行标准化管理。严格执行国家现行规范以及本工程涉及的行业和地方现行规范、规程。分包专业编制的质量计划、创优措施必须与总包的质量目标吻合。(二)图纸自审、会审由于本工程建设规模大,质量要求高,结构复杂、专业多。按我们以前的有效办法,在设计院进行设计交底、图纸会审前,由总包单位组织各有关专业进行专业图纸自审,解决各专业间的设计矛盾问题,找出各专业配合的主要矛盾和难点。(三)配合关系图表由项目经理部组织各分包单位,根据设计要求制定专业配合图表,提出主要配合事项,提交有关业专进行配合,使配合工作做到胸中有数,有序进行。(四)施工方案分包单位要按照合同要求,编制详细的分包工程施工方案,经审批后严格组织实施。(五)关键项目质量控制对关键特殊项目的施工过程项目经理部进行专检,分包专业在本工序自检后,填写《要求质量检测通知单》报项目经理部,经项目经理部和监理检查同意后,方可进行下道施工。(六)技术档案管理专业分包单位必须有健全的质量检查制度,配有专(兼)职质检员、资料员。根据施工进度,及时、同步做好各项技术资料的收集、整理工作,并及时报经理部汇总归档。经理部专职资料员不定期对分包进行检查,对资料不全、不符合要求的分包商将及时采取措施纠正,确保资料及时、准确、完整归档。79 施工组织设计五、对专业分包单位的安全文明施工管理(一)安全文明施工目标专业分包单位的安全文明施工目标按照经理部的管理目标执行。(二)平面管理施工现场平面管理,分包商必须服从项目经理部的管理。项目经理部随施工进度和主次工序进行动态管理,施工前,分包的施工平面布置、用电、用水计划,必须报项目经理部审批后方可实施。项目经理部负责协调各分包施工中的道路、场地、用电、用水、机械、测量、脚手架的使用问题。(三)文明施工责任区项目经理部根据施工的进展,实行动态责任区制度,以主导施工专业为主划分责任区范围,主导施工专业负责责任区的文明施工,使文明施工责任明确,责任到人。(四)成品保护施工前分包专业应制定各自的专项成品保护措施,对成品、半成品实行分层、分段交接制度。项目经理部组织各分包共同成立成品保护“执法队”检查落实成品保护措施,处罚违章者。在分包工程完工后,经理部及时对预留洞进行填补、修复工作。79